Resolved
RESOLVED that, having examined the report Members were assured that the arrangements in place to oversee Services across the Council are effective.
Corporate Policy and Resources Committee decided this item on Thursday 12 May 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, having examined the report Members were assured that the arrangements in place to oversee Services across the Council are effective.
F CPR.06 16/17
Corporate Policy & Resources Committee
12 May 2016
Subject: Progress and Delivery Report – Services – 4th Period Report – March 2016
Report by: Director of Resources
Contact Officer: Ian Knowles – Director of Resources 01427 675183 [email protected]
Purpose / Summary: This report deals with the progress and delivery of the services the council provides. It is an “exceptions” report and will deal with those services which are either performing above the required level or are below the target set for them. The report will also update members on those areas which were included in the first quarter report and have subsequently improved and therefore are not included in this report.
RECOMMENDATION(S): 1) That the Committee examine the report and assure themselves that the arrangements in place to oversee Services across the Council are effective.
1 IMPLICATIONS
Legal: None arising from this report
Financial : FIN/22/17 None
Staffing : None arising from this report
Equality and Diversity including Human Rights: None arising from this report.
Risk Assessment : None arising from this report
Climate Related Risks and Opportunities : None arising from this report
Title and Location of any Background Papers used in the preparation of this report:
Call in and Urgency:
Is the decision one which Rule 14 of the Scrutiny Procedure Rules apply?
Yes No x
Key Decision:
Yes No x
2 1.0 Background
1.1Councillors have received progress and delivery reports since 2012. They have sought to give councillors information on how the council is performing through its services, project delivery and finances. This has given councillors the opportunities to question officers on performance and ensure that any rectification measures proposed to remedy poor performance are sufficient to tackle the issues identified.
1.2This report is about the services the council is delivering in order to meet the objectives it has set itself in the corporate plan.
1.3For clarity this report will provide information on those services that are either performing below their target level or have exceeded the performance expected of them. This will be done within certain tolerance levels therefore services which are just below their target performance will not be reported at this stage, but will be monitoring through the council’s services leadership team. Generally explanations and rectifications are given where an aspect of a service is performing below the required standard.
1.4In addition the report will contain information on services which were included in the last period’s exceptions report, but have subsequently improved to the extent that they are not included in this report. This is to demonstrate to members that remedial measures which have been put in place are working.
2.0Update on Issues highlighted in the Third Quarter report
2.1Complaints received Complaints continued at a similar rate during the last quarter. A separate report on feedback will be brought to policy committee later in the year. Planning continued to represent over 30% of the total number of complaints.
2.2Gainsborough Markets This service has recently become the responsibility of the Projects and Growth Team who are currently exploring the options to improve this service. A separate paper was taken to Prosperous Communities Committee in May.
2.3Local Land Charges
Performance has improved and is now below the target of ten days for returning a search. This does come at a cost and although work is ongoing to secure a IT solution for the longer term.
2.4Development Management 3 Performance against the key measures continues to improve and is now above the government set targets. However complaints have continued at similar levels throughout the year whilst allowed appeals are higher than we would like. A restructure is currently being implemented and is expected improve the situation further.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress and Delivery: Services: Period 4Report | 416 KB | DownloadRead as text |
Follow Corporate Policy and Resources Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Apr 2026 | Minutes of Previous Meeting/sRESOLVED that the Minutes of the Meeting of the Corporate Policy and Resources Committee held on Thursday, 12 Februar... | Noted | Open |
| 16 Apr 2026 | Good Homes AllianceRESOLVED that a) the positive impact of the work to date be acknowledged; and b) it be agreed to fund the for a furth... | Agreed | Open |
| 16 Apr 2026 | Recommendation from JSCC: Review of the Anti-Money Laundering and Financial Crime Prevention PolicyRESOLVED that a) the recommendation from the Joint Staff Consultative Committee be accepted, and the revised Anti-Mon... | Approved | Open |
| 16 Apr 2026 | Committee Timetable 2026/27 for ApprovalRESOLVED that the timetable for the 2026/27 civic year be approved. | Approved | Open |
| 16 Apr 2026 | Exclusion of Public and PressRESOLVED that under Section 100 (A)(4) of the Local Government Act 1972, the public and press be excluded from the me... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.