Resolved
That Members note the report and WLBC’s positive performance against national planning standards, with an ongoing commitment to quarterly updates on decision speed and quality to monitor and maintain this trajectory.
Planning Committee noted this item on Thursday 5 December 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That Members note the report and WLBC’s positive performance against national planning standards, with an ongoing commitment to quarterly updates on decision speed and quality to monitor and maintain this trajectory.
1.1This report provides an overview of West Lancashire Borough Council’s (WLBC) performance against government criteria on planning decision speed and quality. It reviews WLBC’s performance over the past two years and includes the latest quarterly results, with a commitment to provide quarterly updates going forward.
2.1The Government monitors the performance of planning authorities on two key metrics: speed and quality of decisions, specifically for major applications (e.g., developments of 10+ houses or over 1,000 square meters of commercial space) and non-major applications.
2.2Under Section 62A of the Town and Country Planning Act 1990, planning authorities may be designated as underperforming if they fall below specific thresholds, allowing applicants to submit applications directly to the Secretary of State through the Planning Inspectorate. The thresholds for designation are:
Major Development: Fewer than 60% of decisions made within the statutory determination period (or as extended with the applicant’s agreement).
Non-Major Development: Fewer than 70% of decisions made within the statutory determination period (or as extended with the applicant’s agreement).
Appeal Quality Threshold: Authorities with over 10% of decisions overturned at appeal for either category during the two-year assessment period may also face designation. 2.3 The assessment period covers the two years up to the latest quarter for which data is available, allowing time for appeals to be concluded. This report includes data up to the end of the last available quarter in 2023.
WLBC Performance Over Two Years and Latest Quarter
2.4To ensure that Members are regularly updated, this report covers both the two- year assessment period and the most recent quarterly results.
Performance over Two Years
2.5WLBC’s major applications performance between October 2022-September 2024 stands at 84%, (36 of 43 decisions within the statutory determination period) reflecting a performance well above the 60% designation threshold. For non- major applications, the performance figure was 81% (1,066 of 1,319 decisions within the statutory determination period) which reflects a performance above the 70% designation threshold.
2.6In terms of quality of decisions on major applications, WLBC has maintained a strong record, with minimal appeals overturned. Only one major appeal was overturned and of 43 decisions, resulting in a 2.3% appeal overturn rate (1 of 43), This places WLBC among the higher-performing authorities nationally, and in a position achieved by fewer than half of planning authorities in England.
2.7For non-major applications, WLBC has maintained a low appeal overturn rate, with 1.7% (22 of 1,319 applications) overturned, indicating the service's robust decision-making. This figure is well within government thresholds and represents one of the stronger performances in the country. Overall, 69% of all appeals received were dismissed.
Latest Quarter Performance (Q2 – July-September 2024)
2.8WLBC’s major applications for the latest quarter was 100%, reflecting a positive trajectory well about the 60% threshold. Although the rolling 8-quarter average stands at 75%, this recent quarter shows improvement, supported by enhanced internal processes and ensuring appropriate staff resourcing.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Development Management Performance ReportReport | 137 KB | DownloadRead as text |
Follow Planning Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | MINUTESThat the minutes of the meeting held on the 30 th July 2026 be approved as a correct record and signed by the Chairpe... | Approved | Open |
| 3 Sep 2026 | 2025/0548/FUL - Burscough Methodist Church, Orrell Lane, Burscough, L40 0SGAGREED: That planning application 2025/0548/FUL be deferred until a sufficient number of eligible Members are present... | Agreed | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 18 th June 2026 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 30 Jul 2026 | 2025/1054/COU - Former Forest View NurseriesThat planning permission is granted subject to conditions set out on pages 65 - 66 of the Public Reports Pack for the... | Decided | Open |
| 30 Jul 2026 | 2026/0229/FUL - Land West of Red Cat LaneThat planning application 2026/0229/FUL be granted subject to a deed of variation to the original Section 106 Agreeme... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.