Resolved
(1) The strategic risks contained within the WMCA Strategic Risk Register be noted. (2) The strategic risk register would return at the June ARAC with risk scoring updated.
Audit, Risk & Assurance Committee noted this item on Monday 15 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The strategic risks contained within the WMCA Strategic Risk Register be noted. (2) The strategic risk register would return at the June ARAC with risk scoring updated.
Senior Leadership Team (SLT) reviewed the register at its meeting of 13th March 2019 to ensure the register continues to reflect the key risks affecting WMCA at the present time.
Continuing work on the establishment and management of Directorate risk registers, it is anticipated Directorate risk registers will provide a focus on threats to delivery of organisational deliverables contained within the Annual Business Plan, and will also be aligned to the monitoring of performance indicators. This will support SLT members in providing clear oversight and visibility of risks requiring escalation to the Strategic risk register.
Senior Leadership Team has confirmed their intention to review the entire strategic risk register in the next few months in the context of the 2019/20 annual business plan. In preparation for this review, the Chief Executive has requested the attendance of the Chair of Audit, Risk and Assurance Committee during this risk discussion, and the register has been realigned to reflect the current risk score only for the intervening period.
18 strategic risks are currently recorded within the register with 7 risks rated as high (red) rated risks, 10 as medium (amber) risks and 1 rated as a low (green) risk. One risk has been closed during this reporting period.
3. Key risks
3.1Risk ID: S01 – Financial Assumptions for Existing Programmes
This risk continues to present the greatest risk to WMCA due to a funding shortfall in the Investment Programme. A prioritisation exercise is being undertaken and will be presented to the Investment Board in due course.
3.2Risk ID: S02 – Human Resources
Sustained progress has been made in managing the capacity and skills necessary to deliver the strategic objectives within tight timescales. This has been achieved by the appointment of the Investment and Commercial Activities Director to provide a full complement of Directors at SLT, a flexible approach to resources throughout the organisation, and the utilisation of specialist consultant services when required.
Resource requirements have been considered as part of the development of the 2019/20 budget and establishment of the annual business plan to ensure delivery of objectives can be achieved. This is being supported by the current review of the Corporate Services directorate by SLT, and will result in a future target operating model to be defined and implemented by the summer, ensuring the directorate has the capacity and skills to deliver an effective and efficient service to meet the continuing growth of WMCA. Major delivery programmes that have been established more recently have developed resource plans alongside business plans and budgets, including the provision of specialist support services where required.
With the increased clarity on resources, this risk has been reviewed by SLT and has been reduced from high to a medium rated risk.
3.3Risk ID: S07 – Delivery
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
WMCA Strategic Risk RegisterReport | 124 KB | DownloadRead as text |
PDF |
WMCA Strategic Risk Register_Mar 19 Final ARAC1Report | 134 KB | Download |
Follow Audit, Risk & Assurance Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Terms of Reference - To NoteResolved that: The Terms of Reference be noted. | Noted | Open |
| 14 Jul 2026 | West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Resolved that: The update be noted. | Noted | Open |
| 14 Jul 2026 | Annual Review Letter 2025/26Resolved that: The Local Government and Social Care Ombudsman’s annual review letter for 2025/26 be noted. | Noted | Open |
| 14 Jul 2026 | Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)... | Noted | Open |
| 14 Jul 2026 | Consideration of Private Internal Audit Reports(1) The contents of the latest Internal Audit Update Report and progress against delivery of the 2025/26 Internal Aud... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.