Resolved
That the current status of development for park and ride be noted.
Transport Delivery Committee noted this item on Monday 22 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the current status of development for park and ride be noted.
Transport Delivery Committee Date 22 July 2019
Report Title Park & Ride Update
Accountable Director Pete Bond, Director of Integrated Network Services
Accountable employee(s) Richard Mayes, Head of Park & Ride (interim)
Report has been reviewed Rail and Metro Lead Members’ Group (by email) by
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended:
1. To note the current status of development for Park & Ride (P&R).
1.0Purpose
1.1This report details the progress of Park & Ride site proposals already in delivery or development, since the previous report in January 2019. It also provides an update on the development of an overarching framework to govern future development, funding and management of Park & Ride sites.
2.0Park & Ride development activity
2.1Work has been continuing to develop and deliver a number of expansions at sites across the network.
2.2A summary of sites where work is continuing is provided in Table 1 below. Additionally a summary of other sites that are being considered in the context of the emerging strategy and development framework in Table 2.
Page 1 of 12 Table 1 – Ongoing Car Park Expansion projects (in alphabetical order)
A34 / M6 In conjunction with the Sprint development team, TfWM is considering Junction 7 options for a Park & Ride site on the A34 Sprint corridor, close to (Sprint) junction 7 of the M6, to act as an intercept for cars heading to Birmingham and Walsall. Work is ongoing to understand the demand profile at this location, in order to ensure that proposals are aligned with the expected usage. A number of possible sites have been identified and TfWM is working with these land owners and local authorities to understand the opportunities available.
Bradley Lane Construction work on the new 196 space car park was put on hold as (Metro) a result of the main contractor, Dawnus, entering administration on 14 March 2019. The first phase of works has required a focus on ground remediation because of former coal mine workings on the site and, through engagement with Dawnus’ main subcontractor, these works were satisfactorily completed. The next phase of work, to complete the embankment, steps and ramp, are due to recommence at the beginning of August. It is anticipated that work on the site will be completed prior to the end of 2019.
Longbridge Following receipt of planning permission in October 2018, and (Rail) subsequent confirmation of budget approval, the existing car park facility was closed on 19 May 2019. TfWM’s contractor then took over the site and work commenced immediately on delivering the five deck, multi-storey car park. With the optimum floor plan in place, following refinement to the design, the new facility is expected to have 629 spaces in total across the six levels. The site has been cleared and subterranean work has begun. It is anticipated that the car park will be completed and open for use in Spring 2020. As previously confirmed, a charge will be applied at Longbridge to help cover construction and operational costs, following an agreement by WMCA in February 2018. Further details regarding the development and delivery of user charging will be presented once proposals have been finalised.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Park and Ride UpdateReport | 229 KB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.