Challenge and Improvement Committee, Tuesday 8 January 2019 at 6.30pm

Leisure Contract Implementation

Agreed Committee 1 paper

Challenge and Improvement Committee agreed this item on Tuesday 8 January 2019. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

RESOLVED that it be recommended to the Prosperous Communities Committee that: a) the contents of the report, and the work undertaken since the award of the leisure contract, be supported by Members; and b) Members agree to receive an interim report at the end of Year One and a further report at the end of Year Two of the contract which monitors performance of the agreed targets.
Word for word from the decision West Lindsey published for this meeting. Source: democracy.west-lindsey.gov.uk

Follow this further

Built from West Lindsey's papers

What the report saysPro

Report to Challenge and Improvement Committee

Challenge & Improvement

8 January 2019

Subject: Leisure Contract Implementation

Report by: Mark Sturgess – Executive Director of Operations

Contact Officer: Karen Whitfield Community & Commercial Programme Manager 01427 675140 [email protected]

Purpose / Summary: To report on the implementation of the Council’s leisure contract and progress to date.

RECOMMENDATION(S):

1. Members support the contents of this report and the work undertaken since the award of the leisure contract

2. Members agree to receive a further report at the end of Year two of the contract which monitors performance of the agreed targets.

1 IMPLICATIONS

Legal:

None arising

Financial: FIN/176/19

None arising

Staffing:

None arising

Equality and Diversity including Human Rights: None Arising

Risk Assessment:

None arising

Climate Related Risks and Opportunities: None arising

Title and Location of any Background Papers used in the preparation of this report:

Call in and Urgency:

Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply? i.e. is the report exempt from being called in due to Yes No x urgency (in consultation with C&I chairman)

Key Decision: A matter which affects two or more wards, or has Yes No x significant financial implications

2 1. Background

1.1This report has been requested by Challenge and Improve Committee in advance of a meeting of Prosperous Communities Committee scheduled for the 29th January.

1.2As leisure is a non-statutory service, and with increasing pressure on Council budgets, back in 2015 the Council began to look at cost effective solutions for continuing to provide a leisure service, and ways to deliver tangible health benefits. This work was extensive and included an independent leisure options review, feasibility studies and a Member workshop which resulted in a Procurement Strategy being developed.

1.3Members of Prosperous Communities considered and agreed the main principles and outcomes of the current leisure contract on the 8th December 2015 and 19th July 2016.

1.4Following a full OJEU procurement process Members of Corporate Policy & Resources awarded the contract to Everyone Active on the 11th January 2018. The new contract provides for:

a) Refurbishment of West Lindsey Leisure Centre including the development of a health and wellbeing hub;

b) Development of a new dry leisure facility in Market Rasen;

c) Employment of an Active Communities Manager;

d) Launch of a district wide outreach service

2. Contract implementation

2.1Contract price

The contract provides an average annual income of £136k for the Council. In addition the capital used to refurbish West Lindsey Leisure Centre will be repaid plus 4% interest over the lifetime of the contract. These amounts are covered by a payment schedule as part of the contract and, as a result of the contract award, the overall benefit to the Council over the lifetime of the contract is £2.477 million.

2.2Refurbishment of West Lindsey Leisure Centre

Refurbishment of West Lindsey Leisure Centre began at the commencement of the current contract on the 1st June.

The first phase of works included the development of the health and wellbeing hub. This was completed in September and the centre held a very successful official open day which was hosted by Sir Colin Jackson.

3 The development of the health and wellbeing hub replaced the indoor bowls facility at the leisure centre. In the period between the contract award and the commencement of the contract, both Members and Officers worked hard to limit the impact on affected users. Several options were identified and offered including signposting to alternative facilities and incorporating a dedicated short mat area within the leisure centre. These offers were not taken up and the bowls club have continued to explore opportunities for alternative provision within the town.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Contract ImplementationAgenda 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 17 attended
PH
Councillor Paul Howitt-CowanChairman, present
LS
Councillor Lewis StrangeVice-Chairman, present
MA
Councillor Mrs Angela WhiteVice-Chairman, present
BA
Councillor Bruce AllisonCommittee Member, present
DB
Councillor David BondCommittee Member, present
MA
Councillor Mrs Angela LawrenceCommittee Member, present
MJ
Councillor Mrs Jessie MilneCommittee Member, absent
RP
Councillor Roger PattersonCommittee Member, present
MD
Councillor Mrs Diana RodgersCommittee Member, present
ML
Councillor Mrs Lesley RollingsCommittee Member, present
TS
Councillor Thomas SmithCommittee Member, present
MA
Councillor Mrs Anne WelburnCommittee Member, present

All 17 on the meeting page

On this subject at West Lindsey

Search all
  1. Leisure Contract ImplementationThis decision
  2. Leisure Contract ReprocurementNoted

More from West Lindsey Challenge and Improvement Committee

All decisions
MeetingDecisionOutcome
2 Apr 2019 Minutes of the previous meetingRESOLVED that the Minutes of the meeting of the Challenge and Improvement Committee held on 19 February 2019 be confi... Decided Open
2 Apr 2019 Matters Arising ScheduleRESOLVED that the Matters Arising Schedule as at 25 March 2019 be received and noted. Noted Open
2 Apr 2019 Progress and Delivery Report - Period 3 2018/19RESOLVED that Members be assured that suitable challenge is being made to the information contained in the report. Decided Open
2 Apr 2019 C&I Annual ReportRESOLVED that the Challenge and Improvement Annual Report be supported for submission to Annual Council in May 2019. Decided Open
2 Apr 2019 Forward PlanRESOLVED that the forward plan be received and noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies