(1) The capital funding request of £7.7m to fund the development of a brand new City of Wolverhampton College Technical Centre that would be situated at the rear of the College’s existing Wellington Road campus and form Phase 1 of the wider City Learning Quarter Programme was approved. (2) It was noted that the WMCA Programme Assurance & Appraisal team had undertaken both independent assurance and investment appraisal on the business case submission and their respective reports were attached to support the consideration of the business case. (3) It was noted that this investment was approved by the Investment Board on 29 June as noted in the minutes attached at agenda item 15, minute no. 12.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title City Learning Quarter (Phase 1) - College of Wolverhampton Technical Centre Business Case
Portfolio Lead Finance - Councillor Bob Sleigh
Accountable Chief Laura Shoaf, West Midlands Combined Authority Executive email: [email removed]
Accountable Employee Ian Martin, Director of Investment & Commercial Activity email: [email removed]
Zareena Ahmed- Shere (City of Wolverhampton Council)
Recommendation(s) for action or decision:
The WMCA Board is recommended to:
(1) Note that, in accordance to the Single Assurance Framework, the City of Wolverhampton Council have submitted a Full Business Case (FBC) requesting funding WMCA to approve the capital funding request of £7.7 million to fund the development of a brand new City of Wolverhampton College Technical Centre (CoWTechC) that will be situated at the rear of the College’s existing Wellington Road campus and forms Phase 1 of the wider City Learning Quarter (CLQ) Programme.
(2) Note that the WMCA Programme Assurance & Appraisal team have undertaken both independent assurance and investment appraisal on the business case submission and their respective reports are attached to support the consideration of business case.
At the point of this appraisal activity, the key risks and opportunities highlighted by WMCA Appraisal team to City of Wolverhampton Council are:
The key risks which have been identified through reading the CowTechC business case are: a. A vast amount of the benefits associated with this intervention are from the wider CLQ Programme. Funding for this phase is not certain. It would be useful to establish how advanced discussions for funding are and the level of uncertainty around Programme delivery.
b. If the market value of the current Paget Road side is not known, it is not clear what the scope of the proceeds will be used to fund upon its sale. There is uncertainty over the remaining balance which is required to pay down borrowing which will in turn improve the financial standing and stability of the college. If there is no remaining balance, will further funds be requested from WMCA or another funder and/or how will the future operation of the college be safeguarded?
c. There were numerous omissions within the Financial Case which would be expected at FBC stage such as quantified cost breakdowns, cash flow statements and an assessment of capital/revenue costings. These have now been disclosed and WMCA Finance will need to review before Investment Board to make a fair financial judgement.
d. It is not clear if Wolverhampton Council have contracted Turner & Townsend for projects before and if so, did this model prove successful for delivery? Examples would be useful to evidence this.
e. Following on from what happened with Carillion, it would be useful to understand if financial due diligence been undertaken on Wates and/or the selected construction contractor and what their success rate for delivery of similar projects is.
The key opportunities which have been identified through reading the CowTechC business case are:
a. The relocation to brownfield land just under 0.5 miles away from both Wolverhampton Railway Station and Wolverhampton Bus Station will increase accessibility for students. Additionally, the Midlands Metro is immediately adjacent with links to Birmingham and its surrounding areas.
b. With a strong BCR of 6.7:1, this project will provide 5499 learner assists in the first 10 years of operation, some £46 million of economic benefit will also delivered by 2041.
c. With IC engines being phased out by 2030, there is a key opportunity for the college to work with upcoming projects across the region such as the UK Battery Industrial Centre and Very-Light Rail which focus on green technologies.
d. The option to refurbish the existing site will cost £40m compared to the £7.7m needed to relocate to a new and improved site. In addition, the fruition of outputs would decrease which discounts refurbishment as a viable option.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.