RESOLVED that: - (a) the Director of Resources be granted delegated authority to sign the partnership agreement with On- lincolnshire and pay the amount of £555k; (b) Officers work with BDUK and On-Lincolnshire as part of Phase 3; and (c) Officers lobby Central Government to deliver 100% coverage across West Lindsey.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
Subject: Broadband Provision Across the District – Update
Report by: Director of Resources
Contact Officer: Ian Knowles Director of Resources 01427 675183 [email protected]
Purpose / Summary: To provide Members with an up to date position with regard to Broadband provision across the District.
RECOMMENDATION(S):
Member agree that:
a) That the Director of Resources is delegated to sign the partnership agreement with Onlincolnshire and pay the amount of £555k b) Officers work with BDUK and Onlincolnshire as part of phase 3 c) Officers lobby Central Government to deliver 100% coverage of West Lindsey
1 IMPLICATIONS
Legal:
Signing the partnership agreement will commit WLDC to paying the agreed amount without guarantees on the work to be undertaken. However without the agreement and payment no work will be undertaken. It is therefore in the interests of West Lindsey residents that payment is made to Onlincolnshire.
Financial Implications: FIN/93/18 A Capital Budget of £555k was approved as part of the 2013/14 Capital Programme as our contribution to support the BDUK roll out within West Lindsey. To be funded from Capital Receipts.
Staffing :
Equality and Diversity including Human Rights :n/a
Risk Assessment :
Key Risk: Payment to BDUK may be made and no postcodes fall within the acceptable value for money criteria to be accepted as part of Phase 3.
Mitigation: Work is being undertaken with BDUK and Onlincolnshire to ensure that West Lindsey are included as part of phase 3 and as many of the post codes are covered as possible.
Key Risk: West Lindsey is included in the works programme of phase 3 but timescales may change due to the increased work plan. Current plan scheduled to be completed by December 2019.
Mitigation: Updates given once available on postcodes to be included in Phase 3 and timescales involved to ensure visibility to all involved.
Climate Related Risks and Opportunities :n/a
Title and Location of any Background Papers used in the preparation of this report: Results from Broadband survey and speed test https://www.west- lindsey.gov.uk/my-council/have-your-say/consultations/previous-consultation-
2 results/high-speed-broadband/
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply?
Yes No x
Key Decision:
Yes x No
3 1. Introduction
1.1In December 2016 a decision was made by the Prosperous Communities Committee for a survey to be developed that would test the extent of the issue of broadband connectivity throughout West Lindsey. The results of this survey were brought to this Committee in June 2017 with 3 high level options for the future.
1.2The superfast (UK) coverage across West Lindsey at that time (Nov 2016) was 85.4% based on the website ThinkBroadband.com. The equivalent figure at October 2017 is 86.74%.
2. Current position
2.1West Lindsey was excluded from BDUK Phase 2, based on BDUK’s interpretation of a commercial loan to Quickline. However, this situation has now been resolved and West Lindsey is to be included in Phase 3.
The proposed postcodes for this phase are currently confidential due to the commercial sensitivity. However, the postcodes to be passed to BT by Onlincolnshire for modelling equate to approximately 8.5% of the total premises count for West Lindsey.
This figure will change once the modelling has taken place and realistically more like 70% of the postcodes submitted may get accepted. If any postcodes are accepted onto the programme then a change request will need to be implemented to establish the timescales.
If 70% of the proposed post codes are covered by BDUK Phase 3 then the coverage shown above as 86.74% should be expected to increase to something approaching 92% to 93%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.