West Lancashire Borough Council
Planning Committee, Thursday 18 June 2026 at 7.00pm

2024/0168/FUL - Abbey Farm Caravan Park, Abbey Lane, Lathom

Approved Planning 2 papers

AI summaryWest Lancashire Planning Committee grants variation of conditions at Abbey Farm Caravan Park, Lathom, requiring a new sewage treatment plant within 2 months to address pollution of Abbey Brook.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVariation of conditions 3-7, removal of condition 8
MoneyNo significant financial or resource implications
What happens nextSewage plant details in 2 monthsTreatment plant and drainage works must be implemented within 2 months of approval
Who it affectsAbbey Farm Caravan Park, Lathom11-hectare site with 177 static and touring caravans

What was decided

Planning permission was granted for the variation of conditions 3, 4, 5, 6 and 7 and the removal of condition 8 of planning permission 2019/0056/FUL at Abbey Farm Caravan Park, Abbey Lane, Lathom. Report 1.1, 2.1

Condition 6 was varied to require submission of full details of a new sewage treatment plant to replace the existing septic tank within 2 months, with implementation within 2 months of approval. Report P26

Condition 7 was varied to require the surface water drainage scheme to be carried out in accordance with approved details within 2 months, to be retained for the lifetime of the development. Report P29

Why

The Environment Agency advised that the existing foul drainage system is causing pollution of Abbey Brook and a new package treatment plant would improve effluent quality, though planning and permitting controls should remain separate. Report 6.4, 6.23

The Arboricultural Officer, Merseyside Environmental Advisory Service, and Principal Drainage Engineer were satisfied that the submitted landscaping, ecological management plan, and drainage details are acceptable. Report 6.1, 6.9, 6.10

The Lancashire County Council Historic Environment Team confirmed that condition 8 on archaeology had served its purpose and could be removed, as previous archaeological work and a 1977 gas pipeline easement document satisfied their concerns. Report 6.7, 6.29, 6.30

What happens next

The applicant must submit full details of a new sewage treatment plant to the Local Planning Authority within 2 months of the decision and implement the approved scheme within 2 months of its approval. Report P26

The approved surface water drainage scheme must be carried out within 2 months of the permission and retained for the lifetime of the development. Report P29

Photographs demonstrating ecological enhancement works (bat boxes, bird boxes, hibernaculum) must be submitted to the Local Planning Authority within 6 months of the date of the permission. Report P118

Options considered

  • Chosen: Grant planning permission with varied conditions 3-7 and removed condition 8. Consultees satisfied; conditions considered enforceable, appropriate, and necessary in planning terms; Environment Agency advice supports new sewage treatment plant approach. Report 2.1, 11.0, 11.2
  • Rejected: Deny the variation and retain all original conditions. Not specifically discussed as an option; revised wording addresses Environment Agency concerns about pollution and statutory consultees withdrew objections. Report 6.4, 6.9, 6.10

Implications

  • Environment and climate: Existing foul drainage discharge from the site is causing pollution of Abbey Brook, a designated Main River. A new modern sewage treatment plant is expected to improve effluent quality. Report 6.4, 6.23, 1.7
  • Legal: Officers advised that Section 73 application cannot revisit the lawfulness of the parent permission or address unrelated alleged breaches; matters outside the scope of conditions 3-8 fall to enforcement powers. Report 6.32, 6.33
  • Equalities: The decision does not have any direct impact on members of the public, employees, elected members or stakeholders; no Equality Impact Assessment required. Report P146
  • Risk: A new or varied Environmental Permit under the Environmental Permitting (England and Wales) Regulations 2016 may be required for the new sewage treatment plant and for activities within 8 metres of Abbey Brook. Report P131, P132
  • Other: The site lies within the Merseyside and Greater Manchester Green Belt; conditions limit total occupancy to 177 caravans and restrict use to holiday purposes only. Report 6.14, P111, P113

Who and where

  • The applicant (operator of Abbey Farm Caravan Park) Report 1.2, 3.1
  • Neighbours and nearby residents, including those at Abbey Cottage and Cross House Report 3.3, 3.4, 6.11
  • Environment Agency, as regulator of the site's Environmental Permit for discharge Report 6.3, 6.4
  • Users of Abbey Brook and the adjacent public footpath Report 6.11, P75

Timeline

  • 06.03.19: Original planning permission 2019/0056/FUL granted for continued holiday use of caravan park with up to 177 caravans. Report 5.6
  • 06.07.20: Condition 8 archaeological works approved under application 2020/0401/CON. Report 5.4
  • 19.03.2026: Application first considered by Planning Committee and deferred for further consideration of drainage condition wording. Report 1.2, 1.3
  • 23.04.2026: Application deferred again at Planning Committee to allow a full written Environment Agency response. Report 1.4
  • Within 2 months of permission: New sewage treatment plant details must be submitted and approved surface water drainage scheme must be carried out. Report P26, P29
  • Within 2 months of sewage plant approval: Approved new sewage treatment plant scheme must be implemented in full. Report P26
  • Within 6 months of permission: Photographs of completed ecological enhancement works (bat boxes, bird boxes, hibernaculum) must be submitted. Report P118

Plain English for the jargon

  • Section 73 application: An application to vary or remove conditions attached to an existing planning permission, without changing the underlying consent.
  • Environmental Permit: A permit issued by the Environment Agency under the Environmental Permitting (England and Wales) Regulations 2016 that regulates discharges to controlled waters such as Abbey Brook.
  • Main River: A watercourse designated by the Environment Agency; works within 8 metres generally require an Environmental Permit.
  • Section 106: Not used in this application; planning obligations under Section 106 of the Town and Country Planning Act 1990 were not raised.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14a

