2025/0724/FUL - The Saddlery, Ash Brow, Newburgh, Lancashire, WN8 7NF
ApprovedPlanning2 papers
AI summaryWest Lancashire Planning Committee granted permission to demolish equestrian buildings at The Saddlery, Ash Brow, Newburgh and build two four-bedroom dwellings, subject to 17 conditions including a Construction Management Plan.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo detached four bedroom dwellings with garages
MoneyNot stated
What happens nextDevelopment must begin within three yearsConditions to be discharged before and during build
Who it affectsThe Saddlery site, Ash Brow, NewburghNear Grade II listed buildings and conservation area
What was decided
Planning permission is granted, subject to the 17 conditions in paragraph 12.1 of the officer report, plus an additional Construction Management Plan condition covering traffic, mud, parking and neighbour communication. Report 2.1, 12.1
Why
Officers found the site is previously developed land in the Green Belt where redevelopment under NPPF paragraph 154(g) is appropriate, and any harm to openness would not be substantial. Report 10.9, 10.10, 10.23
The council can only show a 1.34 year housing land supply, so the tilted balance applies and the public benefits of new homes outweigh less than substantial harm to the conservation area and listed buildings. Report 10.19, 10.36, 10.37, 10.72, 10.74
Newburgh is a Rural Sustainable Village with bus stops, a train station within walking distance and local services, making the location sustainable for two additional homes. Report 10.21
What happens next
A Construction Management Plan must be submitted and approved before any work starts, covering worker parking, loading, vehicle turning, mud control, neighbour liaison and compliance monitoring.
Other pre-commencement conditions require a drainage strategy, footpath FP0820046 specification, a Construction Environment Management Plan, a swallow method statement, tree protection and evidence of purchased biodiversity units. Report P184, P187, P195, P198, P204, P193
The development must begin within three years and built in line with the approved plans, with materials, boundary treatments, obscure glazing on Plot 1, lighting, waste and ecology details secured by condition. Report P169, P171, P173, P179, P182, P189, P191, P200
Options considered
Chosen: Grant planning permission subject to conditions (officer recommendation). Site is previously developed land in the Green Belt, tilted balance applies, public benefits outweigh less than substantial heritage harm, no unresolved objections from statutory consultees. Report 2.1, 10.10, 10.37, 10.51, 6.7, 6.22, 6.38, 11.6
Implications
Legal: The council has a statutory duty under section 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990 to preserve or enhance the conservation area, weighed against public benefits under NPPF paragraph 215. Report 10.24, 10.36
Equalities: Officers assessed no direct impact on members of the public, employees, elected members or stakeholders, so no Equality Impact Assessment was required. Report P219
Climate: Flood risk and surface water drainage were assessed; the site is in Flood Zone 1 with surface water risk, addressed through a drainage strategy condition and Sustainable Drainage Systems standards. Report 10.52, 10.57, 10.58, P184, P186
Other: Biodiversity Net Gain of 5.04% on site, with the remaining shortfall to be made up by purchased offsite units from a registered habitat bank; statutory 10% BNG condition applies. Report 10.65, P193, P194
Risk: Any actions arising are covered by the scheme of delegation to officers and have been reflected in relevant risk registers. Report 15.1
Who and where
Neighbours at 1 to 4 The Saddlery, Derby House, Spring Cottage, Old Post Office Farm and Ashdene on Ash Brow Report 10.42, 10.44
Users of public footpath FP0820046, who gain a stoned surface and improvements Report 6.16, P187
Newburgh Parish Council and 19 objectors, who raised concerns on highways, Green Belt, heritage, ecology, design and neighbour impact Report 7.1, P63, 7.2, P65
The applicant, who will deliver two four-bedroom dwellings and biodiversity units Report 4.1, 4.2, 10.65
Users of the Newburgh Conservation Area and visitors to nearby Grade II listed buildings Report 3.2, 6.18, 6.20
Timeline
Three years from the date of permission: Development must begin, otherwise the permission expires. Report P169, P170
1 April 2026: Council's housing land supply position recalculated at 1.34 years, triggering the tilted balance. Report 10.19, 10.72
Prior to commencement of development: Drainage strategy, footpath FP0820046 specification, Construction Management Plan, CEMP, swallow method statement, tree protection and BNG evidence must be submitted and approved. Report P184, P187, P195, P198, P204, P193
Before any above ground construction works: Material samples and boundary treatment details must be approved. Report P173, P179
Prior to first occupation of the dwellings: Footpath FP0820046 improvements, waste management measures, bird and bat boxes and obscure glazing on Plot 1 must be in place. Report P182, P187, P191, P200
Plain English for the jargon
BNG: Biodiversity Net Gain, a statutory requirement for development to deliver at least a 10% increase in biodiversity value.
