Corporate Policy and Resources Committee, Thursday 5 November 2020 at 6.30pm

Solar Photovoltaic proposal for new Depot

Approved Committee 1 paper

Corporate Policy and Resources Committee approved this item on Thursday 5 November 2020. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

RESOLVED to: (1) Approve an application for funding to the Public Sector Decarbonisation Scheme for installation of Solar Photovoltaic Panels at the new central waste depot at Caenby Corner; ... view the full minutes text for item 42.
Word for word from the decision West Lindsey published for this meeting. Source: democracy.west-lindsey.gov.uk

Follow this further

Built from West Lindsey's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Corporate Policy and Resources

Thursday 5th November 2020

Subject: Solar Photovoltaic (PV) Proposal for new Waste Depot

Report by: Assistant Director of Operational and Commercial Services

Contact Officer: Ady Selby Assistant Director of Operational and Commercial Services

[email protected]

Purpose / Summary: Inform Councillors of a grant funding bid that is being submitted for Solar Photovoltaic (PV) Panels for the new central waste depot. The report also seeks approval from Corporate Policy and Resources Committee for a contingency spend to be drawn from The Carbon Management Reserve Fund in the event that the grant bid is unsuccessful.

RECOMMENDATION(S): That Members:

1. Approve an application for funding to the Public Sector Decarbonisation Scheme for installation of Solar Photovoltaic Panels at the new central waste depot at Caenby Corner.

2. Approve a capital budget of up to £50,000 for 2021/22 and subsequent expenditure, for the installation of Solar Photovoltaic Panels to be funded by grant and/or the Carbon Management Reserve, dependent on level of grant funding received.

The Assistant Director for Operational and Commercial Services is to consult with the Chairman of Corporate Policy and Resources Committee when the result of the grant bid is known. 3. Ratify the award of work via the project contractor (subject to any conditions imposed by an award of funding.)

4. Note and endorse the measures to improve energy efficiency at the new depot and approve that they are in line with Council aims to achieve energy sustainability in all Council controlled premises. IMPLICATIONS

Legal: Following the UK Government’s Climate Emergency Declaration, Net- zero greenhouse gases by 2050 was made a statutory target in June 2019 through the Climate Change Act (2050 Target Amendment) Order.

The council has the ability to award the contract for these works through the existing project contract with Henry Boot for design and build of the depot.

Financial : FIN/100/21/TJB

The approval of a capital budget 2021/22 and subsequent expenditure of £50,000 is deemed appropriate to provide a level of contingency in the estimated pricing quoted for the installation Solar Photovoltaic Panels at the new Depot.

This work will be carried out by our Depot contractor as a variation to the building design.

A grant bid to meet the financing of this investment will be made to Public Sector Decarbonisation Scheme. In the event that the bid is unsuccessful then the costs will be met from the Carbon Management Reserve, which will then be fully allocated.

It is envisaged that this investment will generate an annual £2,272 of saving in electricity cost estimates for the new depot.

Staffing : Negligible impact.

Annual maintenance and cleaning requirement so a ‘mansafe system’ would be added to the roof design as there isn’t a parapet to prevent falls.

Equality and Diversity including Human Rights :

Data Protection Implications : Climate Related Risks and Opportunities: The proposed installation of Solar PV Panels will reduce the environmental impact of the depot. West Lindsey has made a commitment to be net-zero carbon emissions from our own activities by 2050 and source energy from renewable sources by 2040. It is estimated that the carbon reduction impact of this scheme is estimated at 11.918kg p.a. See main report.

Section 17 Crime and Disorder Considerations:

Health Implications:

Title and Location of any Background Papers used in the preparation of this report : N/A

Risk Assessment :

The funding bid may not be successful, so it is important to make sure the business case for solar PV can be made on its own merits. This is the case, but should the unit costs of energy fall the payback period will be prolonged. This is unlikely given historical rates and projections. Pre-commissioning approval for grid connection has not been received. Timescales may risk slippage if waiting for a response from the District Network Operator (DNO).

Call in and Urgency:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Solar Photovoltaic proposal for new DepotReport 268 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 29 attended
MA
Councillor Mrs Anne WelburnChairman, present
PH
Councillor Paul Howitt-CowanVice-Chairman, present
OB
Councillor Owen BierleyCommittee Member, present
MB
Councillor Matthew BolesCommittee Member, present
SB
Councillor Stephen BunneyCommittee Member, present
DC
Councillor David CottonCommittee Member, present
MD
Councillor Michael DevineCommittee Member, present
IF
Councillor Ian FleetwoodCommittee Member, present
GM
Councillor Giles McNeillCommittee Member, present
JM
Councillor John McNeillCommittee Member, present
MJ
Councillor Mrs Jessie MilneCommittee Member, present as substitute
MM
Councillor Mrs Mandy SneeCommittee Member, present

All 29 on the meeting page

More from West Lindsey Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
16 Apr 2026 Minutes of Previous Meeting/sRESOLVED that the Minutes of the Meeting of the Corporate Policy and Resources Committee held on Thursday, 12 Februar... Noted Open
16 Apr 2026 Good Homes AllianceRESOLVED that a) the positive impact of the work to date be acknowledged; and b) it be agreed to fund the for a furth... Agreed Open
16 Apr 2026 Recommendation from JSCC: Review of the Anti-Money Laundering and Financial Crime Prevention PolicyRESOLVED that a) the recommendation from the Joint Staff Consultative Committee be accepted, and the revised Anti-Mon... Approved Open
16 Apr 2026 Committee Timetable 2026/27 for ApprovalRESOLVED that the timetable for the 2026/27 civic year be approved. Approved Open
16 Apr 2026 Exclusion of Public and PressRESOLVED that under Section 100 (A)(4) of the Local Government Act 1972, the public and press be excluded from the me... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies