That the use of £103,860 of S106 monies from planning permission 2009/1052/FUL on the improved provision for cycling and walking access between Ormskirk town centre and Edge Hill University on Ruff Lane and St Helens Road and the junction of these roads with Park Road as outlined in the report, be approved.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek authorisation to spend Section 106 funds on the next phase of the Edge Hill Cycle Link.
2.0RECOMMENDATIONS TO CABINET
2.1To agree the use of £103,860 of S106 monies from planning permission 2009/1052/FUL on the improved provision for cycling and walking access between Ormskirk town centre and Edge Hill University on Ruff Lane and St Helens Road and the junction of these roads with Park Road as outlined in this report.
3.0BACKGROUND & PROPOSALS
3.1The Edge Hill Cycle Link has been a long-held aspiration of this Council and Lancashire County Council (LCC) for some years now, with the recently completed improvements to the path between the rail and bus station in Ormskirk providing the first phase in delivering the cycle link. Officers have been working with LCC colleagues to work-up plans for the remainder of the cycle link, which will travel across the bus station site, along St Helens Road and then along Ruff Lane, and plans for the next phase of delivery have now been prepared and can be delivered by LCC subject to agreement of this Council to spend a further tranche of S106 monies on the next phase. 3.2 The next phase will involve changes to the junction of St Helens Road / Ruff Lane / Park Road to introduce improved footpaths, dedicated cycle lanes and a dedicated phase on the traffic signals to allow bicycles to cross from Ruff Lane to the western (north-bound) side of St Helens Road. This will involve making Ruff Lane one-way between Knowsley Road and St Helens Road for vehicles and so preventing access for vehicles onto Ruff Lane from the junction of St Helens Road / Ruff Lane / Park Road. The Plan at Appendix A shows the improvements proposed.
3.3This phase of the cycle link will cost in the region of £240,000 and can be delivered by LCC this financial year (i.e. by 31st March 2021).
3.4Overall, the Edge Hill Cycle Link is being funded by a combination of S106 monies secured from developments at Edge Hill University (which must be used to improve accessibility to the university campus by means other than the private car) and LCC Local Transport Plan funding. It is proposed that this phase be funded through £103,860 of S106 monies from planning permission 2009/1052/FUL, with the remaining costs being met from LCC's Local Transport Plan funding.
3.5The S106 funding has been earmarked for use on the Edge Hill Cycle Link for some time, but given the passage of time since the funding was first earmarked, and the slightly different proposals being put forward now, the recommendation at paragraph 2.1 above seeks Cabinet's approval of the use of the Section 106 funds to be put towards this phase of the Edge Hill Cycle Link and so improve connectivity to the university campus by walking and cycling.
4.0SUSTAINABILITY IMPLICATIONS
4.1The promotion of walking and cycling will have positive sustainability implications for Ormskirk and West Lancashire, encouraging travel to the Edge Hill University campus by means other than the private car, will reduce congestion, improve air quality and encourage a more active lifestyle for those travelling to/from the University.
5.0FINANCIAL AND RESOURCE IMPLICATIONS
5.1The Edge Hill Cycle Link proposals will be funded through a combination of Section 106 funding (as per the recommendation at 2.1 above) and Local Transport Plan funding from LCC.
6.0RISK ASSESSMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.