(1) It was noted that the year to date position as at the end of November 2022 against the Transport for West Midlands revenue budget showed an adverse variance of £0.6m. (2) It was noted that the Transport for West Midlands capital programme expenditure as at the end of November 2022 totalled £181m, which was £78.6m below budget.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Director Linda Horne Executive Director of Finance and Business Hub E-mail - [email removed]
Accountable Employee Kate Taylor Head of Finance Business Partnering and Strategic Planning E-mail - [email removed] Report has been Councillor Pervez Akhtar considered by
Recommendation(s) for action or decision:
The West Midlands Transport Delivery Committee is recommended to: (1) Note the year to date position as at the end of November 2022 against the TfWM Revenue Budget shows an adverse variance of £0.6m, as detailed in Section A.
(2) Note the TfWM Capital Programme expenditure as at the end of November 2022 totals £181m, which is £78.6m below budget, as detailed in Section B. 1. Purpose
1.1This report sets out the financial position as at 30 November 2022. The content relates to the financial position of the Combined Authority’s Transport Delivery Revenue and Capital Budgets and consists of the following Sections:
Page 1 of 9 SECTION A
2.0Section A - Summary Revenue Position
2.1The year to date position on the Transport revenue budget as at the end of November 2022 shows an adverse variance of £0.6m against budget.
Novembet 2022 Year to Date Full Year Actual Budget Variance Forecast Budget Variance £'000 £'000 £'000 £'000 £'000 £'000 Net TfWM Surplus / (Deficit) before reserves 420 (3,641) 4,061 (9,150) (9,078) (72) Use of Reserves 1,384 6,048 (4,664) 9,179 9,078 101
2.2The most notable variance at this early stage of the year relates to Concessions where there is lower than budgeted patronage and fare levels.
These savings have been partly offset by lower than budgeted drawdown of reserves to support the overall budget as they have not yet been required.
2.3As noted in the previous report, the key movements within the full year position reflects an increase in the MML operating costs of £4.2m to reflect ongoing cost pressures and revenue lost during the service shutdown. This increase has been offset by additional Local Transport Fund (LTF) grant of £1.8m and non-pay savings of £2.5m.
2.4Further details of net spending are set out in Appendix 1.
SECTION B
3.0Summary Position TfWM Capital Budget 3.1 Overall, TfWM Capital Programme expenditure totalled £181m which was £78.6m below the year to date budget of £259.6m, with the variance primarily contained within the Investment Programme portfolio (£35.2m).
YEAR TO DATE - NOVEMBER 22 FULL YEAR TRANSPORT PROGRAMME ACTUAL BUDGET VARIANCE FORECAST BUDGET VARIANCE £000 £000 £000 £000 £000 £000
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies