Governance and Audit Committee decided this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to accept the current status of this project.
Committee: Governance & Audit
Date: 19th June 2018
Subject: Commercial Billing Update
Report by: Tracey Bircumshaw Strategic Finance and Business Manager
Contact Officer: Tracey Bircumshaw [email protected]
Purpose / Summary: To update Members on the progress of the Commercial Billing solution.
RECOMMENDATION(S): That Members accept the current status of this project. IMPLICATIONS
Legal: None
Financial: FIN-52-19
The external costs to the Council have been £1,500 and are contained within the 2017/18 financial year budget.
Staffing: None
Equality and Diversity including Human Rights: None
Risk Assessment: Risk management arrangements are part of corporate governance and issues raised under these arrangements have been included in the Annual Governance Statement
Climate Related Risks and Opportunities: None
Title and Location of any Background Papers used in the preparation of this report: None.
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply?
Yes No x
Key Decision:
Yes No x 1. Background
1.1This report was requested by the Governance and Audit Committee to inform them on progress of the Commercial Billing project, which had been raised as an issue within the Sales and Invoice Audit resulting in a limited assurance being given.
1.2In 2016 a request was made from the Trade Waste Service to investigate whether the current financial Debtors system could be developed to enable variable payment options. Their business case detailed that due to the increasing number of customers and the frequent amendment to their requirements i.e. number and capacity of bin and number of lifts, the administration for invoicing was becoming inefficient.
1.3From a customer perspective, whilst there was little evidence of demand at this time, the team also wanted to be able to provide variable payment options similar to the utility companies i.e. Variable payment terms i.e. annual, monthly on account, monthly actuals in arrears Variable payment options, bank transfer, cheque, Direct Debits for all payment terms
1.4The current system is able to produce all the relevant payment terms however it is unable to process variable monthly direct debits. The management of invoices is labour intensive with cancellations and new invoices being raised to ensure accurate billing for changes in requirements.
1.5A quote for a solution was provided by our suppliers Civica and was £15,000. At this time and due to the lack of demand the business case was not supported as it was not a value for money solution.
1.6In February 2017 the Finance and Business Support Manager came up with a suggested alternative solution within the limitations of the current system and after discussions with Civica this was viewed as quick and low cost piece of work at a quoted price of £1,500. Civica were engaged to commence the work.
2. Project Progress
2.1Whilst work was ongoing during April and May there was no progress being made and it transpired that after a short period of illness the consultant working on the project retired. We had no communication in this regard from Civica.
2.2After some insistence in July 2017 Civica investigated the current state of the project and it was found that the work undertaken was not developed in the correct way and Civica would not be able to finalise nor support this in the future. Civica quoted for 12 consultancy days at a cost of £12,600. The Strategic Finance and Business Manager was therefore insistent that Civica finalise the project at the original cost, due to the issues and delays experienced and the lack of communication and poor customer service we had received. It was therefore agreed that the price would remain at £1,500 and a new consultant was allocated to the project, and the product to be supported in the future.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Commercial Billing UpdateReport | 137 KB | DownloadRead as text |
Follow Governance and Audit Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Governance and Audit Committee held on 26 July 2026 be confirmed and ... | Decided | Open |
| 21 Jul 2026 | Internal Audit Follow up reportThat the progress to date be noted and the content of the report be agreed. | Noted | Open |
| 21 Jul 2026 | Internal Audit Annual Report 2025.26That the Annual Report be noted. | Noted | Open |
| 21 Jul 2026 | Internal Audit Progress ReportThat the progress to date and content of the report be noted. | Noted | Open |
| 21 Jul 2026 | Strategic RisksThat the report be noted and a further summary report be presented to November 2026 meeting. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.