Independent Review of Tawd Valley Developments Ltd
AgreedExecutive2 papers
Executive Overview & Scrutiny Committee agreed this item on Thursday 23 September 2021. Below is the council's own wording, with the papers it was decided on.
That the following agreed comment of Executive Overview & Scrutiny Committee be forwarded to the Chief Operating Officer and relevant Portfolio Holder for their consideration. "That Members receive the updated and current financial position on the approved Business Plan at the time the report goes to Council'. (Note: Councillor D Westley asked for it to be recorded that he had asked for a copy of the original Grant Application provided by Central Government to assist in establishing Tawd Valley Developments Limited, and the terms upon which the Grant was agreed. He advised that he was informed that neither of the documents can be found).
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek authority to instruct Local Partnerships to undertake an independent review of Tawd Valley Developments Limited as outlined in the scope in section 6.3 of this report.
2.0RECOMMENDATIONS FOR CABINET
2.1That authority is granted to the Chief Operating Officer in consultation with the portfolio holder to take all necessary steps to progress the independent review as outlined in the scope in section 6.3 and present their findings to Council at the earliest opportunity.
2.2To approve a maximum investment of £10,000 to undertake the review
2.3That the Chief Operating Officer be given delegated authority in consultation with the relevant Portfolio Holder to consider any agreed comments from Executive Overview & Scrutiny Committee.
2.4That Call In is not appropriate for this item as the Report is being submitted to a special meeting of the Executive Overview & Scrutiny Committee on the 23rd September 2021 3.0 RECOMMENDATIONS FOR EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE
3.1Consideration be given to the Report and any agreed comments be forwarded to the Chief Operating Officer in consultation with the relevant Portfolio Holder for consideration.
Background
4.1Tawd Valley Development Company Limited (TVDL) is a wholly Council owned development company established in 2018. The Development Company was created in order to enter the development market in West Lancashire, to acquire sites and deliver new homes for the residents of the borough, and to also consider commercial developments and developments outside the Borough.
4.2The Development Company was the chosen option of the Council as:
the initial financial viability assessments indicated that site development could deliver a sustainable and profitable enterprise the Council received the Grant Funding (780k DCLG) to facilitate the formation and site preparation of a Development Company to deliver the Development Objectives the Development Company created a separate legal entity which could attract further grant funding into the borough the Development Company would be controlled by the Council and would allow the Council to prioritise its Development Objectives 4.3 The agreed development objectives of TVD are:
Generate a financial return for the Council through development of profitable services/activities, recognising that this will take time to be realised. Capture any financial benefits and tax efficiencies of dedicated delivery vehicles which are Council controlled but can benefit from agile operating arrangements. Provide an income from the new vehicle that is substantial and the new ways of working so transformational that the cost of planning, due diligence advice and setting up and operating the vehicle outweigh the status quo. Create profitable, complementary and transparent relationships with landowners, developers and investors which deliver financial and regeneration benefits. Secure additional private and Government investment into the Borough, creating a focus on delivery and providing a mechanism to build new homes for sale and rent, regeneration and commercial and industrial schemes to the Council. Maximise appropriate development, accelerate growth and take appropriate risks for the Council by providing dedicated delivery arrangements and property and commercial expertise. 4.4 A series of legal agreements govern the relationship between TVDL and the Council. TVDL has an independent Board consisting of 4 Directors, 2 Council Officers and two independents appointed through a selection process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive Overview & Scrutiny Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.