Resolved

That planning permission be granted for the variation of Conditions 3–7 inclusive, and the removal of Condition 8, subject to the amendments set out below: Condition 6: Within 2 months of the date of this permission, full details of a new sewage treatment plant to replace the existing septic tank shall be submitted to, and approved in writing by, the Local Planning Authority. The approved scheme shall be implemented in full within 2 months of its approval. Reason: To ensure compliance with Policy GN3 of the West Lancashire Local Plan 2012–2027 and to minimise the risk of pollution. Condition 7: Within 2 months of the date of this permission, the surface water drainage scheme shall be carried out in complete accordance with the approved surface water drainage details and retained and operated in accordance with those approved details for the lifetime of the development. Reason: To ensure the site is adequately drained in the interest of local amenity, there is no flood risk on or off the site resulting from the proposed development, that appropriate and sufficient maintenance mechanisms are put in place for the lifetime of the development to reduce the flood risk to the development as a result of inadequate maintenance and the water quality is not detrimentally impacted by the proposed development, so the development complies with the provisions of Policy GN3 in the West Lancashire Local Plan 2012-2027 Development Plan Document.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

1.1To advise Planning Committee on an application which seeks the variation of conditions 3, 4, 5, 6, 7 and the removal of condition 8 of planning permission 2019/0056/FUL relating to landscaping, ecology and archaeology.

1.2The Assistant Director of Planning and Regulatory Services submitted a report on planning application 2024/0168/FUL relating to Abbey Farm Caravan Park, Abbey Lane, Lathom, Ormskirk, Lancashire, L40 5TX to Planning Committee on 19th March 2026.

1.3At this Planning Committee Members deferred said application for further consideration of wording of drainage conditions. A third party sought clarification on the following issues:

• Is it the case that discharge cannot commence until the permit is granted? • Are the Environment Agency satisfied with the wording of condition 6? • Who will be responsible for the monitoring/sampling of the treated effluent and responsible or taking action should the effluent not meet the required standard? • What will be required by way of an Operation and Maintenance Plan for the new treatment plant and would it include details such as:

➢ How often the treatment plant should be emptied ➢ How often the plant should be serviced ➢ What pollutants should the treated effluent be sampled for, how often and by who.

1.4These questions and the surface water drainage map for the site were sent to the Environment Agency (EA) for their comments. The EA's comments were then summarised in the updated report taken to Planning Committee on 23rd April 2026. Members, after consideration of the response, decided that a full publicly available written response from the Environment Agency (EA) was required and deferred the application once more for these reasons.

1.5The EA advised that rather than remove Condition 6, it be varied. The EA recommended that any wording to reference a septic tank be removed and officers suggested the following as an alternative (which was included in the Late Observations report). The varied condition was worded as follows:

"Within 2 months of the date of this permission, full details of a new sewage treatment plant to replace the existing septic tank shall be submitted to, and approved in writing by, the Local Planning Authority. The approved scheme shall be implemented in full within 2 months of its approval.

Reason: To ensure compliance with Policy GN3 of the West Lancashire Local Plan 2012–2027 and to minimise the risk of pollution."

1.6The EA were also asked about the proposed wording of Condition 7 relating to surface water management. However, they advised that surface water is not within their remit and so they had no comment on condition 7.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024/0168/FUL: Abbey Farm Caravan Park, Abbey Lane, LathomReport 236 KB DownloadRead as text
PDF
2024/0168/FUL: Abbey Farm Caravan ParkAppendix 1 115 KB Download

At this meeting

Whole meeting

Who was there

12 of 22 attended
LM
Councillor Linda Marjorie WebsterChairperson, present
MM
Councillor Mrs Marilyn WestleyVice-Chairperson, present
JA
Councillor Judy AbbottCommittee Member, present
CR
Councillor Charles Robert BerryCommittee Member, present
AB
Councillor Aaron BodyCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present as substitute
AM
Councillor Anne Mary FennellCommittee Member, present
&P
Councillor & Parish Councillor Norma GoodierCommittee Member, present
JH
Councillor John HowardCommittee Member, present
JI
Councillor Janet IngmanCommittee Member, present
RL
Councillor Richard LeeCommittee Member, present
GO
Councillor Gaynar OwenCommittee Member, apologies, sent representative

All 22 on the meeting page

On this subject at West Lancashire

Search all
  1. 2024/0168/FUL - Abbey Farm Caravan Park, Abbey Lane, LathomThis decision
  2. 2024/0168/FUL - Abbey Farm Caravan Park, Abbey Lane, LathomDeferred
  3. PLANNING APPLICATION REF: 2024/0168/FUL - Abbey Farm Caravan Park, Abbey Lane, Lathom, Ormskirk, Lancashire, L40 5TXDeferred
  4. 2019/1118//FUL - Land Bounded By Liverpool Road South, Abbey Lane, Burscough, LancashireDecided
  5. 2019/1119/FUL - Land Bounded By Liverpool Road South, Abbey Lane, Burscough, LancashireApproved

More from West Lancashire Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 MINUTESThat the minutes of the meeting held on the 30 th July 2026 be approved as a correct record and signed by the Chairpe... Approved Open
3 Sep 2026 2025/0548/FUL - Burscough Methodist Church, Orrell Lane, Burscough, L40 0SGAGREED: That planning application 2025/0548/FUL be deferred until a sufficient number of eligible Members are present... Agreed Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 18 th June 2026 be approved as a correct record and signed by the Chairman. Approved Open
30 Jul 2026 2025/1054/COU - Former Forest View NurseriesThat planning permission is granted subject to conditions set out on pages 65 - 66 of the Public Reports Pack for the... Decided Open
30 Jul 2026 2026/0229/FUL - Land West of Red Cat LaneThat planning application 2026/0229/FUL be granted subject to a deed of variation to the original Section 106 Agreeme... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies