(1) It was noted that this report was being submitted to WMCA Board as a requirement of the WMCA Assurance Framework which stated Final Business Cases must be approved by WMCA Board. (2) The funding request of £2.15m for design and construction for enhanced works to the proposed scheme, which had passed through the Assurance Process and was recommended by Investment Board, was approved.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1In May 2019, a Change Request was submitted to the WMCA which included bringing the NEC Longabout within the scope of the OBC. This was approved by the WMCA Board in July 2019.
The NEC Longabout Programme
2.2Solihull Metropolitan Borough Council has reviewed this junction and with the support of detailed transport modelling consider that it is desirable to separate out traffic heading north on the A452 from traffic emerging from Northway onto the NEC Longabout. In order to achieve this, Solihull MBC is proposing a cut-through for the A452 northbound traffic which would allow traffic from Northway to be able to take an alternative route as a resilience plan along Bickenhill Parkway and provide extra capacity to the NEC Longabout. If the capacity on the NEC Longabout is increased, then queuing and delays reduce at Northway. This will provide both immediate and longer-term benefits to the area. The enhancements to the NEC Longabout would:
(a) Fully mitigate the problems encountered by HS2 traffic once the NEC Longabout becomes operational;
(b) Provide the resilience the NEC currently has on the network for event days; and
(c) Provide capacity required to enable UK Central (UKC) related development.
Oakervee Review
2.3The Oakervee Review concerning the future of HS2 is due to complete in Autumn 2019, with the initial construction works for the Longabout commencing in March 2020. Therefore, we expect that the decision on HS2 will have been taken before any significant abortive costs would have been incurred on the Longabout. Whilst the exact date of when the Oakervee review decision is announced is unknown, updated estimated cost profiling at this stage provides for expenditure for design works in November and December at £65,000 a month. Therefore, the maximum abortive costs would be £130,000.
3. Assurance Process
3.1The Final Business Case has been reviewed at various stages throughout the Assurance Process as follows: Technical Appraisal Panel (1 July 2019) Investment Advisory Group (2 September 2019) WMCA Strategic Leadership Team (25 September 2019) WMCA Investment Board (21 October 2019) WMCA Programme Board (25 October 2019)
3.2The business case was endorsed at each stage with conditions for improvement, which culminated in a number of amendments being required to the FBC. These amendments have all been made to the satisfaction of those respective Boards.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.