That the contents of the report and progress on the town centre programme be noted; 2. That it be noted that the report had been considered, and the broad contents endorsed, for submission to this Board by the Housing and Land Steering Group.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1Town centre regeneration and re-purposing is a very high profile agenda, nationally and regionally. The Housing & Land Delivery Board has emphasised the importance of this region, positioning itself front and centre of the agenda, making a very positive start to a new regional town centre programme in 2018; and preparing to deliver transformative, visible change and implementing ‘quick wins’ in our centres in 2019.
2.2To date, five centres have been agreed by the Housing & Land Delivery Board at the meeting on 25 October 2018 for early focus/intervention; these are the first wave pilots of the new regional town centre programme. A Town Centre Working Group of council officials meets regularly and is working collaboratively on the agreed process. A clear work programme for the group detailing various stages of work and tasks has been collectively agreed (See Appendix A).
2.3The ‘further research’ stage in each of the centres has now been completed. This involved identifying the progress in each centre in terms of having a robust strategy/vision, supportive planning policy framework, a robust town centre health check and identified interventions with a view to having an ambitious draft Delivery and Investment Plan for each centre Q1 2019 that secures inclusive growth and town centre re-purposing. Each plan will be tailored to each centre but will share common elements and learning from each centre in terms of evidence, delivery mechanisms and interventions and the Working Group is identifying what those elements would be.
2.4Each centre is at a different stage but there is a consensus that delivery is critical and that the process must be flexible to avoid creating delay in the delivery of projects. Some key tasks will be undertaken in parallel with others so that they do not delay the formulation of interventions and investment in projects. Action and investment must drive the programme. 3.0 Town Centre Programme
Status Report on the Five Centres
3.1A summary of where each centre is in the process is set out below:
Bilston Planning Policy is to be reviewed through the Black Country Core Strategy Review. Baseline audit undertaken and being reviewed through the Black Country Core Strategy review. Initial work on possible interventions Primary intervention sites identified.
Bordesley Green Vision articulated through Bordesley Green Area Action Plan (Submission Version) Baseline health check undertaken (use class and vacancy rates). High Level interventions and key site opportunities identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing & Land Delivery Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.