Resolved
Report to be noted. That the Annual Governance Statement 2019/20, set out in appendix 1, be approved and commended to the Leader and Chief Operating Officer for signature.
Audit & Governance Committee noted this item on Tuesday 28 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Report to be noted. That the Annual Governance Statement 2019/20, set out in appendix 1, be approved and commended to the Leader and Chief Operating Officer for signature.
INTERNAL AUDIT SERVICE ANNUAL REPORT 2019-2020
Jacqui Pendleton Internal Audit Manager West Lancashire Borough Council July 2020 Index
Page 1. Executive Summary 3-4
2. Introduction 5
3. Internal Audit Activity 2019/20 6-9
4. Internal Audit Developments 9 - 10
5. Annual Governance Statement 10
6. Internal Audit Manager's Overall Opinion 11
Page 2 of 11 1. Executive Summary 1.1 The Internal Audit Manager is obliged, under the Public Sector Internal Audit Standards (PSIAS), to provide an annual report summarising the work undertaken by internal audit during the financial year just closed, and to provide an overall opinion on West Lancashire Borough Council's internal control environment.
1.2In respect of 2019/20, 21 assurance audits were completed, 15 of which recorded an audit opinion and a further 6 with no opinion which have been taken into account. The overall audit opinions given in the assurance audit reports can be summarised as:
Assurance Opinion Assessment of Internal Control Number Substantial Assurance Level of Assurance = High 5
The controls evaluated are well designed, appropriate in scope and applied consistently and effectively. Any issues identified are minor in nature and should not prevent objectives being achieved.
There is a low risk of fraud, negligence, loss or damage to reputation. Moderate Assurance Level of Assurance = Medium 7
The controls evaluated are generally well designed, appropriate in scope and applied in the main consistently and effectively, but some weaknesses have been identified that require management attention. These issues increase the risk that some objectives may not be fully achieved.
There is a medium/low risk of fraud, negligence, loss or damage to reputation. Limited Assurance Level of Assurance = Low 1
Some controls evaluated are generally well designed, appropriate in scope and applied consistently and effectively. However, issues of poor design, gaps in coverage or inconsistent or ineffective implementation have been identified that require immediate management attention. The issues if unresolved, mean that objectives may not be achieved.
Page 3 of 11 There is a medium risk of fraud, negligence, loss or damage to reputation. No Assurance Level of Assurance = None 2
Expected controls are absent, or where evaluated are flawed in design, scope or application leaving the system open to error or abuse. The auditor is unable to form a view as to whether objectives will be achieved.
There is a high risk of fraud, negligence, loss or damage to reputation.
1.3Based upon the work undertaken by Internal Audit in respect of 2019/20, and the implications of the Covid-19 epidemic on the Councils internal control framework, the opinion of the Internal Audit Manager on the overall adequacy and effectiveness of the organisation’s framework of governance, risk management and control is moderate assurance.
Page 4 of 11 2. Introduction
2.1In accordance with the Accounts and Audit Regulations 2015, the Council must ensure that it provides adequate and effective internal audit arrangements in respect of its accounting records and systems of internal control, and that it conducts an annual review of the effectiveness of these. In addition, these arrangements must be delivered in accordance with the Public Sector Internal Audit Standards (PSIAS), revised in January 2017, and Local Government Application Notes (LGAN), which came into effect on 1 April 2013 and 1 February 2019. 2.2 The work carried out by the Internal Audit Service involves reviewing and reporting on the control environment established by management to: Determine and monitor the achievement of the Council's objectives Identify, assess and appropriately manage the risks to achieving the Council's objectives Facilitate policy and decision making Ensure economical, effective and efficient use of resources Ensure compliance with established policies, procedures, laws and regulations Safeguard the Authority's assets and special interests.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Annual ReportReport | 438 KB | DownloadRead as text |
Follow Audit & Governance Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of previous meetingThat the minutes of the meeting held on Wednesday, 18 February 2026 be agreed as a correct record and signed by the C... | Agreed | Open |
| 10 Jun 2026 | Annual Governance Statement 2025/26A. That the Annual Governance Statement 2025/26, set out in Appendix 1, be approved and commended to the Leader and C... | Approved | Open |
| 10 Jun 2026 | External Audit PlanThat the on the Statement of Accounts for 2025-26 from Grant Thornton be noted. | Noted | Open |
| 10 Jun 2026 | External Audit RecommendationsA. That the status and progress on external audit recommendations and value for money assessment be noted. B. That me... | Noted | Open |
| 10 Jun 2026 | Internal Audit RecommendationsThat the status of outstanding internal audit recommendations be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.