Transport Delivery Overview & Scrutiny Committee Date 4th September 2023
Report title CRSTS re-base proposal
Portfolio Lead Transport - Councillor Mike Bird
Accountable Chief Anne Shaw, Executive Director, Transport for Executive West Midlands Email: [email removed] Accountable Carl Beet, Head of Transport Strategy and Employee Planning, TfWM [email removed] Report has been Strategic Transport Board – 27th July 2023 considered by 1. Purpose*
1.1This note provides an update to Transport Delivery Overview & Scrutiny Committee (TDOS) on the City Region Sustainable Transport Settlement (CRSTS), specifically regarding a re-baselining exercise that is currently being undertaken across the programme.
2. Background*
2.1The CRSTS is a £1.05bn programme of transport improvements across the West Midlands. The programme is spread over a 5-year funding period covering financial years 2022/23 – 2026/27 with a requirement that all funding is spent and all delivery complete by the end of March 2027.
2.2In the Spring Budget it was announced that £8.8bn would be available nationally for the second round of CRSTS (CRSTS 2). The WMCA allocation for this has not yet been determined.
Re-base context
2.3A number of CRSTS eligible MCA’s have raised that, given the high rate of inflation since the creation of the original programme, delivery of all the outputs outlined in initial programmes developed over 2021 and submitted in January 2022 will be unaffordable. In acknowledgment of this, the Department for Transport and HM Treasury have agreed to permit a one time only re-base of the CRSTS programme.
2.4This re-base must be agreed locally before being submitted to DfT by 29th September 2022 for approval. The following conditions must be met as part of this exercise: • Projects can be removed from the programme or added but DfT have emphasised this should not be seen as an opportunity to introduce brand new initiatives. • All projects must align with the objectives of the national CRSTS programme. • The total funding envelope must remain the same. • Overall, the target 15-20% local contribution must be met. • The outputs can be reduced. • The funding time horizons must remain the same (spend and delivery by March 2027). • The re-based programme submitted to DfT will need to demonstrate that it still delivers good value for money.
WMCA re-baselining process
2.5In June 2023, TfWM issued a template to representatives from the 7 constituent authorities to provide them with an opportunity to re-base their CRSTS schemes. Sponsors were requested to consider their allocation under two scenarios:
• 1. 5 year re-base within CRSTS 1 – promoters could redistribute their funding allocation within the current 5 year programme (2022/23 – 2026/27) for example by removing projects or reducing project scope. The total funding over 5 years for each authority cannot exceed the allocation from the CRSTS baseline. • 2. 10 year re-base over CRSTS 1 & 2 – promoters could redistribute the profile of funding over a 10-year scenario by moving some spend into the CRSTS 2 period (2027/28 – 2031 / 32). The total funding in the CRSTS 1 period (2022/23 – 2026/27) cannot exceed the CRSTS baseline allocation for the authority.
2.6The completed templates have now been submitted to WMCA to allow a West Midlands wide view to be developed, prior to local political ratification by promoting authorities and the Mayor. Once a local political consensus has been agreed, the revised programme will submit to WMCA Board for approval on 15th September, in advance of submission to DfT.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CRSTS Re-base ProposalReport | 179 KB | DownloadRead as text |
Follow Transport Delivery Overview & Scrutiny Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2026 | Member Engagement Groups – Progress ReportIt was agreed that this matter would be brought to the May meeting as a potential focus for committee’s 2026/27 work ... | Agreed | Open |
| 8 Sep 2025 | Exclusion of the Public and PressThe public and press be excluded from the meeting for the following item of business under s100(A) of the Local Gover... | Decided | Open |
| 10 Mar 2025 | Presentation on WMCA Air Quality Sensor Network and WebsiteThe report be noted | Noted | Open |
| 10 Mar 2025 | Railways Bill ConsultationThe report be noted. | Noted | Open |
| 10 Mar 2025 | Capital Performance Report (February 2025)The committee report and dashboard be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.