Gainsborough Town Centre Townscape Heritage Application
ApprovedCommittee1 paper
Corporate Policy and Resources Committee approved this item on Thursday 21 September 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED to: 1. proceed with the submission of a Stage 1 Townscape Heritage bid; 2. approve the use of the Investment for Growth Reserve as capital match funding within the application; 3. approve a revised budget within the Capital Programme as detailed within the financial implications.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
Report to Corporate Policy and Resources Committee
Committee
Corporate Policy and Resources Committee
Date
21 September 2017
Subject: Gainsborough Town Centre Townscape Heritage Application
Report by: Eve Fawcett-Moralee Economic and Commercial Growth Director
Contact Officer: Wendy Osgodby Senior Growth Strategy and Projects Officer Direct Dial :01427 676636 [email protected]
Purpose / Summary: To provide an update on the application to the Heritage Lottery Fund for Townscape Heritage funding for Gainsborough Town Centre, thereby obtaining formal commitment and financial support.
RECOMMENDATION(S):
1. To proceed with the submission of a Stage 1 Townscape Heritage bid. 2. To approve the use of the Investment for Growth Reserve as capital match funding within the application. 3. To approve a revised budget within the Capital Programme as detailed within the financial implications. IMPLICATIONS
Legal: Any works carried out under the TH scheme will require the owner’s consent and statutory consent (in the form of Listed Building Consent). All works will need to be state aid compliant.
Financial : FIN/67/18
Within the Capital Programme 2017/18 there is a budget of £1.717m for the purpose of delivering this scheme, the financing of which was to be £0.429m from the Investment for Growth Reserve and £1.288m from grant.
In accordance with Financial Procedure Rules, this Committee must approve the submission of grant bids, and accept a commitment to approve relevant match funding in support of the bid, in addition to accepting any future ongoing revenue implications.
The Committee are therefore requested to amend the Capital programme to reflect a budget of £1.615m funded by £0.365m from the Investment for Growth Fund and £1.250m from HLF grant funding.
The delivery of this project is dependent on the success of the bid. Approval to spend will therefore be subject of a future report, once the outcome is known and which will contain details of the schemes to be delivered.
At this stage it is not envisaged that there will be any ongoing revenue financial implications.
Staffing : This project will be led by the Senior Growth Strategy and Projects Officer supported by the Senior Projects Officer and the Growth Team as part of the agreed work plan.
A steering group has been established to act as a coordinating and monitoring body involving local residents, businesses, council representatives, and representatives from the community and voluntary sector.
Equality and Diversity including Human Rights :
The Stage one application form includes a full equalities impact checklist which takes account of the impact of the project upon groups with protected characteristics under the 2010 Equalities Act. Risk Assessment : Risk We are rejected for the THI funding.
Mitigation We do not consider a third bid for a substantial period of time and reflect on the organisational lessons offered through HLF rejecting the application.
Risk We fail to accurately evaluate the conservation deficit in the town centre.
Mitigation Consult with the Conservation Officer on our assumptions about the historic environment of the town centre.
Commission the building character appraisals contained in the 2016 WLDC THI bid to be updated.
Climate Related Risks and Opportunities : Any new development will ensure that current building regulation standards on sustainability can be achieved and include provision for cyclists.
Title and Location of any Background Papers used in the preparation of this report: Prosperous Communities Committee – 7 June 2016 - Gainsborough Townscape Heritage Initiative (THI) Bid https://www.west-lindsey.gov.uk/my-council/decision-making-and-council- meetings/meetings-agendas-minutes-and-reports/prosperous-communities- committee/prosperous-communities-committee-reports/
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply? i.e. is the report exempt from being called in due to Yes No x urgency (in consultation with C&I chairman)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Policy and Resources Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.