(1) The financial position as at 30 November 2023 was noted. (2) The latest forecast for 2023/24 was noted. (3) The new grant awards to the WMCA, and the arrangements for these grants, were noted. (4) The intention to enter into contracts with local authorities for year-three activity following the Department for Levelling Up, Housing & Communities relaxing the carry forward requirements which applied to the UK Shared Prosperity Fund was noted. (5) It was noted that under the delegation provided by the WMCA Board on 17 November 2023, the Section 151 Officer recently approved the acceptance of the £100m funding for brownfield regeneration, secured as part of the Trailblazer Devolution Deal. (6) The additional funding awarded to the region for highways maintenance works, as part of the Government’s Network North plan, was noted and the proposed allocation of this funding was endorsed. (7) The treasury and prudential indicators for the period ended 30 November 2023 were noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Chief Laura Shoaf, West Midlands Combined Authority Executive email: [email removed]
Accountable Linda Horne, Executive Director of Finance and Employee Business Hub email: [email removed]
Report has been WMCA Executive Board – 3 January 2024 considered by WM FDs – 4 January 2024
Recommendation(s) for action or decision:
WMCA Board is recommended to:
(1) Note the financial position as at 30 November 2023, as detailed in Sections 2 and 3.
(2) Note the latest forecast for 2023/24 as detailed in Section 4.
(3) Note the new grant awards to the WMCA as outlined in Section 5, and the arrangements for these grants.
(4) Note the intention to enter into contracts with Local Authorities for year three activity following DLUHC relaxing the carry forward requirements which apply to the UK Shared Prosperity Fund, as outlined in Section 5.
(5) Note that under the delegation provided by WMCA Board in November 2023, the WMCA Section 151 Officer recently approved the acceptance of the £100m funding for Brownfield regeneration, secured as part of the Trailblazer Devolution Deal (Section 5).
(6) Note the additional funding awarded to the region for Highways Maintenance works, as part of the Government’s Network North plan, and endorse the proposed allocation of this funding.
(7) Note the Treasury and Prudential indicators for the period ending 30 November 2023 as outlined in Section 7 and Appendix 6 of this report.
Page 1 of 27 1.0 Purpose
1.1To provide an update on the Combined Authority’s financial position based on the information known at the end of November 2023. The report includes capital and revenue financial performance, explanations for variations, an update on the likely outturn for 2023/24 and risks which are being managed by the Authority.
2.02023/24 Year to Date Revenue Position
2.1Appendix 1 shows the overall consolidated revenue position for the West Midlands Combined Authority, whilst Appendices 2 to 4 present the detailed summaries for Transport, the WMCA Portfolios and the Mayoral office, respectively.
2.2The position at the end of November is a surplus of £4.2m which is a favourable variance from budget of £4.1m (as compared to the position at September 2023 of £3.9m).
2.3Within Transport there is a surplus of £2.7m which represents a favourable variance from budget of £2.2m. The year to date position is due to the impact of staffing vacancies as well as receipt of Local Transport Fund grant which will meet contractual costs of the tendered bus service across the rest of the fiscal year. Concessionary related underspends have arisen due to patronage remaining below pre pandemic levels. In line with agreement from the Board, these savings have been transferred to a reserve to protect against future transport network risks, £2.0m to date.
2.4Within the Portfolio budgets there is a favourable variance of £1.9m due to staff vacancies, underspends on external advice and receipt of new grant income. There remain underspends against the grants within Economic Skills and Communities totalling £27.2m to date, including AEB, Multiply, Digital Skills and UKSPF. This position is only of timing, with fully recovery of the position anticipated at year end.
2.5The Mayoral Office position as at the end of November 2023 was in line with budget.
3.02023/24 Capital Programme Position
3.1Appendix 5 sets out the position on the Capital Programme as at the end of November 2023. Actual costs totalled £229.5m, resulting in a favourable variance of £140.3m against a phased budget of £369.8m. This means that around 62% of the planned programme has been delivered in line with original phasing.
3.2The year to date expenditure to budget variance is primarily contained within Transport (£60.8m), Housing and Regeneration (£23.8m) and a further £54.9m within the capital programme delivered externally by Local Authorities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.