Subject: Progress and Delivery Report – Projects – 4th Period Report – January to March 2016
Report by: Director of Resources
Contact Officer: Ian Knowles – Director of Resources. 01427 676682 [email protected]
Purpose / Summary: This report deals with the progress and delivery of projects which are aimed at the delivery of the corporate plan. This report highlights those projects that have entered the delivery stage and are either off track or at risk of not delivering.
RECOMMENDATION(S): 1) That the committee examine the responses given to the report by the Corporate Policy and Resources Committee and the Prosperous Communities Committee and assure themselves that the appropriate level of challenge is being made by those committees to the information contained in the report.
1 IMPLICATIONS
Legal: None arising from this report
Financial : FIN23/17 None
Staffing : None arising from this report
Equality and Diversity including Human Rights: None arising from this report.
Risk Assessment : None arising from this report
Climate Related Risks and Opportunities : None arising from this report
Title and Location of any Background Papers used in the preparation of this report:
Call in and Urgency:
Is the decision one which Rule 14 of the Scrutiny Procedure Rules apply?
Yes No x
Key Decision:
Yes No x
2 1.0 Background
1.1Councillors have received progress and delivery reports since 2012. The Leadership team has sought to give councillors information on how the council is performing through its services, project delivery and finances. Members are asked to : Identify and recognise achievements and success Seek assurance on remedial actions where appropriate Make recommendations for any changes to policy or request for strategic reviews
1.2This report is about the projects the council is delivering in order to meet the objectives it has set itself in the corporate plan.
1.3For clarity and in order to comply with the council’s project management requirements only those projects which are in the “delivery stage” will be reported through this mechanism.
1.4In addition from time to time projects are rescoped and their timelines altered during the delivery phase. That can mean that their status can change. Where this happens, when a project was red in a previous progress and delivery report (at significant risk of not delivering either to the timetable or within budget) this will be reported to members through this mechanism, together with an explanation of why the project has been rescoped and new time lines set.
2.0Programme/Projects Overview
2.1To oversee programme/project development and delivery the Council has established three ‘themed’ Boards – Transformation; Commercial and Growth. Each Board oversees projects relating to their particular theme and seeks assurance from project managers that where issues are identified rectifications are in place.
2.2A fourth Board is in existence; The Entrepreneurial Board, which has an overall view of programme/project delivery with each of the three Boards report to it and highlight successes or areas/issues to be addressed. By having an overarching view, the Entrepreneurial Board plays a key role in resource allocation and prioritisation of work.
3.0The Report
3.1This report covers the period from January to March 2015. It is a report “by exception” which contains information on those programmes/projects that are current during the reporting period and are at risk of not delivering their outcomes and/or may not be completed within prescribed timescales or costs.
3 4.0 Programmes/Projects by Exception
4.1The following programmes/projects are considered to be at risk of delivery within agreed timescales and/or costs, or the intended outcomes are at risk of being realised. Recommendations and/or rectifications have been offered by the relevant project managers and have been considered by both the respective Board and the Entrepreneurial Board.
Fraud Investigation Services - AMBER
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Challenge and Improvement Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingRESOLVED that the Minutes of the meeting of the Challenge and Improvement Committee held on 19 February 2019 be confi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.