It was agreed that the document explained the information in a clear and concise format and was easy to navigate around. Following a question from a Member of Committee regarding cases of data loss across the Council, the Corporate Policy Manager introduced the second part of the report regarding the six monthly review of strategic risks. He explained that the assessment template detailed what the triggers might be, the potential impact, the current controls in place and any other areas of consideration. Using the example of information security, the likelihood of it happening was high, despite the measures in place and the structures needed to be as robust as possible. The fact that there had not been significant losses was likely to be the strength of the systems but there always needed to be structured discussion around the likelihood, the impact and how to reduce both. There was discussion regarding the risks included in the report and whether there were any marginal risks not covered. Members heard that all risk areas were based around the delivery of the Corporate Plan and that if any service risks impacted on strategic delivery, they would be referenced in the report. Members engaged in discussion around the risks that sat outside of the control of the District Council and it was confirmed that there was a role for the Council to play, for example in education. The Corporate policy Manager explained several initiatives that were running across the Council with the aim of making small improvements where possible. He gave the example of work experience placements for students and a mentoring scheme that had been running ... view the full minutes text for item 28.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
1. To present to Committee for consideration and Purpose / Summary: approval, the Council’s revised Risk Management Strategy 2019-2023. 2. To present to Committee for review the strategic risks facing the Council as at October 2019.
RECOMMENDATION(S): 1. That Members approve the Council’s Risk Management Strategy 2019- 2023. 2. Members obtain assurance that strategic risks are being captured, considered and managed effectively IMPLICATIONS
Legal: None
Financial: FIN/70/20/TJB
There are no specific financial implications of this report.
However, effective risk management ensures that there is a robust mechanism to identify, analyse and mitigate risks which may have an impact on delivery of our plans and finances.
Staffing: None
Equality and Diversity including Human Rights: None
Data Protection Implications: None
Climate Related Risks and Opportunities: None
Section 17 Crime and Disorder Considerations: None
Health Implications: None
Title and Location of any Background Papers used in the preparation of this report : None.
Risk Assessment: None 1 Introduction
1.1Risk management is a statutory requirement for local government to ensure business continuity and is an essential component of corporate governance.
1.2By having effective risk management practices in place and embedded as part of everyday working and decision making, the Council can ensure that it is focusing on the right areas and can direct scarce resources at those issues most likely to have an adverse effect on the achievement of strategic aims.
1.3This is particularly pertinent in the current economic and ever changing environment within which local government operates.
1.4This report contains two sections. The first introduces the draft Council Risk Management Strategy 2019-2023 for approval, while the second section presents the Council’s strategic risks for review.
2. Draft Risk Management Strategy 2019-2023
2.1The previous Strategy covering the period 2016-2018 was produced and approved by Members in 2016. This has now been updated to take account of and complement the Council’s new Corporate Plan (2019- 2023); to reflect the current context within which the Council is operating and to bear relation to current internal structures and areas of responsibility.
2.2The revised Strategy takes account of the very good work that has taken place in relation to risk management within the Council during the intervening period. This has been endorsed by the Head of Internal Audit
2.3The Strategy sets out the Council’s approach to managing risk and also details the authority’s ‘risk appetite’ as being ‘Creative and Aware’ in nature. This means that the Council is willing to take calculated risks to seize opportunities (innovation) and achieve success. The Council will consider all delivery options and choose the one that is most likely to result in successful delivery while also providing a good level of reward.
2.4The Strategy is supported by a similarly reviewed Approved Code of Practice (ACoP). This is an internally focused piece of guidance which helps to ensure consistency in approach and sets out the appropriate roles and responsibilities across the Council in relation to risk management.
2.5To support the delivery of the revised Strategy, externally facilitated risk management training has taken place for staff and Members. This work was positively received by all who took part. Part of this work determined the ‘risk appetite’ of the Council (as a collective body) referred to at 2.3 above. 2.6 One main amendment made from the previous Strategy is the introduction of consideration of inherent (current) risk levels and target (desired future or residual) risk levels against each risk. The Strategy sets out explanations of these concepts on pages six and seven.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.