Corporate Policy and Resources Committee agreed this item on Tuesday 11 March 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED that a) the award of funding, once received for Warm Homes Local Grant from Midlands Net Zero Hub (MNZH), be accepted, and the signing of the grant funding agreement by Section 151 Officer, for return to MNZH, be authorised; and b) a new capital scheme be created in the Capital Programme and a capital and revenue budget be created ... view the full minutes text for item 118.
Word for word from the decision West Lindsey published for this meeting.Source: democracy.west-lindsey.gov.uk
Report to Corporate Policy and Resources Committee
Corporate Policy and Resources
11th March 2025
Subject: Warm Homes Local Grant (WHLG)
Report by: Veronica Edwards Healthy and Accessible Homes Team Leader
Contact Officer: Veronica Edwards Healthy and Accessible Homes Team Leader 01427 675 187 [email protected]
To provide information on Central and South Purpose / Summary: Lincolnshire Consortium indicative allocation and seek approval to sign the grant funding agreement
RECOMMENDATION(S):
1 Corporate Policy and Resources Committee agree to accept the award of funding once received for Warm Homes Local Grant from Midlands Net Zero Hub (MNZH) and authorise signing of the grant funding agreement by Section 151 Officer, for return to MNZH. 2. Create a new capital scheme in the Capital Programme and create a capital and revenue budget for the WHLG once funding agreement has been signed. IMPLICATIONS
Legal: (N.B.) Where there are legal implications the report MUST be seen by the MO MNZH will issue a grant funding agreement to the Council which will include all details of the funding which is to be allocated to the Consortium for Warm Homes Local Grant. As accountable body, to the Central and South Lincolnshire Consortium, WLDC will seek a review of the grant funding agreement by Legal Services Lincolnshire.
The Council will need to ensure that WHLG Delivery proposal is compliant with UK subsidy control rules. This will be reviewed by legal service Lincolnshire as part of the contracting procedure.
All procurement activity will be undertaken in line with the Council’s Contract Procedure Rules (CPRs) and ultimately Public Contract Regulations 2015 (PCRs), which is embedded into UK Law. All frameworks which the Council are using and may consider using are PCR compliant.
Financial: FIN/153/25/SL/MT Committee are asked to approve the signatory of the Grant Funding agreement, due to the value of the contract – indicative allocation for West Lindsey District Council £1,356,919, with final allocation due to be confirmed in March 2025.
This project relies on securing of capital grant funding via Department of Energy Security and Net Zero (ESNZ) of £9mil to deliver the WHLG scheme.
Admin allocation to be used for the Energy Efficiency Project Officer (subject to job evaluation) hosted by West Lindsey District Council (WLDC). This will be a 36- month contract. Staffing : (N.B.) Where there are staffing implications the report MUST have a HR Ref
The scheme will be delivered by the following: - Current staff within Homes, Health and Wellbeing Team - An extension to the Energy Efficiency Project officer post funded by the Warm Homes Local Grant administration allocation, hosted by WLDC, - Customer journey support provided by MNZH appointed partner -installations, and all other services via procured delivery partner.
HR Ref: HR227-02-19
Equality and Diversity including Human Rights : N/A
Data Protection Implications :
Data Sharing agreement in place with Midlands Net Zero Hub Climate Related Risks and Opportunities:
This scheme strongly aligns with the council's environmental objectives, particularly: Becoming a net-zero carbon council by 2050
Supporting residents to reduce emissions Addressing fuel poverty while promoting sustainability Monitoring methods: Before and after EPC ratings
Energy consumption data from participating households Carbon savings calculations Number and types of measures installed In conclusion, the Warm Homes Local Grant demonstrates very significant positive environmental impacts, particularly in energy efficiency and carbon reduction. While there are some very minor negative impacts from implementation and transport mileage, these are vastly outweighed by the long-term environmental benefits. The scheme represents an excellent opportunity to achieve both social and environmental objectives simultaneously.
Section 17 Crime and Disorder Considerations: N/A Health Implications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Policy and Resources Committee at West Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.