Resolved
RESOLVED that: (a) the responses given in regards to the Planning Enforcement audit be noted; and (b) the Local Enforcement Plan, as set out in Appendix 1, be approved to come into effect from 1 April 2018.
Prosperous Communities Committee noted this item on Tuesday 20 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: (a) the responses given in regards to the Planning Enforcement audit be noted; and (b) the Local Enforcement Plan, as set out in Appendix 1, be approved to come into effect from 1 April 2018.
Prosperous Communities Committee
Date 20th March 2018
Subject: Local Enforcement Plan (Planning Enforcement)
Report by: Head of Paid Service Mark Sturgess
Contact Officer: Andy Gray Housing and Environmental Enforcement Manager
Purpose / Summary: To provide Committee with a revised Local Enforcement Plan (Planning Enforcement) and request its approval.
RECOMMENDATION(S):
Elected Members are asked to:
a) Note the responses given in regards to the planning enforcement audit
b) Approve the Local Enforcement Plan as set out in Appendix 1 to come into effect on the 1st April 2018
1 IMPLICATIONS
Legal:
The legal framework within which the Council operates its planning enforcement function is set out in the policy. The following guidance and legislation applies: - The Town & Country Planning Act 1990 (as amended) - The Town & Country Planning (Use Classes) Order 1987 (as amended) - Planning (Listed Buildings & Conservation Area) Act 1990 - Planning & Compensation Act 1991 - Planning & Compulsory Purchase Act 2004 - Localism Act 2011 - National Planning Policy Framework (March 2010) - National Planning Practice Guidance (March 2014) https://www.gov.uk/guidance/ensuring-effective-enforcement
Financial : FIN/156/18/CC
There are no financial implications within this report.
Works in default may be carried out as part of the enforcement process Any works in default are then recovered via the enforcement or civil debtor process, Report agreed at Management Team – FIN/MT/64/18
Report agreed at Challenge and Improvement - FIN/144/18/SL
Staffing :
There are no staffing implications within this report.
Equality and Diversity including Human Rights : There are not expected to be any adverse impacts on any of the specific user groups in relation to this policy being implemented. The Policy itself sets out the approach that will be taken and the options available to the Council. Within each specific case An Equality Impact Assessment has been carried out and is included as Appendix 2.
2 Risk Assessment :
Out of Date Policy: the existing policy requires updating to reflect the current legislative framework and priorities that are in place. The risk is mitigated with the development and approval of a new policy.
Audit: a risk is presented in regards to the “limited assurance” received by Planning Enforcement as part of the wider Development Management audit. This report and subsequent policy mitigates immediately some of the actions identified and proposes actions for addressing the remaining actions.
Climate Related Risks and Opportunities : None noted
Title and Location of any Background Papers used in the preparation of this report: Existing Planning Enforcement Policy: https://www.west-lindsey.gov.uk/my-services/planning-and-building/planning- enforcement/
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply? i.e. is the report exempt from being called in due to Yes No X urgency (in consultation with C&I chairman)
Key Decision: A matter which affects two or more wards, or has Yes X No significant financial implications
3 1. Introduction
1.1This report contains an updated version of the Council’s Planning Enforcement Policy, which moving forward will be known as the Local Enforcement Plan. This sets out the approach that is taken when dealing with planning enforcement matters.
1.2The report also provides information in response to the development management audit report completed in September 2017, within which the planning enforcement service received limited assurance.
2. Development Management Audit
2.1The development management audit report completed in September 2017 included within its scope an audit of the planning enforcement work area. The service was given limited assurance as part of the audit.
2.2The audit clearly identifies that the service are makes effective decisions, evidenced by the upholding of appeals and takes a proportionate, policy based approach to the matters that it deals with.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Enforcement Plan (Planning Enforcement)Report | 279 KB | DownloadRead as text |
Follow Prosperous Communities Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Apr 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Prosperous Communities Committee held on 17 March 2026 be confirmed a... | Decided | Open |
| 28 Apr 2026 | Waste & Recycling Operational Policy ReviewRESOLVED that a) all changes in table one of the report be approved for making to the Waste & Recycling Operational S... | Approved | Open |
| 17 Mar 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Prosperous Communities Committee held on 27 January 2026 be confirmed... | Decided | Open |
| 17 Mar 2026 | Leisure, Culture, Events and Tourism Member Working Group, Terms of ReferenceRESOLVED that the reviewed Terms of Reference for the Working Group, as shown at appendix 1, and subject to the repla... | Approved | Open |
| 27 Jan 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Prosperous Communities Committee held on 2 December 2025 be confirmed... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.