That the year to date net revenue expenditure for 2017/18 shows a favourable variance of £5.0m compared to budget and a full year forecast variance of £5.2m following the final re-forecast of the year be noted ; 2. That the total capital expenditure to the end of January 2018 within the overall transport programme was broadly in line with budget, showing a 3 % variance (£1.7m) and 3. That the treasury indicators are within the expected range and there are no issues to highlight be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Director Sean Pearce Director of Finance Tel 0121 214 7936 Email - [email removed] Accountable employee(s) Linda Horne, Head of Finance & Business Planning Tel 0121 214 7508 Email [email removed] Report to be/has been Cllr Worrall (Lead Member- Finance and Performance considered by Monitoring)
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended to:
1. Note that the year to date net revenue expenditure for 2017/18 shows a favourable variance of £5.0m compared to budget and a full year forecast favourable variance of £5.2m following the final re-forecast of the year.
2. Note that total capital expenditure to the end of January 2018 within the overall transport programme was broadly in line with budget, showing a 3% variance (£1.7m)
3. Note that the treasury indicators are within expected range and there are no issues to highlight.
Page 1 of 10 [NOT PROTECTIVELY MARKED]
1.0Purpose
1.1This report sets out the financial position as at 31 January 2018 and is the fifth monitoring report for the 2017/18 financial year. The content relates to the financial position of the Combined Authority’s Transport Delivery Revenue and Capital Budgets. The report consists of the following Sections:
Section A Summary TFWM Revenue Budget
Section B Summary TFWM Capital Budget
Section C Treasury Management Indicators
SECTION A
2.0Summary Revenue Position
2.1As at the end of January 2018 there is a net favourable year to date variance against budget of £5.0m. Following the third and final re-forecast of the year there is a favourable full year position of £5.2m against budget.
2.2This is an adverse movement of £470,000 from the last forecast reported to January Committee and consists of £265,000, which is the rebate from Constituent Authorities that was agreed to be released from the Transport Levy budget as part of the recommendations in the WMCA 2018-19 budget report. The remaining £205,000 reflects additional cost pressures related to TfWM activities.
2.3The 9 Feb 2018 WMCA Budget for 2018/19 approved plans to use £4.8m of this saving to support the Transport Revenue Budget during the period 2018/19 to 2020/21. This reflected £3.0 million to be set aside to earmarked reserves to support the transport delivery revenue budget enabling a corresponding levy reduction in each of the 3 years of £1.0 million a year. The remainder, £1.8m, earmarked for Transport for West Midlands rebranding and a contribution to emerging transport investment requirements
2.4Year to Date and Full Year Variances:
The following are a summary of the main movements within the categories of spend set out in the table that follows paragraph 2.5.
Concessions:
The favourable variances of £974,000 year to date and forecast £1.355m full year are as previously reported, mainly as a result of savings on the national bus concession scheme owing to lower patronage, and the release of provisions within the Child, Metro and Rail Concessions budget for fare and patronage increases that are no longer required.
Bus Services:
The adverse year to date variance of £223,000 and anticipated full year adverse position of £333,000 are mainly due to a number of infrastructure cost pressures as a result of increased maintenance requirements seen in-year and projected for the remainder of the year in relation
Page 2 of 10 [NOT PROTECTIVELY MARKED]
to Bus Stations and on-street infrastructure. Another factor has been lower income year to date in relation to Bus Station departures due to a lower number of departures taking place than budgeted.
Rail and Metro services:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.