(1) The award of £39.4 million Devolution Deal funding to Coventry Rail Station Masterplan project, which was promoted by Coventry City Council based on assurance work completed and the endorsement of the Project by the Investment Board on 29 January 2018 was approved. (2) Delegated authority was given to the Monitoring Officer and the Director of Finance in consultation with the Portfolio Lead for Finance to conclude the grant agreement with Coventry City Council in accordance with this report.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Employee Sean Pearce, Director of Finance email: [email removed] tel: (0121) 214 7936
Report to be/has been Technical Approval Panel (1/11/17) considered by WMCA Investment Advisory Group (4/12/17) WMCA Leadership Team (10/1/18) Investment Board (29/1/18) Programme Board (23/2/18)
The WMCA Authority Board is recommended to:
(1) Approve the award of £39.4 million Devolution Deal funding to Coventry Rail Station Masterplan project, which is promoted by Coventry City Council based on assurance work completed and the endorsement of the Project by the Investment Board on 29 January 2018. (2) Delegate to the Monitoring Officer and the Director of Finance in consultation with the Portfolio Lead for Finance to conclude the grant agreement with Coventry City Council in accordance with this report. 1 Purpose 1.0 This report seeks the approval of £39.4 million for Coventry Rail Station Masterplan (CSMP), requested via a full business case. 1.1 This report sets out the work undertaken by the Investment Board and the assurance now provided to support the approval being proposed to the West Midlands Combined Authority Investment Board. It summarises the key aspects to the application and is supported by the summarised business case submitted by the lead Council, in this case, Coventry City Council that was considered by the Investment Board. 1.2 The Coventry Station Masterplan is an £82 million programme of works to increase capacity at Coventry Rail Station. £42.6 million is already secure, funding has been awarded from a number of sources including Coventry and Warwickshire Local Enterprise Partnership (CWLEP), Department for Transport (DfT) and prudential borrowing via Coventry City Council. 1.3 The West Midlands Combined Authority funding is therefore the remaining element to be secured to enable a fully funded programme. 2 Background 2.0 The Coventry Station Masterplan project aims to improve connectivity to UK Central and HS2, boosting jobs and growth in the city centre. The current Grade-II listed railway station which has seen little change since it opened in 1962 is now a barrier to achieving this. The station has experienced unprecedented passenger growth over the last 10 years and is now beyond its design capacity, which is suppressing demand for travel and limiting current and future economic and jobs growth in the city. 2.1 The Station Masterplan will involve a comprehensive redevelopment of the station, delivering new infrastructure including a second station building, 644 space multi- storey car park with an uplift of 350 car park spaces from the current provision, a new footbridge connecting all platforms, a new bay platform to enable more frequent services between Coventry and Nuneaton, a 6 bay bus interchange with provision for rail replacement services and significant highway improvements to deal with traffic operation around the station and bus interchange. A pedestrian underpass has already been completed which will provide traffic free access for pedestrians between the bus interchange and station building. 2.2 The programme has been phased to minimise disruption to the railway station, which will remain in operation throughout programme delivery. The phasing of the programme is set out in the following table: Table 1: Key Project Milestones
CSMP Key Milestone Target
Planning Applications February 2018
Finalise Land Acquisition (CPO process) Spring 2019
Footbridge and Canopies/Substation May 2018 - Summer 2019
NUCKLE Phase 1.2 Oct 2018 - May 2019
Highways Phased delivery Spring 2019 – End 2020
New Station Building End 2020
Multi-storey Car Park End 2020
Bus Interchange Summer 2021
3 Impact on the Delivery of the Strategic Transport Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.