Resolved
(1) The report was noted. (2) A further report be submitted to a future meeting of the committee when there was greater clarity regarding the funds available for rail mprovements following the cancellation of HS2 north of Birmingham.
Transport Delivery Overview & Scrutiny Committee noted this item on Monday 11 December 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The report was noted. (2) A further report be submitted to a future meeting of the committee when there was greater clarity regarding the funds available for rail mprovements following the cancellation of HS2 north of Birmingham.
2.1The Prime Minister announcement the cancellation of HS2 Phases 2a, 2b and subsequently HS2 East in his speech at the Conservative Party Conference on 4 October 2023. 2.2 This was accompanied by an announcement to reprioritises spending on transport across the north, the Midlands and in other parts of England as part of a new “Network North” initiative.
3. Cancellation of HS2 north of the West Midlands: Overview
3.1The Government will deliver:
• HS2 Phase 1 between West Midlands to London Euston. There will be two branches: one to central Birmingham; and one to Handsacre, on the West Coast Main Line (WCML) near Lichfield. Passengers from London will be able to travel on through HS2 trains via Handsacre to Manchester, Liverpool and Scotland.
Government will not proceed with: • HS2 Phase 2a - Handsacre to Crewe • HS2 Phase 2b - Crewe to Manchester Piccadilly • HS2 West Midlands to East Midlands Parkway
Government had already previously cancelled the following: • HS2 Phase 2b Connection to WCML near Wigan • HS2 East Midlands to Leeds and East Coast Main Line near York
Euston Station and HS2 Services
3.2Completion of HS2 Euston station will be dependent on securing private finance from developers and will be reduced in size from 10 platforms to 6, which should be able to accommodate:
• 3 trains per hour (up to 400m long) via old Oak Common to the West Midlands Interchange and Birmingham Curzon stations • 5 trains per hour to destinations in the North West and Scotland via Handsacre Junction. These trains will be restricted to 200m (with less capacity than the current Pendolino trains) unless new longer platforms at existing stations can be provided which would not appear to be possible at constrained locations such as Manchester Piccadilly. • Plans for HS2 services to the North West and Scotland from both Birmingham Curzon Station and the West Midlands Interchange Station were dependent on the infrastructure and on-train capacity provided by the HS2 Phase 2a/b sections to Crewe and Manchester.
3.3This reduction in platforms also means the station will not be able to cope with any additional HS2 services should the decisions not to proceed with either Phases 2a, 2b and HS2 East be reversed.
3.4A new development company, separate from HS2 Ltd, will manage the delivery of Euston and aims to deliver 10,000 new homes surrounding the station.
3.5Until Euston station has been completed it is envisaged that a 6 train per hour service should be able to operate to/from the Old Oak Common Interchange in West London. 3.6 At Old Oak Common connections will be available to Great Western train services and with the new Elizabeth Line services to Heathrow, Paddington Station, Bond St, Tottenham Court Road, Liverpool St Station, Stratford QE Park and Canary Wharf.
Removal of safeguarding for the previous HS2 alignment
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HS2: Cancellation of Phases 2a, 2b and HS2 EastReport | 153 KB | DownloadRead as text |
PDF |
WMCA Board Paper: Update on HS2 Announcements and Network North FundingReport | 324 KB | Download |
Follow Transport Delivery Overview & Scrutiny Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2026 | Member Engagement Groups – Progress ReportIt was agreed that this matter would be brought to the May meeting as a potential focus for committee’s 2026/27 work ... | Agreed | Open |
| 8 Sep 2025 | Exclusion of the Public and PressThe public and press be excluded from the meeting for the following item of business under s100(A) of the Local Gover... | Decided | Open |
| 10 Mar 2025 | Presentation on WMCA Air Quality Sensor Network and WebsiteThe report be noted | Noted | Open |
| 10 Mar 2025 | Railways Bill ConsultationThe report be noted. | Noted | Open |
| 10 Mar 2025 | Capital Performance Report (February 2025)The committee report and dashboard be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.