PLANNING APPLICATION 2024/1028/FUL - Fleetwood Farm, 12 CHURCH ROAD, BANKS

Deferred Planning 2 papers

AI summaryWest Lancashire Planning Committee defers Fleetwood Farm 20-dwelling application in Banks for further investigation of heritage and alternative site uses.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredHeritage matters and alternative site uses
MoneyNot stated
What happens nextFurther investigation neededHeritage and alternative uses to be examined
Who it affectsBanks village residentsFleetwood Farm, 12 Church Road, Banks

What was decided

Planning application 2024/1028/FUL was deferred to allow further investigation into heritage matters and alternative usage of the site, despite an officer recommendation to grant permission subject to conditions. Report 2.1

Why

Officers had recommended approval with conditions, concluding the sequential and exception tests were passed and that the tilted balance applied because the council's housing land supply is 1.86 years. Report 2.1, 10.19, 10.22, 10.27

Fleetwood Farmhouse and its attached barn are non-designated heritage assets on the List of Locally Important Buildings, and their total demolition would cause a low level of harm contrary to Local Plan Policy EN4. Report 1.2, P32, P75

More than 250 letters of objection and a 1,077-signature petition were received, with North Meols Parish Council, the local MP and a ward councillor calling for a mixed-use retail or community scheme instead of housing. Report P102, 7.6, 7.1, 7.3, 7.4

What happens next

Further investigation into heritage matters at the site, including the locally listed farmhouse and barn, before the application returns to committee. Report 1.2

Further consideration of alternative uses of the site, such as retail or mixed-use development similar to Mark Square in Tarleton. Report P84, P90, P107

Options considered

  • Rejected: Grant planning permission subject to the conditions in paragraph 12 of the report (officer recommendation).. Committee chose to defer pending further investigation of heritage and alternative uses Report 2.1
  • Chosen: Defer the application to allow further investigation of heritage matters and alternative site uses.. Concern about the total loss of a non-designated heritage asset and strong public calls for a mixed-use village centre instead of housing Report 1.2, P32, P102, 7.6

Implications

  • Other: Loss of a non-designated heritage asset: total demolition of Fleetwood Farmhouse and attached barn would cause a low level of harm and conflict with Local Plan Policy EN4. Report 1.2, P32, P75
  • Legal: Tilted balance applied because the council cannot demonstrate a five-year housing land supply (1.86 years), engaging the presumption in favour of sustainable development in NPPF paragraph 11. Report 10.19
  • Risk: The site lies entirely within Flood Zone 3a; the Environment Agency accepted the proposal subject to finished floor levels at least 300mm above ground and implementation of the flood risk mitigation measures. Report 10.16, P47, P51
  • Equalities: Strong local opposition focused on the lack of community infrastructure, retail and services for an ageing village population, with 26% of residents aged 65 and over. Report P102, 7.6, P104, P106
  • Climate: Biodiversity Net Gain: with offsite compensation, the development is capable of delivering the mandatory minimum 10% net gain, subject to a Landscape Planting and Maintenance Plan covering 30 years. Report P69, P70

Who and where

  • Residents of Banks village (over 250 objectors and 1,077 petition signatories) Report P102, 7.6
  • North Meols Parish Council Report 7.1, P79
  • The local MP for the area Report 7.4
  • A ward councillor who objected to the application Report 7.3
  • The applicant (a provider of affordable housing) Report 4.1, 10.5, 10.28

Timeline

  • 02/12/24: Application and initial supporting documents submitted Report P127
  • 14/02/25: Growth Lancashire heritage consultation response received Report 6.6
  • 27/05/25: MEAS ecology consultation response with biodiversity net gain concerns Report 6.9, P63
  • 26/08/25: Natural England raises no objection Report 6.10, P73
  • 10/09/25: Sequential Test Addendum submitted by the applicant Report P138
  • 24/10/25: LCC Historic Environment Team recommends a building record prior to demolition Report 6.11, P75
  • 30/10/25: MEAS final response accepts the Biodiversity Net Gain submission Report 6.9, P69, P70
  • 2025-11-20: Planning Committee defers the application for further investigation

Plain English for the jargon

  • NDHA: Non-Designated Heritage Asset, a building or site of local heritage significance that is not on the national statutory list.
  • NPPF: National Planning Policy Framework, the government's main planning policy document.
  • Sequential test: A planning test requiring development in areas at risk of flooding to be directed to lower-risk sites first.
  • Exception test: A planning test applied where the sequential test cannot be passed; the development must provide wider sustainability benefits and be safe for its lifetime.
  • Tilted balance: The presumption in favour of sustainable development in NPPF paragraph 11, applied when the council cannot show a five-year housing land supply.
  • Biodiversity Net Gain (BNG): A requirement that new development delivers an overall increase in natural habitat value, with a statutory minimum of 10%.
  • S278 agreement: An agreement under Section 278 of the Highways Act 1980 allowing a developer to carry out works on the public highway.
  • EPSML: European Protected Species Mitigation Licence, required before disturbing protected species such as bats.
  • Flood Zone 3a: An area with a high probability of river or sea flooding (1 in 100 or greater annual chance).
  • MEAS: Merseyside Environmental Advisory Service, a shared service that advises councils on ecology, landscape and related matters.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item124a

Resolved

That planning application 2024/1028/FUL be deferred to allow for further investigation regarding matters of heritage, and alternative usage of the site.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

1.1To advise Planning Committee on an application which seeks planning permission for the demolition of existing structures on the site and the erection of a housing scheme of 20 dwellings comprised of 8 dwelling houses, 4 bungalows and 8 cottage style apartments, with access, car parking, landscaping and other associated works.

