Resolved
RESOLVED to note the report.
Governance and Audit Committee noted this item on Tuesday 16 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report.
Internal Audit Progress Report
West Lindsey DC March 2019
For all your assurance needs Contents Key Messages Page 2 Introduction Summary Assurances
Internal Audit work completed Page 5 Overview of Assurances Audit Reports at Draft Work in Progress
Appendices Page 8 Assurance Definitions Details of Overdue Actions 2018/19 Audit Plan to Date
Lucy Pledge CMIIA QIAL- Audit and Risk Manager (Head of Internal Audit) [email protected]
John Sketchley – Audit Team Leader [email protected]
This report has been prepared solely for the use of Members and Management of West Lindsey District Council. Details may be made available to specified external organisations, including external auditors, but otherwise the report should not be used or referred to in whole or in part without prior consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended for any other purpose.
The matters raised in this report are only those that came to our attention during the course of our work – there may be weaknesses in governance, risk management and the system of internal control that we are not aware of because they did not form part of our work programme, were excluded from the scope of individual audit engagements or were not bought to our attention. The opinion is based solely the work undertaken as part of the agreed internal audit plan. 1 Introduction The purpose of this report is to:
• Provide details of the audit work during the period 07.12.2018 – 10.03.2019 • Advise on progress with the 2018/19 plan • Raise any other matters that may be relevant to the Audit Committee role
Key Messages During the period we have completed nine reviews:
• • Seven final assurance reports One consultancy report 2 • One Assurance Mapping report HIGH ASSURANCE
Assurances The following audit work has been completed and a final report issued:
• Key Controls Insurance– High 5 • Key Controls VAT – High SUBSTANTIAL • Customer First – Substantial ASSURANCE • Corporate Planning – Substantial • Commercial Plans Follow Up – Substantial • Key Controls Health & Safety – Substantial • • • ICT Records Management - Substantial Good Governance – Consultancy Assurance Map 0 LIMITED ASSURANCE
1 Note: The assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. The definitions for each level are shown in Appendix 1. CONSULTANCY
2 During the period we have issued four reports giving high or substantial assurance.
High Assurance The Council must have an insurance process in place, in order to mitigate risks. The main aim for an organisation handling insurance claims, is to ensure that each claimant is dealt with efficiently, effectively and professionally. It is equally important to make sure that each claim is legitimate.
The audit gave assurance that the insurance function within the Council Key is effectively managed whilst guaranteeing that claims are dealt with Controls accurately, compliantly and timely. Insurance Our assurance rating for insurance at West Lindsey District Council is High. A sample of claims was taken from the claim log sheet for analysis. For each claim log and claim form, the information is accurate, up to date and clear to follow.
There are no recommended actions from this audit.
The aim of the audit is to give assurance that the VAT re-claiming function of the Council is effectively managed, accurate, compliant and timely whilst, guaranteeing that fines are not incurred. We are also checking that the VAT is correctly identified and recorded.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Quarter 4 Monitoring 18/19Frontsheet | 123 KB | Download |
PDF |
Internal Audit Quarter 4 Monitoring 18/19 main reportReport | 737 KB | DownloadRead as text |
Follow Governance and Audit Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Governance and Audit Committee held on 26 July 2026 be confirmed and ... | Decided | Open |
| 21 Jul 2026 | Internal Audit Follow up reportThat the progress to date be noted and the content of the report be agreed. | Noted | Open |
| 21 Jul 2026 | Internal Audit Annual Report 2025.26That the Annual Report be noted. | Noted | Open |
| 21 Jul 2026 | Internal Audit Progress ReportThat the progress to date and content of the report be noted. | Noted | Open |
| 21 Jul 2026 | Strategic RisksThat the report be noted and a further summary report be presented to November 2026 meeting. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.