Resolved
RESOLVED that the contents of the report be noted.
Challenge and Improvement Committee noted this item on Tuesday 4 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contents of the report be noted.
CAI.52 16/17
Committee: Challenge and Improvement
Date 4th April 2017
Subject: Planning Enforcement Update
Report by: Chief Operating Officer
Contact Officer: Andy Gray Housing and Communities Team Manager 01427 675195 [email protected]
Purpose / Summary: To provide elected members with an update in regards to the performance of planning enforcement services
RECOMMENDATION(S):
1) Members are asked to note the contents of this report
1 IMPLICATIONS
Legal:
Financial: FIN REF: - FIN/153/17
There are no financial implications within this report.
Staffing:
The section on resources outlines the current challenges facing the work area in relation to resources. Temporary measures are in place until June 17.
Equality and Diversity including Human Rights :
Risk Assessment :
Climate Related Risks and Opportunities:
Title and Location of any Background Papers used in the preparation of this report:
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply? i.e. is the report exempt from being called in due to Yes No urgency (in consultation with C&I chairman)
Key Decision: A matter which affects two or more wards, or has Yes No significant financial implications
2 1. Background
1.1This report has been produced as a result of a request from elected members at a previous challenge and improvement committee and a subsequent briefing. The report outlines the current performance information relating to planning enforcement.
1.2It is recognised that this area of work is high profile and high priority for elected members.
2. Performance
2.1Information is provided to elected members within the progress and delivery report which outlines the month to month situation within the service area. This report provides an overview of the key measures.
2.2Figure 1 shows the number of open planning enforcement cases. This is currently 154 and has increased from a caseload of 80 in April 15. The number of open cases has increased steadily as demonstrated by the graph.
2.3There were 267 reports in 14/15, 248 in 15/16 and already 200 to February 17. Each report requires assessment and investigation depending on its priority.
2.46 notices have been served in an attempt to rectify breaches in 16/17 and 4 were served in 15/16. This does not include planning contravention notices served. Figure 1.
2.5Figure 2 demonstrates the time taken to resolve a planning enforcement request. This is the average number of days taken to 3 determine (close) a request in the year to date. In January 17 this figure was 147 days. In 15/16 the average number of days was 130 and in 14/15 it was 78.
Figure 2.
2.6Table 1 shows the priority level of cases that have been reported to date in 16/17. The assessment on the case is made by the officer in line with the enforcement policy.
Month Priority 1 Priority 2 Priority 3 Priority 4 Apr 2016 1 20 25 1 May 2016 1 21 28 2 Jun 2016 1 22 36 2 Jul 2016 1 24 41 2 Aug 2016 1 27 52 2 Sep 2016 2 31 55 3 Oct 2016 4 33 58 4 Nov 2016 4 35 61 5 Dec 2016 4 35 64 7 Jan 2017 7 36 72 9 Feb 2017 8 37 80 13
2.7Table 2 shows the reasons for closure for cases that have been closed in 16/17 to date. There are 113 in total and in 56 of these no breach of
4 planning has been identified. This data has only been collected in detail during this financial year but will now be collected routinely.
Table 2. Planning Enforcement Closure Reasons 16/17 Enforceme Lawful – No Not Breach Deemed nt Notice Planning Month Breach Expedi Rectifi Closed Complied Permission Found ent ed With Granted Apr-16 2 4 1 0 0 0 May-16 4 1 1 1 1 0 Jun-16 6 2 5 0 0 2 Jul-16 7 1 2 1 0 2 Aug-16 16 4 1 0 0 4 Sep-16 4 1 1 0 0 1 Oct-16 0 1 0 1 0 3 Nov-16 3 1 1 1 0 1 Dec-16 9 1 1 0 0 0 Jan-17 4 2 0 2 0 2 Feb-17 1 0 1 0 0 3 Totals 56 18 14 6 1 18
3. Resources
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enforcement Performance UpdateReport | 208 KB | DownloadRead as text |
Follow Challenge and Improvement Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2019 | Minutes of the previous meetingRESOLVED that the Minutes of the meeting of the Challenge and Improvement Committee held on 19 February 2019 be confi... | Decided | Open |
| 2 Apr 2019 | Matters Arising ScheduleRESOLVED that the Matters Arising Schedule as at 25 March 2019 be received and noted. | Noted | Open |
| 2 Apr 2019 | Progress and Delivery Report - Period 3 2018/19RESOLVED that Members be assured that suitable challenge is being made to the information contained in the report. | Decided | Open |
| 2 Apr 2019 | C&I Annual ReportRESOLVED that the Challenge and Improvement Annual Report be supported for submission to Annual Council in May 2019. | Decided | Open |
| 2 Apr 2019 | Forward PlanRESOLVED that the forward plan be received and noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.