2.0RECOMMENDATION TO PLANNING COMMITTEE

2.1That planning permission is GRANTED subject to conditions set out at paragraph 12. 3.0 THE SITE

3.1The application site is located to the south of Church Road in Banks and comprises a farmhouse and associated farm buildings. The site extends to approx. 0.5ha and is surrounded on all sides by a mix of built development including a supermarket to the west and a row of local shops to the north.

1.2The buildings have become disused over time however the main building Fleetwood Farmhouse, together with its attached barn, is on the List Of Locally Important Buildings and is therefore classified as a non-designated heritage asset.

1.3The site lies within the settlement area of Banks and partially within the designated large village centre.

4.0PROPOSAL

4.1The application seeks planning permission for the demolition of existing structures on the site and the erection of a housing scheme of 20 dwellings comprised of 8 dwelling houses, 4 bungalows and 8 cottage style apartments, with access, car parking, landscaping and other associated works.

5.0PREVIOUS RELEVANT DECISIONS

5.1None

6.0OBSERVATION OF CONSULTEES

6.1Lancashire Fire and Rescue Service (09/01/25)

Note the application and provide advice in respect of Building Regulations requirements

6.2WLBC Environmental Protection Officer (09/01/25)

The application site is in close proximity to road traffic and a nearby Co-op convenience store and its associated refrigeration plant, all of which have the potential for an increased noise climate with the potential to impact the amenity of the proposed dwellings.

A Noise Impact Assessment report has been submitted in support of the application (Reference: 51-241-R1-3, dated November 24). The report determined that certain facades within the development will be subjected to predicted noise levels ranging from 40 dB and up to 57 dB in the worst affected external amenity areas and certain external amenity areas will exceed the upper criterion of 55 dB. In mitigation against this, acoustic barriers have been recommended to reduce noise levels and a proposed scheme of higher specification glazing to control internal noise levels have been recommended across the development.

Conditions are recommended in respect of Noise Mitigation and Construction Management Plan.

6.3WLBC Environmental Protection Officer - Land Contamination (27/01/25) The application is supported by the reports which have been carried out largely in accordance with industry best practice and British Standards. Elevated levels of some organic contaminated was identified in Made Ground near to farm buildings with lead in the area of TP1.

Although ground gas monitoring was carried out, the results cannot be relied on because of high water levels in the boreholes. Normal CS3 gas preclusion measures would be required however, remedial measures are proposed that should take the source of ground gas into account.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024_1028_FULAppendix 1 145 KB Download
PDF
PLANNING APPLICATION 2024/1028/FUL: Fleetwood Farm, 12 CHURCH ROAD, BANKSReport 309 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 24 attended
GO
Councillor Gaynar OwenChairperson, present
AF
Councillor Andy FowlerVice-Chairperson, present
JA
Councillor Judy AbbottCommittee Member, present
TD
Councillor Terence DevineCommittee Member, present
PH
Councillor Paul HoganCommittee Member, present
SP
Councillor Suresh PatelCommittee Member, present
EP
Councillor Edward PopeCommittee Member, present
LM
Councillor Linda Marjorie WebsterCommittee Member, apologies, sent representative
MM
Councillor Mrs Marilyn WestleyCommittee Member, apologies, sent representative
MJ
Councillor Mrs Joan WitterCommittee Member, present
NE
Neil EcclesCouncil Staff, expected
PC
Paul CharlsonOfficer, expected

All 24 on the meeting page

On this subject at West Lancashire

Search all
  1. PLANNING APPLICATION 2024/1028/FUL - Fleetwood Farm, 12 CHURCH ROAD, BANKSThis decision
  2. PLANNING APPLICATION REF: 2025/0629/FUL - West Lancashire Light Railway, Station Road, Hesketh BankDeferred
  3. PLANNING APPLICATION REF: 2024/0168/FUL - Abbey Farm Caravan Park, Abbey Lane, Lathom, Ormskirk, Lancashire, L40 5TXDeferred
  4. PLANNING APPLICATION REF: 2025/0587/FUL - Wayfarer, 1-5 Alder Lane, ParboldApproved
  5. PLANNING APPLICATION REF: 2023/0787/OUT - Land To The East Of Boundary Lane, Hesketh Bank, PR4 6AJRefused
  6. PLANNING APPLICATION REF: 2024/0020/FUL - Eden Tearoom And Galleries, Course Lane, Newburgh, Wigan, Lancashire, WN8 7UBDecided

More from West Lancashire Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 MINUTESThat the minutes of the meeting held on the 30 th July 2026 be approved as a correct record and signed by the Chairpe... Approved Open
3 Sep 2026 2025/0548/FUL - Burscough Methodist Church, Orrell Lane, Burscough, L40 0SGAGREED: That planning application 2025/0548/FUL be deferred until a sufficient number of eligible Members are present... Agreed Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 18 th June 2026 be approved as a correct record and signed by the Chairman. Approved Open
30 Jul 2026 2025/1054/COU - Former Forest View NurseriesThat planning permission is granted subject to conditions set out on pages 65 - 66 of the Public Reports Pack for the... Decided Open
30 Jul 2026 2026/0229/FUL - Land West of Red Cat LaneThat planning application 2026/0229/FUL be granted subject to a deed of variation to the original Section 106 Agreeme... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies