Resolved
That the minutes of the last meeting held on the 2 November 2022 be received as a correct record.
Leisure Procurement Cabinet Working Group decided this item on Wednesday 11 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the last meeting held on the 2 November 2022 be received as a correct record.
LEISURE PROCUREMENT COMMITTEE HELD: Wednesday, 2 November 2022 Start: 7.00 p.m. Finish: 8.28 p.m.
PRESENT:
Councillor: D Westley (Chairman) C Coughlan (Vice-Chairman)
Councillors: Y Gagen A Owens J Howard
In Attendance: J Foley, Alliance Leisure P Curtis, Hadron Consulting
Officers: Simon Kirby, Head of Wellbeing and Leisure Services Tom Dickinson, Principal Solicitor Rebecca Connick, Leisure Procurement Project Co-ordinator Jennifer Lunn, Senior Legal Executive/Assistant Solicitor Jill Ryan, Principal Democratic Services Officer
1 APOLOGIES
There were no apologies for absence received.
2 MEMBERSHIP OF THE COMMITTEE
In accordance with Regulatory Procedure Rule No.4, the Committee noted the termination of Councillor R Bailey and the appointment of Councillor J Howard for this meeting only, thereby giving effect to the wishes of the Political Groups.
3 URGENT BUSINESS
There were no items of urgent business received.
4 DECLARATIONS OF INTEREST
There were no Declarations of Interest received.
5 TERMS OF REFERENCE
RESOLVED: That Council approves the following Terms of Reference of the Committee:
Functions
(a) To consider the opportunities available for the procurement of a new partnership arrangement for the provision of leisure services, which would include significant capital investment for built sports provision, as outline in LEISURE PROCUREMENT COMMITTEE HELD: Wednesday, 2 November 2022
the Key Action Plan of the Council's Leisure Strategy.
(b) To report recommendations to Cabinet (and Council when required).
Delegations
None. The Committee will be consulted on reports prior to being submitted to Cabinet. As such, these reports will not be routinely submitted to Executive Overview & Scrutiny Committee, unless a specific request is made.
6 UPDATE OF NEW FACILITY BUILDS
The Head of Wellbeing and Leisure introduced James Foley from Alliance Leisure and Peter Curtis from Hadron Consulting who gave a joint presentation on the new facility builds in Ormskirk and Skelmersdale.
The presentation outlined the progress made on both schemes and an opportunity was given to members of the Committee to ask questions.
Comments and questions were raised in respect of the following:-
The financial information received, and the important fact that the projects would be driven by affordability. The use of Levelling up Fund monies. It was felt that consultation was important which would give people renewed faith that the development is ongoing. The Youth Zone in Skelmersdale and the possibility of one in the Ormskirk build. The progress made on the new builds was welcomed and Members were pleased with progress made. The effect that rising energy costs could have on the affordability of heating swimming pools. It was felt that this was an important factor. Delivering not just aesthetical buildings but environmentally friendly buildings was important. The layout and design of the two new Leisure Centres was welcomed. Burscough Sports Centre, more details were requested on this scheme, and it was reported that Members would be receiving a more detailed update on the Burscough Sports Centre in the future.
RESOLVED: A. That the contents of the presentation be noted.
B. That James Foley from Alliance Leisure and Peter Curtis from Hadron Consulting be thanked for their informative presentation.
(Note: James Foley and Peter Curtis left the meeting at this point and were not present for the remainder of the meeting). LEISURE PROCUREMENT COMMITTEE HELD: Wednesday, 2 November 2022
7 UPDATE ON SPORT AND LEISURE MANAGEMENT TENDER
The Head of Wellbeing and Place gave an update to the Committee on the sport and leisure management tender.
He informed the Committee that a report would be brought back to the next meeting of this Committee.
RESOLVED: That the update be noted,
8 DATE OF NEXT MEETING
RESOLVED: That the date of the next meeting would be the 29 November 2022 as scheduled.
9 EXCLUSION OF PRESS AND PUBLIC
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 201 KB | DownloadRead as text |
Follow Leisure Procurement Cabinet Working Group at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jan 2023 | Date of next meetingThat the date of the next meeting as scheduled was the 15 February 2023 at 7.00pm. | Decided | Open |
| 11 Jan 2023 | Exclusion of press and publicThat under Section100A(4) of the Local Government Act 1972, the public be excluded from the meeting during considerat... | Decided | Open |
| 11 Jan 2023 | Update on Beacon ParkThat the update be noted. | Noted | Open |
| 11 Jan 2023 | Update on New facilities projectA. That the update be noted B. That Peter Curtis and Seb Rowe be thanked for a very informative update. | Noted | Open |
| 2 Nov 2022 | Terms of referenceThat Council approves the following Terms of Reference of the Committee: Functions (a) To consider the opportunities ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.