It was agreed that this information could be shared through the Members’ Newsletter. There were questions raised regarding use of CCTV, the CCTV cameras at the Gainsborough leisure centre and also concerns raised about cleanliness levels at the leisure centre. The Vice-Chairman noted that, as detailed in the minutes from both the Prosperous Communities Committee and the Corporate Policy and Resources Committee, these issues had been raised and were being addressed by Officers. The Monitoring Officer undertook to clarify concerns regarding CCTV at the leisure centre. With regards to the report being discussed and the recommendation to the Committee, the Vice-Chairman read aloud the recommendation and stated that, as given in the minutes of the two policy meetings, she believed there was sufficient challenge being made. The recommendation was moved and seconded and it was therefore RESOLVED that the Committee be assured the appropriate level of challenge was being made by the Corporate Policy and Resources Committee and the Prosperous Communities Committee to the information contained in the report.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
Purpose / Summary: To consider the Progress and Delivery report for period two (June-September) 2019-20.
RECOMMENDATION(S):
That the Committee examine the responses given to the report by the Corporate Policy and Resources Committee and the Prosperous Communities Committee and assure themselves that the appropriate level of challenge is being made by those committees to the information contained in the report. IMPLICATIONS
Legal: There are no legal implications as a result of this report
Financial : FIN/103/20/SL There are no financial implications as a result of this report.
Staffing : There are no staffing implications as a result of this report
Equality and Diversity including Human Rights :
N/A
Risk Assessment :
N/A
Climate Related Risks and Opportunities : N/A
Title and Location of any Background Papers used in the preparation of this report: N/A
Call in and Urgency:
Is the decision one which Rule 14.7 of the Scrutiny Procedure Rules apply?
Yes No X
Key Decision:
Yes No X 1.0 Introduction Councillors have received Progress and Delivery (P&D) reports since 2012. These performance reports provide information on how the Council is performing using a balanced scorecard approach that measures performance of Council services based on the following perspectives:
Customer Financial Process Quality
The purpose of the P&D reporting cycle is to provide Councillors on policy committees the opportunity to discuss service based performance with officers and for Councillors to be given assurance that proposed measures to remedy consistently below target performance are sufficient enough to allow for required improvements. Once the report has been received by each policy committee, the Council’s Overview and Scrutiny Committee is given the opportunity to scrutinise any challenges made, thus feeding in to a cycle of continuous improvement of the Council’s performance management processes.
As per the Council’s Constitution, this report provides information on an exception basis, i.e. those performance measures that are performing above or below agreed targets for at least two consecutive periods. Where performance is below expected standards, Team Managers are required to provide explanatory commentary, including what remedial action is/will be taken to improve performance to the expected level. Performance measures that are performing within agreed tolerance levels are not included in this report, though all P&D performance measures continue to be monitored corporately, facilitated by the Performance and Programmes Team.
Performance measures for 2019/20 were agreed by a member steering group in February 2019. A member steering group is currently working with Officers to agree the P&D performance measures and targets for 2020/21, with these due to be signed off by Corporate Policy and Resources Committee in January 2020.
How to use this report Performance is assessed using the RAG traffic light system as follows: Performance is below agreed tolerance levels Performance is within agreed tolerance levels Performance is better than agreed tolerance levels.
The municipal year is divided into four periods in alignment with the Council’s committee schedule. Period one covers April and May, period two runs from June – September, period three covers October – December and period four runs from January – March. As well as current performance, information for the preceding three periods is included in the report on a rolling basis to provide context and to allow for comparison. In addition, direction of travel is also included which compares performance for the current period to the same period the previous year, i.e. period one 2019/20 is compared to period one 2018/19.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the meeting of the Overview and Scrutiny Committee held on 8 September 2026 be confirmed...
West Lindsey Homelessness Action PlanRESOLVED that: 1. The draft 2026-2028 was reviewed. 2. It was agreed that the Action Plan provided a robust framework...
Minutes of the previous meetingRESOLVED that the minutes of the meeting of the Overview and Scrutiny Committee held on 30 June 2026 be confirmed and...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.