RESOLVED that: (a) the Housing Assistance Policy, as set out in Appendix 3, be approved to come into effect on 1 June 2018, subject to the Policy being amended as follows: - all references to the First time buyer initiative being amended to read Empty Property buyer initiative (b) it be RECOMMENDED to the Corporate Policy and Resources Committee that the earmarked reserve allocated for private sector renewal be released to fund the assistance offered within the Policy. Note: Councillor Gillian Bardsley, during consideration of the above item, declared a pecuniary interest as landlord and left the meeting. Councillor Mrs Bardsley did not take part in the deliberations or vote on the above item of business but ... view the full minutes text for item 120.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
Contact Officer: Andy Gray Housing and Environmental Enforcement Manager
Purpose / Summary: To provide elected members with an updated Housing Assistance Policy and to seek approval for the financial assistance provided within it.
RECOMMENDATION(S):
Elected Members are asked to:
a) Approve the Housing Assistance Policy as set out in Appendix 3 to come into effect on 1st June 2018.
b) Recommend to Corporate Policy and Resources Committee that the earmarked reserve allocated for private sector renewal is released to fund the assistance offered within the policy. IMPLICATIONS
Legal:
The Regulatory Reform (Housing Assistance) (England & Wales) Order 2002 provides the framework for the Council to provide a wider range of discretionary assistance. The Council has a statutory duty to provide mandatory DFGs and there is no intention to amend this duty.
The aspects of the policy that relate to private sector renewal are entirely discretionary. Additional procurement advice will be sought in regards to the specific aspects of this policy to ensure that the legal risk is minimal. Given that the offers being made are positive it is not expected that any legal issues will be identified. Financial : Fin Ref: FIN/18/19
DISABLED FACILITIES GRANT
The Council currently delivers Disabled Facilities Grant (DFGs) and receives a grant allocation from Lincolnshire County Council as part of the Better Care Fund on an annual basis. The existing allocation in 17/18 was £602,000 and this is scheduled to increase to £648,000 in 18/19. A capital budget is approved as Business As Usual (BAU), with some element of the grant funding supporting the revenue cost of administration of the scheme.
In terms of the DFG scheme the discretionary elements will be funded from the capital budget already approved in the capital programme. No additional funds are requested within this report and will therefore be managed within the existing budget.
There is the proposal to create a relocation grant from the DFG allocation, this would not constitute capital expenditure and therefore would be a charge to Revenue. Therefore an element of the DFG funding will need to moved to Revenue to cover any expenses incurred and the Capital budget reduced.
This policy does meet the extended powers under The Regulatory Reform (Housing Assistance) Order 2002.
PRIVATE SECTOR RENEWAL
The Private Sector Renewal capital budget sits within the Capital Programme as a Pre-Stage 1 scheme as there has not been a policy or business case developed to enable the allocation of this budget to date. The overall budget for this capital programme is £1,439,000 (as detailed at paragraph 6 below). This will be financed initially by £825,000 from the Investment for Growth Earmarked Reserve and £614,900 from Capital Receipts.
The proposals highlighted for Private Sector Renewal are in the main compliant with the CIPFA Code for Capital expenditure. However, one element poses potential challenges, the Landlord incentive grant (£2,500), which will be
classified as Revenue Expenditure and therefore would utilise the Investment for Growth Earmarked Reserve, and thereby reducing the capital budget.
Staffing :
There are no staffing implications within this report.
Equality and Diversity including Human Rights : None. Risk Assessment :
Private Sector Renewal
Lack of Capital Receipts – capital receipts are required in order for the scheme to be able to continue beyond the three year funded period. A lack of these receipts will mean that no further funding can be offered.
Climate Related Risks and Opportunities : None noted
Title and Location of any Background Papers used in the preparation of this report: None.
Call in and Urgency:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.