Annual Accounts 2023/24 for West Midlands Combined Authority
ApprovedFinance4 papers
Audit, Risk & Assurance Committee approved this item on Thursday 5 December 2024. Below is the council's own wording, with the papers it was decided on.
(1) The WMCA’s annual accounts for 2023/24 be approved. (2) The Audit Findings Report for 2023/24 presented by Grant Thornton be noted. (3) That Grant Thornton proposed to issue an unqualified audit opinion for the accounts be noted. (4) The signing of the letter of representation by the Executive Director of Finance and Business Hub as set out in Appendix F of the Audit Findings Report be approved. (5) That the Chair of Audit, Risk and Assurance Committee be authorised to sign off any further changes required to the Statement of Accounts for 2023/24 prior to their publication be approved. (6) Subject to no further issues being raised by Grant Thornton, approve that the Mayor and the Executive Director of the Finance and Business Hub be authorised to sign the accounts on behalf of the WMCA be agreed. (7) The Auditor’s Annual Report on WMCA for the year ended 31 March 2023 be noted. (8) Publication of the Auditor’s Annual Report on the WMCA’s website be approved.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Name of meeting: Audit, Risk and Assurance Committee
Meeting date: 05 December 2024 Annual Accounts 2023/24 for West Midlands Combined Report title: Authority
Linda Horne, Executive Director of Finance and Business Responsible Director: Hub Email: [email removed]
Report author: Louise Cowen, Head of Finanical Management Email: [email removed]
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
Recommendations The Audit, Risk and Assurance Committee is asked to:
(1) Approve the WMCA’s annual accounts for 2023/24. (2) Note the Audit Findings Report for 2023/24 presented by Grant Thornton. (3) Note that Grant Thornton propose to issue an unqualified audit opinion for the accounts. (4) Approve the signing of the letter of representation by the Executive Director of Finance and Business Hub as set out in Appendix F of the Audit Findings Report. (5) Approve that the Chair of Audit, Risk and Assurance Committee be authorised to sign off any further changes required to the Statement of Accounts for 2023/24 prior to their publication. (6) Subject to no further issues being raised by Grant Thornton, approve that the Mayor and the Executive Director of the Finance and Business Hub be authorised to sign the accounts on behalf of the WMCA. (7) Note the Auditor’s Annual Report on West Midlands Combined Authority for the year ended 31 March 2023. (8) Approve publication of the Auditor’s Annual Report on the Combined Authority’s website.
Voting Requirements A simple majority of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendation/proposition for it to become a decision of the board. 1. Executive Summary 1.1 This report has been prepared to enable the Audit, Risk & Assurance Committee to approve the annual accounts for the West Midlands Combined Authority (WMCA) for the financial year ended 31 March 2024. WMCA’s draft Audit Findings Report is also presented (Appendix 2) along with the WMCA’s Auditor’s Draft Annual Report (AAR) for the year ended 31 March 2024, which summarises the key findings arising from the work carried out by the external audit team at Grant Thornton is also presented (Appendix 3). The AAR provides a commentary on the results of Grant Thornton’s work to the Authority and to external stakeholders.
2. Matters for Consideration
2.1The WMCA’s draft statutory financial statements for 2023/24 were published on the WMCA’s website on 28 June 2024 and were also subsequently shared with members of the Committee on 8 July 2024. The draft accounts were reviewed by the Chair of the Committee and certified by the Executive Director of the Finance and Business Hub ahead of their publication.
2.2The majority of the audit process has now been completed without any significant issues to report and the following are attached for review and approval:
i) West Midlands Combined Authority financial report 2023/24 (Appendix 1) ii) Grant Thornton Audit Findings Report (including Letter of Representation - Appendix F) (Appendix 2) iii) Grant Thornton Auditor’s Draft Annual Report (Appendix 3)
Annual Accounts
2.3The West Midlands Combined Authority Board has received regular financial monitoring updates throughout 2023/24. The final outturn position for 2023/24 was reported to West Midlands Combined Authority Board on 14 June 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Risk & Assurance Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.