CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
West Midlands Combined Authority
Audit, Risk & Assurance Committee, Monday 15 July 2024 at 10.00am

Internal Audit Update Report

Noted Finance 3 papers

Audit, Risk & Assurance Committee noted this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

(1) The contents of the latest internal audit update report be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Audit, Risk & Assurance Committee

Internal Audit Update Report – 15 July 2024

Contents Page Number Introduction 2 Progress Summary (2023/24 2-3 Internal Audit Plan) Progress Detail (2023/24 Internal 4-6 Audit Plan) Progress Summary (2024/25 6 Internal Audit Plan) Follow-up of previous 6-8 recommendations Appendices Appendix A – Investment 9 programme M&E Report 1. Introduction

The purpose of this report is to bring the Audit, Risk and Assurance Committee (ARAC) up to date with the progress made against completing delivery of the 2023/24 internal audit plan.

The Audit, Risk and Assurance Committee has a responsibility to review the effectiveness of the system of internal controls and to monitor arrangements in place relating to corporate governance and risk management arrangements. Internal audit is an assurance function which provides an independent and objective opinion to the organisation on the control environment, comprising risk management, control, and governance.

This update provides the committee with information on recent audit work that has been carried out since the previous update in March 2024, and to assist them in discharging their responsibility by giving the necessary assurances on the system of internal control.

This progress update has been split to provide updates on work undertaken to progress completion of the 2023/24 Internal Audit Plan and updates on work undertaken on audits contained within the 2024/25 Internal Audit Plan.

Where appropriate each report issued during the year is given an overall opinion based on the following criteria:

No Assurance Limited Satisfactory Substantial Immediate action is Significant gaps, There is a generally A sound system of required to address weaknesses or non- sound system of governance, risk fundamental gaps, compliance were governance, risk management and weaknesses or non- identified. Improvement management and control exists, with compliance identified. is required to the system control in place. Some internal controls The system of of governance, risk issues, non-compliance operating effectively and governance, risk management and or scope for being consistently management and control to effectively improvement were applied to support the control is inadequate to manage risks to the identified which may put achievement of effectively manage risks achievement of at risk the achievement objectives in the area to the achievement of objectives in the area of objectives in the area audited. objectives in the area audited. audited. audited.

2. Progress Summary (2023/24 Internal Audit Plan)

The following internal audit reviews have been completed or are in progress in relation to the 2023/24 Internal Audit Plan.

Page 2 of 8 ANA1 Auditable area Level of assurance obtained Rating Internal Audit Reviews previously reported Adult Education Budget High Satisfactory External Funding Arrangements High Satisfactory

Gifts and Hospitality arrangements High Limited

Health & Safety Medium Satisfactory

KFS – Budgetary Control High Substantial

KFS – General Ledger High Substantial

KFS - Payroll High Satisfactory

KFS – Treasury Management High Satisfactory

KFS - Accounts Payable High Satisfactory KFS – Accounts Receivable High Satisfactory National Fraud Initiative Medium Satisfactory Audit reviews completed this period Investment Programme Monitoring & Evaluation High Satisfactory Audits in progress Status Adult Education Budget – Procurement High Draft report issued – awaiting management response Contract Management High Development plan issued – awaiting management response Swift High In progress Business Continuity Medium Draft report issued – awaiting management response Operator Charging Medium Deferred to 2024/25 Internal Audit Plan UK shared prosperity fund Medium Deferred to 2024/25 Internal Audit Plan

1 Audit Needs Assessment rating

Page 3 of 8 ANA1 Auditable area Level of assurance obtained Rating Energy efficiency retrofit Medium Draft report issued – awaiting management response

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit Update ReportReport 193 KB DownloadRead as text
PDF
Enc. 2 for Internal Audit Update ReportReport 258 KB Download
PDF
Internal Audit Update ReportReport 142 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
MS
Mark SmithChair, present
NB
Councillor Nicholas BardsleyCommittee Member - Voting, present
RB
Councillor Richard Baxter-PayneCommittee Member, present, as expected, virtual
RL
Councillor Ram Lakha OBECommittee Member - Voting, present
EF
Councillor Edward FitterCommittee Member - Voting, present
JJ
Councillor Jaspreet JaspalCommittee Member - Voting, present
TJ
Councillor Thomas JohnstonCommittee Member - Voting, present
WL
Councillor Wayne LittleCommittee Member - Voting, present
RM
Councillor Rose MartinCommittee Member - Voting, present
KM
Councillor Karen McCarthyCommittee Member - Voting, present
JP
Councillor Jacquie PrestwoodCommittee Member, present
IW
Councillor Ian WoodallCommittee Member - Voting, absent

On this subject at West Midlands Combined Authority

Search all
  1. Internal Audit Update ReportThis decision
  2. Consideration of Private Internal Audit ReportsNoted
  3. Consideration of Private Internal Audit ReportsAgreed
  4. Internal Audit CharterApproved
  5. Internal Audit Outturn 2024-25 & Update ReportNoted
  6. Consideration of Private Internal Audit ReportsNoted

More from West Midlands Combined Authority Audit, Risk & Assurance Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Terms of Reference - To NoteResolved that: The Terms of Reference be noted. Noted Open
14 Jul 2026 West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Resolved that: The update be noted. Noted Open
14 Jul 2026 Annual Review Letter 2025/26Resolved that: The Local Government and Social Care Ombudsman’s annual review letter for 2025/26 be noted. Noted Open
14 Jul 2026 Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)... Noted Open
14 Jul 2026 Consideration of Private Internal Audit Reports(1) The contents of the latest Internal Audit Update Report and progress against delivery of the 2025/26 Internal Aud... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies