Resolved. 1. That the net revenue expenditure final outturn position for the 2019/20 financial year after contributions to earmarked reserves shows a minor adverse variance of £0.020m compared to budget and the final outturn position before contributions to earmarked reserves was a £1.274m favourable variance against forecast and a £3.839m favourable variance against budget be noted and 2. That the total capital expenditure to the end of March 2020 for the overall transport programme was £130.6 million, which was £72.0m below the budget of £202.6m and the actual costs were marginally below (£4m) the annual forecast of £134.6m be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Director Linda Horne Finance Director Tel 0121 214 7508 Email - [email removed] Accountable employee(s) Louise Cowen, Financial Services Manager Tel 0121 214 7454 Email - [email removed]
Report to be/has been Councillor Akhtar considered by
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended to:
1. Note that the net revenue expenditure final outturn position for the 2019/20 financial year after contributions to earmarked reserves shows a minor adverse variance of £0.020m compared to budget. The final outturn position before contributions to earmarked reserves was a £1.274m favourable variance against forecast and a £3.839m favourable variance against budget.
2. Note that total capital expenditure to the end of March 2020 for the overall transport programme was £130.6 million, which was £72.0m below the budget of £202.6m. Actual costs were marginally below (£4m) the annual forecast of £134.6m.
1. Purpose
1.1This report sets out the financial outturn position for 2019/20 subject to external audit.
1.2The content relates to the financial position of the Combined Authority’s Transport Delivery Revenue and Capital Budgets and consists of the following Sections:
Section A Summary TfWM Revenue Budget
Section B Summary TfWM Capital Budget Page 1 of 12 SECTION A
2. Summary Revenue Position
2.1The full year outturn position on the Transport revenue budget as at the end of March 2020 shows an overall minor adverse variance of £0.020m against budget.
2.2Excluding transfers to reserves, the full year Transport outturn represented a £3.839m favourable position against budget: an improvement of £1.274m on the £2.565m forecast favourable position reported in January 2020, which supports the 2020/21 budget position.
2.3The overall favourable variance to budget is primarily as a result of savings on concessionary travel as a result of lower patronage, the timing of recruitment activity and lower infrastructure and capital financing costs offset by the need to prudently provide for and recognise income drops as a result of the COVID-19 pandemic.
2.4The £1.274m variance from the £2.565m forecast movement to budget reported in January 2020 was due to final concessionary travel patronage and passenger information offset by the impact of COVID-19.
2.5The key favourable variances compared with the January 2020 forecast comprise:
A favourable £1.519m variance on travel concessions compared with forecast was due to further reductions in patronage in the latter part of the year. This extended the overall favourable variance to budget to £3.055m resulting from overall reductions in passenger volumes during the year as previously reported. Passenger Information delivered a £0.572m favourable variance to forecast after changes to cleaning contracts were implemented. This led to an overall favourable variance to budget of £0.166m. As further opportunities were taken in the latter part of the year to review marketing and communications activities, a further £0.149m favourable variance to forecast was delivered in Network Resilience. This contributed to the overall £0.501m variance to budget as a result of staffing variations and lower external advice requirements. The cost of Strategic Development delivered a £0.143m favourable variance to forecast as opportunities arose to use grants received to fund development activity. The overall position was an adverse variance of £0.106m to budget. Accessible Transport contract management delivered a £0.141m favourable variance to forecast owing to savings arising from revised contractual arrangements; a total favourable variance of £0.190m when compared with budget.
2.6The key adverse variances compared to the January 2020 forecast are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.