Resolved
RESOLVED that Members had considered the content of the report and identified any actions required.
Governance and Audit Committee decided this item on Tuesday 24 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Members had considered the content of the report and identified any actions required.
STRICTLY PRIVATE AND CONFIDENTIAL
WEST LINDSEY DISTRICT COUNCIL Follow Up Final Internal Audit Report: 2.24/25 21 August 2024 This report is solely for the use of the persons to whom it is addressed. To the fullest extent permitted by law, RSM UK Risk Assurance Services LLP will accept no responsibility or liability in respect of this report to any other party. OUTCOME OVERVIEW Background: We have undertaken a review to follow up on progress made to implement the previously agreed management actions from the following audits:
• WLDC 2023/24-02 - Key Project Review - Saxilby Footbridge Refurbishment; • WLDC 2022/23-03 - Contract Management; • WLDC 2022/23-05 - Risk Management; • WLDC 2023/24-01 - Equality Impact Assessments; • NKDC/WLDC 2022/23-12 - ICT Asset management; and • WLDC/NKDC 2023/24-03 - ICT Cyber Security.
The focus of this review was to provide assurance over the progress made against previously agreed management actions. A total of 24 actions were due at the time of the audit, consisting of four low priority actions and 20 medium priority actions.
Headline findings: Taking account of the issues identified in the remainder of the report and in line with our definitions set out in Appendix A, in our opinion the Council has demonstrated reasonable progress in implementing agreed management actions. Testing found that 16 actions had been either implemented or superseded, six actions had been partially implemented, and the final two actions were not implemented. We have agreed new management actions for the nine actions which are detailed in section two of this report.
2 Summary of Actions for Summary of actions for Management management
01 3 SUMMARY OF PROGRESS ON ACTIONS The following table includes details of the status of each management action:
Number of Implementation Implementation status by review Implemented Not implemented Superseded actions agreed ongoing
WLDC 2023/24-02 - Key Project Review - 12 6 3 1 2 Saxilby Footbridge Refurbishment
WLDC 2022/23-03 - Contract Management 3 1 1 1 0
WLDC 2022/23-05 - Risk Management 1 0 1 0 0
WLDC 2023/24-01 - Equality Impact 3 2 1 0 0 Assessments
NKDC/WLDC 2022/23-12 - ICT Asset 4 4 0 0 0 Management
WLDC/NKDC 2023/24-03 - ICT Cyber 1 1 0 0 0 Security
Total 24 14 (59%) 6 (25%) 2 (8%) 2 (8%)
4 Detailed Findings and Actions
02 5 DETAILED FINDINGS AND ACTIONS The results of our testing are set out below.
1 The entire action has been fully implemented. 2 The action has been partly though not yet fully implemented. 3 The action has not been implemented. 4 The action has been superseded and is no longer applicable. 5 The action is not yet due.
Assignment: Key Project Review - Saxilby Footbridge Refurbishment Original Meet with Canals and Rivers Trust to discuss the long-term future ownership of Saxilby Footbridge – the preferred outcome is that Canals management and Rivers Trust (C&RT) to own ownership of the bridge. action / Priority: Low priority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Follow Up 2.24.25 FINAL WLDCReport | 414 KB | DownloadRead as text |
PDF |
IT Operations 1.24.25 FINAL WLDCReport | 492 KB | Download |
PDF |
Internal Audit Update ReportReport | 28 KB | Download |
PDF |
Progress Report September 2024 WLDCReport | 304 KB | Download |
Follow Governance and Audit Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Minutes of Previous MeetingRESOLVED that the Minutes of the Meeting of the Governance and Audit Committee held on 26 July 2026 be confirmed and ... | Decided | Open |
| 21 Jul 2026 | Internal Audit Follow up reportThat the progress to date be noted and the content of the report be agreed. | Noted | Open |
| 21 Jul 2026 | Internal Audit Annual Report 2025.26That the Annual Report be noted. | Noted | Open |
| 21 Jul 2026 | Internal Audit Progress ReportThat the progress to date and content of the report be noted. | Noted | Open |
| 21 Jul 2026 | Strategic RisksThat the report be noted and a further summary report be presented to November 2026 meeting. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.