That progress of the Sprint Programme be noted; 2. That the relationship between Sprint delivery and the other schemes be noted and 3. That the service be operated by zero emission vehicles and the operator(s) would purchase the vehicles be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Chief Laura Shoaf, Managing Director, TfWM Executive 0121 214 7444 [email removed] Accountable Employee Sandeep Shingadia, Director of Development & Delivery, TfWM 0121 214 7169 [email removed] Report has been Sprint Lead Member Reference Group considered by
Recommendation(s) for action or decision:
Transport Delivery Committee is recommended to:
1. Note the progress of the Sprint Programme 2. Note the relationship between Sprint delivery and other local schemes 3. Note that the service will be operated by zero emission vehicles and the operator(s) will purchase the vehicles
1. Purpose
1.1The previous report to TDC outlined the aspirations for a network of Bus Rapid Transit (‘Sprint’). This report will update on progress on key deliverables for the first two routes, the A456 (Hagley Road), and future pipeline schemes. It will also update on the vehicle used on the route.
2. Priority deliverables and key achievements since last report
1 2.1 The A34 Walsall to Birmingham Sprint scheme is a Bus Rapid Transit proposal enhancing the link between Walsall Town Centre, Perry Barr and Birmingham City Centre, ultimately connecting to the HS2 station at Curzon Street.
2.2The A45 Birmingham to Airport and Solihull Sprint scheme is a Bus Rapid Transit proposal enhancing the link between Birmingham Airport, Solihull, and Birmingham City Centre, serving residents and businesses in Digbeth, Sheldon, and Yardley.
2.3It is intended that the A34 two schemes will operate as a cross city route, with direct services between Birmingham Airport and Walsall, and Solihull and Walsall.
2.4In order to reduce delivery risks it is intended that the routes will be completed over two phases; prior to the Commonwealth Games (CWG) and after the CWG. The first phase of delivery will provide all the shelters for the route and the most significant interventions to support bus journey time reliability.
2.5On 14th February 2020, the WMCA approved to fund the first of a two phase delivery of the A34/A45 cross city Walsall to Solihull and Birmingham airport route. This provided £42.3m for delivery of priority infrastructure on the routes, to be delivered before June 2022. It will also provide priority for existing public transport on these routes, and will pave the way for articulated vehicles, which are planned to be incrementally introduced to the Sprint corridor from January 2023.
2.6On 11th March 2020, the DfT also agreed to devolve the previously retained £35m towards the A45 (subject to construction contract entered into within 6 months). In total, with WMCA, devolved DfT, and other contributions from the City Centre Bus Fund, Ministry of Housing, Communities & Local Government, and Transforming Cities funding combined, the phase 1 budget for A34/A45 routes stands at £87.8m.
2.7The provision of this funding has enabled TfWM to enter into a further Early Contractor Involvement (ECI)/Construction contract, which has discharged the DfT condition noted above.
2.8The scheme will complement other major schemes in the area, notably Perry Barr station, Perry Barr bus interchange, the Perry Barr highway scheme, and the development of the Athletes village. TfWM is working with Birmingham City Council to ensure that the A34 scheme is considered and integral to any scheme design, ensuring that sustainable travel alternatives can be offered to complement or mitigate the impact of other schemes. A Perry Barr Coordination Group oversees collaboration between this interdependent projects, in addition Sprint progress is reported to the CWG Committee in conjunction with all CWG identified schemes.
2.9In Birmingham and Solihull, TfWM have already attained Cabinet approval or the Cabinet has delegated the decision to the Transport Cabinet member and/or senior officers within the relevant Local Authority. Work is progressing on obtaining Cabinet approvals for Sandwell and Walsall.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.