Resolved
RESOLVED to approve the Review 2019-2024.
Regulatory Committee approved this item on Tuesday 10 December 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to approve the Review 2019-2024.
Regulatory Committee
Tuesday 10th December 2019
Subject: Contaminated Land Strategy
Report by: Executive Director of Resources
Andy Gray, Housing and Environmental Contact Officer: Enforcement Manager Sarah Gamble, Senior Environmental Health Practitioner
[email protected], [email protected]
To provide an updated contaminated land Purpose / Summary: strategy and seek approval for this.
RECOMMENDATION(S):
Elected Members are asked to:
a) Approve the Contaminated Land Strategy Review 2019 – 2024 as attached at appendix 1. IMPLICATIONS
Legal:
Under Part 2A, Section 78 of the Environmental Protection Act 1990, which came into force on the 1st April 2000. The Act introduced a duty for all local authorities to identify and remediate land where contamination is causing an unacceptable risk to human health or the wider environment. The duties were implemented by the Contaminated Land (England) Regulations 2006, and is supported by Contaminated land Statutory Guidance.
The Government’s key objectives driving the contaminated land regime is to
- Identify and remove unacceptable risk to human health and the environment - Seek to ensure that contaminated land is made suitable for its current use (Part 2A Regulations) and proposed use (planning regime). - Ensure that the burdens faced by individuals, companies and society as a whole are proportional, manageable and compatible with the principles of suitable development
Financial : FIN/127/20/SL
There are no immediate financial implications arising from this report.
Staff training due in December 2019 will be covered by existing training budget.
For the prioritisation of the sites within the strategy, an additional resource will be required in order to do this effectively. This is for a desk based, but intensive exercise, in which all sites are reviewed and then prioritised in line with the strategy. There will be a financial implication in regards to this and a separate report will be brought to Management Team specifically relating to this in the future. Any proposals will be better informed by the first stage of works that will be undertaken in December 2019, which will provide an estimation of the number of sites that will need prioritisation.
Staffing :
The existing staff do have a level of experience in regards to contaminated land. It is proposed that following on from the intensive prioritisation exercise that the ongoing work in relation to this could be covered within the existing staff resource available.
Equality and Diversity including Human Rights : NONE
Data Protection Implications : Climate Related Risks and Opportunities :
Section 17 Crime and Disorder Considerations :
Health Implications:
Reduces risks to human health and protects wider environment and pressures on development of greenfield sites.
Title and Location of any Background Papers used in the preparation of this report:
Risk Assessment :
There is a statutory duty to revise and update as necessary failure to do is contrary to the regulatory obligations. In addition, there is a fundamental link with Planning Services to ensure safe redevelopment of contaminated sites. If a revised strategy is not published, the Authority could face a legal challenge if decisions are based on an outdated strategy or if specific sites are not considered.
1 Introduction
1.1In 2014 Defra withdrew the capital grant funding that was made available to Local Authorities for the remediation of contaminated land for orphan sites or where landowners (generally residents) would face undue hardship. This has left the Authority with no capital funding to inspect or remediate sites of this nature. Nonetheless, if contaminated land is identified within the District then this may present a financial burden to the Local Authority.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contaminated Land StrategyAppendix 1 | 1.4 MB | Download |
PDF |
Contaminated Land StrategyReport | 235 KB | DownloadRead as text |
Follow Regulatory Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jun 2026 | Chairman's Welcome and Resolution to Vary the AgendaRESOLVED that the agenda be varied as above. | Decided | Open |
| 4 Jun 2026 | Minutes of Previous meetingRESOLVED that the Minutes of the Meeting of the Regulatory Committee held on Thursday 4 December 2025 be confirmed an... | Decided | Open |
| 4 Jun 2026 | Removal of Taxi Driver Knowledge TestRESOLVED that the requirement for a knowledge test to be carried out by any driver applying for a hackney carriage ve... | Decided | Open |
| 4 Jun 2026 | Dog Fouling Public Space Protection Order - ExtensionRESOLVED that the Dog Fouling Public Space Protection Order, be extended for a three-year period from 7 June 2026 to ... | Decided | Open |
| 4 Jun 2026 | Food, Health and Safety Work Plan 26/27RESOLVED that a) the Food, Health and Safety Work Plan as detailed at Appendix 1 be approved; and b) an update on pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.