AI summaryWest Lancashire Local Plan Committee noted an update on new plan making rules and asked officers to return with a 2026/27 work programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the report and asked for a work programme
MoneyNot stated
What happens nextWork programme for 2026/27Officers to return to next meeting with the programme
Who it affectsApplicants, landowners, residents, parishesAnyone involved in development or planning across the Borough

What was decided

The Committee noted the Local Plan Update report. Report 2.1

Officers will return to the next meeting of the Local Plan Committee with a work programme covering the rest of the 2026/2027 financial year for the Committee to agree. Report 2.2

Officers will return to the Local Plan Committee with an update on the impact of the new National Planning Policy Framework when it is published. Report 4.2

Why

The current Local Plan was adopted in October 2013 and runs until 31 March 2027, and the Council can no longer show a five year housing land supply, which means the NPPF presumption in favour of sustainable development applies. Report 3.1, 3.2

New plan making regulations published in March 2026 require Councils to produce a new Local Plan within 30 months, with an extra round of public consultation and three rounds of engagement with the Planning Inspectorate. Report 4.4, 4.5

A new NPPF is expected in Summer 2026 and the Council also faces Local Government Reorganisation and the introduction of a Spatial Development Strategy, so officers need a work programme to plan ahead. Report 4.2, 5.1, 5.2, 5.4

What happens next

Officers will run a Call for Sites exercise in Summer 2026 to identify land with potential for future development. Report 4.11

Publish a notice of intention to commence plan making by 31 December 2026 and a Gateway 1 Self Assessment by 30 April 2027. Report 4.7

Update the Statement of Community Involvement and prepare for the scoping consultation on the Plan, with the Strategic Planning team to update the Council website on progress. Report 4.8, 4.9, 4.13, 4.18

Implications

  • Financial: No direct financial or resource implications arise from the recommendations, but full implications of the new regulations, the Spatial Development Strategy and Local Government Reorganisation are not yet known. Report 6.1
  • Risk: The Council is exposed to speculative development because it cannot show a five year housing land supply and the Local Plan expires in 2027. Report 8.2
  • Risk: Misalignment with the new national plan making system could reduce the Council's influence over local growth. Report 8.3
  • Legal: Failure to follow the new procedural steps for plan preparation, examination and digital publication precisely may expose the Council to legal challenge. Report 8.7
  • Staffing: Procurement and Legal services will need to support the new Local Plan, and Strategic Planning may need to help Parish Councils produce Neighbourhood Plans now that MHCLG funding has ended. Report 4.16
  • Other: No Equality Impact Assessment is required, as the decision has no direct impact on members of the public, employees, elected members or stakeholders. Report P58

Who and where

  • Applicants for planning permission in the Borough Report 3.2
  • Those who own land, developers and site promoters invited to submit sites in the Call for Sites exercise Report 4.11
  • Residents and businesses who will be consulted on the new Plan Report 4.13
  • Residents of Burscough covered by the existing Neighbourhood Plan Report 4.15, 4.17
  • Parish Councils in the Borough who may want to produce Neighbourhood Plans Report 4.16
  • Chorley, South Ribble and Preston Councils working on the Central Lancashire Local Plan Report 5.3

Timeline

  • March 2026: New plan making regulations introduced. Report 4.4
  • Summer 2026: New NPPF expected to be published and Call for Sites exercise to begin. Report 4.2, 4.11
  • 31 December 2026: Deadline to publish notice of intention to commence plan making. Report 4.7
  • 31 March 2027: Current West Lancashire Local Plan expires. Report 3.1, P64
  • 30 April 2027: Deadline to publish Gateway 1 Self Assessment. Report 4.7
  • 2029 / 2030: Spatial Development Strategy for Lancashire expected to be adopted. Report 5.5

Plain English for the jargon

  • NPPF: National Planning Policy Framework, the Government's national planning policy.
  • Five year housing land supply: A supply of planning permissions equal to at least five years of housing need, which Councils must show they have.
  • Gateway 1 Self Assessment: The Council's own published check, due by 30 April 2027, of its readiness to start the 30 month plan making process.
  • Statement of Community Involvement (SCI): Document setting out how the Council will consult residents, businesses and stakeholders on the Local Plan and planning applications.
  • Strategic Environmental Assessment (SEA): Process to assess the environmental effects of the Plan, now called Environmental Outcome Reports.
  • Call for Sites: Exercise inviting landowners, developers and the public to suggest land with potential for future development.
  • Spatial Development Strategy (SDS): Regional plan setting out broad locations for growth, to be produced for Lancashire by the Lancashire Combined County Authority.
  • Local Government Reorganisation (LGR): Government led restructuring of councils under which West Lancashire is due to merge with Chorley and South Ribble to form a new unitary authority.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

A. That the be noted. B. That the Officers return to the next meeting with a work programme for the remainder of the 2026/2027 financial year for agreement by the Committee.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Local Plan Committee

Purpose of the report

1.1To outline the new plan-making system introduced by the Government and the implications for the Council in terms of the statutory duty to produce an up-to-date plan for the Borough.

