Resolved
That the content of the Timetable for Local Plan Preparation report and the September 2021 Local Development Scheme within Appendix A be supported by the Committee
Executive Overview & Scrutiny Committee decided this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the content of the Timetable for Local Plan Preparation report and the September 2021 Local Development Scheme within Appendix A be supported by the Committee
1.1To consider an updated timetable and Local Development Scheme for the preparation of a new local plan for West Lancashire, in light of the delays caused by the Covid-19 pandemic, changes in staffing in the Growth & Development Service and anticipated changes to what may be required of local plans under the proposals in the recent Planning White Paper.
2.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE
2.1That the Committee consider the content of the Timetable for Local Plan Preparation report and the September 2021 Local Development Scheme within Appendix A, and that the agreed comments of Executive Overview and Scrutiny Committee be passed to Cabinet for their consideration.
3.0RECOMMENDATION TO CABINET
3.1That the updated September 2021 Local Development Scheme within Appendix A be approved. 4.0 BACKGROUND
4.1The Local Development Scheme (LDS) is a timetable for the preparation of the Local Plan and other important planning policy documents. The most recent LDS for West Lancashire was approved by Cabinet in March 2021.
4.2The proposed updated September 2021 LDS provided at Appendix A includes an amended timetable for the preparation of the new West Lancashire Local Plan 2023-2040, as follows:
Issues & Options Consultation November 2021 – January 2022 ('Regulation 18')
Development Requirements & Site November – December 2022 Allocations Consultation
Publication / Pre-Submission October – December 2023 ('Regulation 19')
Submission to Planning Inspectorate January 2024
Examination in Public (including January – December 2024 Hearings)
Adoption December 2024
'Regulations' refer to the Town and Country Planning (Local Planning) (England) Regulations 2012 (as amended).
4.3Overall, this represents a delay in the adoption of the new Local Plan (subject to how long the Local Plan Examination may take, which is not within the Council's control), due to the delayed Regulation 18 Consultation stage, the introduction of an additional stage of public consultation in autumn 2022 on development requirements and site allocations, and allowing more time for the preparation of the Publication / Pre-Submission Local Plan document, given the anticipated changes to national guidance on Local Plan preparation following the Planning for the Future White Paper (August 2020).
5.0SUSTAINABILITY IMPLICATIONS
5.1There are no direct implications for sustainability from the recommendations in this report.
6.0FINANCIAL AND RESOURCE IMPLICATIONS
6.1The new Local Plan will be produced by the Council’s Strategic Planning, Regeneration & Implementation Team. However, a document as wide-ranging as a Local Plan will inevitably involve input from various parts of the Council (as well as external stakeholders and partners).
6.2The costs of preparing the Local Plan will be covered by existing general revenue budgets together with the previously agreed contribution from Council Reserves for the costs of additional evidence studies and the Examination of the Local Plan.
6.3For further detail, please see chapter 4 of the LDS at Appendix A, which covers the issue of resources for the preparation of the Local Plan.
7.0RISK ASSESSMENT
7.1Please see chapter 5 of the LDS at Appendix A, which covers the issue of risk assessment for the Local Plan and sets out a number of possible risks and mitigation measures. This now includes a risk assessment associated with the impact any further Covid-19 (or similar) lockdowns may have on Local Plan preparation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LDS-LP Timetable_Cabinet_App A_LDS-Sept 2021Appendix | 783 KB | Download |
PDF |
Timetable for Local Plan PreparationReport | 223 KB | DownloadRead as text |
Follow Executive Overview & Scrutiny Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2024 | MINUTESThat the Minutes of the meeting held on 25 January 2024 be received as a correct record and signed by the Chairman. (... | Decided | Open |
| 14 Mar 2024 | Relevant minutes of cabinetThat the Minutes of Cabinet held on 6 February 2024 be noted. | Noted | Open |
| 14 Mar 2024 | Draft homelessness & rough sleepers strategy 2024-29That the report be considered and noted. | Noted | Open |
| 14 Mar 2024 | Corporate performance reporting: 2024/25That the Committee considered and noted the draft delivery plan for the Council Priorities as attached at Appendix 1. | Noted | Open |
| 14 Mar 2024 | Quarterly council performance delivery: q3 2023/24That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted. (N... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.