NPPF: National Planning Policy Framework, the government's national planning policy document.
Tilted balance: Planning test under NPPF paragraph 11(d) where a council cannot show a five year housing land supply, requiring permission unless harms significantly outweigh benefits.
CEMP: Construction Environment Management Plan, setting out ecological safeguards during building works.
CMP: Construction Management Plan, setting out how construction traffic, mud and neighbour impacts will be controlled.
PROW: Public Right of Way, a legally protected path such as footpath FP0820046.
Previously developed land: Land that is or was occupied by a permanent structure, including the curtilage, used here to justify Green Belt redevelopment under NPPF paragraph 154(g).
Less than substantial harm: A category of heritage harm under NPPF paragraph 215, weighed against public benefits.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7c
Resolved
That planning permission is granted subject to conditions as set out at paragraph 12.1 of the report and additional condition as set out below: No part of the development hereby approved shall commence until a Construction Management Plan (CMP) has been submitted to and approved in writing by the Local Planning Authority. The CMP shall set out, as a minimum, site specific measures to control and monitor impact arising in relation to construction traffic and matters relation to: - details of the parking of workers and siting of site office (if required), - loading and unloading of plant and materials, - arrangements of turning of vehicles within the site - measures to prevent the transfer of mud out of the site - arrangements by which the developer shall maintain communication with residents and businesses in the vicinity of the site, - details of how the developer shall monitor and document compliance with the measures set out in the CMP. The development shall be carried out in full accordance with the approved CMP at all times. Reason: To safeguard the amenities of the adjoining premises and the area generally, and to ensure the road is not blocked during the construction period in accordance with Policies GN3 and IF2 of the West Lancashire Local Plan.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To advise Planning Committee on an application which seeks full planning permission for the demolition of existing equestrian buildings and the construction of two dwellings.
2.0RECOMMENDATION TO PLANNING COMMITTEE
2.1That planning permission is granted subject to conditions as set out at paragraph 12.1. 3.0 THE SITE
3.1The application site is located to the south side of Ash Brow in Newburgh and is accessed via a shared track which runs between Spring Cottage and Derby House and alongside The Saddlery. A public footpath, FP0820046, extends along the shared access track and continues southeast through the site to join with footpath FP0807033 to the south. To the north of the public footpath are a range of six equestrian outbuildings and a tarmac yard, and to the south an existing menage and paddock.
3.2The access route is flanked by Spring Cottage and Derby House, both of which are Grade II listed buildings. The access also falls within, and the site is adjacent to, the Newburgh Conservation Area. The area surrounding the site is primarily characterised by residential dwellings along Ash Brow and open countryside to the rear (south). The Red Lion Hotel is located on the other side of Ash Brow, opposite the entrance to the site.
4.0PROPOSAL
4.1Planning permission is sought for the demolition of existing equestrian buildings and the construction of two dwellings with associated landscaping and boundary treatments.
4.2Both dwellings would be detached, two storey, four-bedroom dwellings with detached garages. They would be of a contemporary architectural style. Each dwelling would have a reasonably sized separate driveway accessed from the proposed access lane.
4.3After discussions with officers, updated plans demonstrating a revised design were received during the application period. These changes altered the architectural style and positions of buildings. Therefore, the assessment is based on these revised drawings.
5.0PREVIOUS RELEVANT DECISIONS
5.1None relevant
6.0OBSERVATIONS OF CONSULTEES
LCC Highways
6.1Initial comments – 05/09/2025 After reviewing the submitted application and the accompanying Transport Statement (TS), the Highway Authority raises no objections to the proposed development.
6.2The TS provides an accurate overview of the effects of the existing and proposed transport conditions which the highway Authority concurs with.
6.3The site access is restricted to single vehicle entry and exit at the kerb line, however the entrance then widens within the site for approximately 13m, allowing vehicles to wait clear of the highway and to pass one another within the site. On this basis the access arrangements are considered acceptable given the number of trips generated by the two dwellings.
6.4It is noted that refuse storage bins may be positioned adjacent to the site access. This arrangement must be revised and bins positioned elsewhere in the site. This would allow the full remaining width of the access to be used by vehicles and pedestrians. 6.5 Noted the public right of way, which should remain open during construction works and after the development has been completed, and the landowner should follow the full legal process if the right of way is to be temporarily closed during construction works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.