Recommendations

2.1That the content of the report be noted.

2.2That Officers return to the next meeting of the Local Plan Committee with a work programme for the remainder of the 2026 / 2027 financial year for agreement by the Committee. 3.0 BACKGROUND

3.1The Current Local Plan was adopted in October 2013 and runs until 31 March 2027. A Local Plan shapes development of an area over a long period of time, usually at least 15 years, and is a key document the Council uses when determining planning applications. The Government encourages Councils to keep their Local Plans under review and update them when significant changes take place.

3.2In national policy, there is a requirement for a Council to maintain a sufficient land supply of planning permissions to meet 5 years' worth of housing need, known as a five-year housing land supply. Changes to how local housing need is calculated has resulted in the Council no longer able to demonstrate a five-year housing land supply. This means that the presumption in favour of sustainable development in the NPPF applies and Local Plan policies carry less weight. Therefore, whilst the current Local Plan expires in 2027, due to the lack of a five-year housing land supply there will be no change to how the Council determines planning applications after 31 March 2027.

4.0CURRENT POSITION

4.1The Council's Planning Service previously began work on a new Local Plan, in Autumn 2019, under the previous plan-making system, consulting on the scope, issues and options for the period 2023-2040. At that time, there were critical shortages in staffing across the entire service meaning this Plan was not able to be progressed.

4.2Successful recruitment took place, however the plan-making system has evolved. Since the Scope, Issues and Options document was consulted on, three new versions of the NPPF have been published and plan-making legislation has changed. A new National Planning Policy Framework (NPPF) is set to be published in Summer 2026 and, therefore, officers will need to assess the Plan against policies of the most up-to-date NPPF at that time. When the new NPPF is published, Officers will return to a meeting of Local Plan Committee with an update on how it impacts the Local Plan.

4.3The fact that the Local Plan expires in 2027 does not mean that it is no longer used when determining planning applications after this date. Officers are required to assess whether the policies in the Local Plan conform with the latest national planning policy.

4.4The Government introduced new regulations in March 2026 that replace the previous 2012 plan-making regulations. In summary, the regulations introduce an additional round of public consultation, three rounds of engagement with the Planning Inspectorate and a compressed timeframe of 30-months to produce and adopt the Plan.

4.5Diagram 1 below illustrates the new five-step plan-making system that requires Councils to produce a new Local Plan within 30 months. To put this into context, the existing Local Plan timetable (formally the Local Development Scheme) for the Borough shows an ambitious, but achievable, 48-month timeframe under the then- 2012 Local Planning regulations. Diagram 1: The 30-month Plan-making process

4.6Of the five steps, Step 1 ("Get ready") is of most relevance to the Council. This is preparatory work to get ready for commencing the formal 30-month process. In this step, progress needs to be made in 5 key areas:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Plan UpdateReport 618 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
IR
Councillor Ian RigbyChairperson, present
JG
Councillor John GordonVice-Chairperson, present
RB
Councillor Robert BaileyCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, apologies, sent representative
MS
Councillor Melissa S ParlourCommittee Member, present
AO
Councillor Adrian OwensCommittee Member, present
RL
Councillor Richard LeeCommittee Member, present
AM
Councillor Anne Mary FennellCommittee Member, present as substitute
&P
Councillor & Parish Councillor Norma GoodierCommittee Member, in attendance, virtual
JH
Councillor John HowardCommittee Member, in attendance, virtual
KJ
Councillor Katie JuckesCommittee Member, in attendance, virtual
GO
Councillor Gareth OakesCommittee Member, in attendance, virtual

All 22 on the meeting page

On this subject at West Lancashire

Search all
  1. Local Plan UpdateThis decision
  2. New Local PlanNoted
  3. National Planning Policy Framework (December 2024) and Revised Timetable for the Local Plan - Members Update included on the Agenda by Councillor A OwensNoted
  4. Local Plan - Scope, Issues and OptionsNoted
  5. Local Plan Regulation 18 (Scope, Issues & Options) ConsultationNoted
  6. Local Plan Regulation 18 (Scope, Issues & Options) ConsultationAgreed

More from West Lancashire Local Plan Committee

All decisions
MeetingDecisionOutcome
29 Jul 2026 Terms of ReferenceThat the Terms of Reference for the Local Plan Committee be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies