Resolved
(1) The progress on programme delivery be noted.
Investment Zone Board noted this item on Thursday 5 December 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The progress on programme delivery be noted.
WM INVESTMENT ZONE – PROJECT STATUS OVERVIEW Appendix A
PERIOD October-December 2024 DATE OF 5th December 2024 COVERED REPORT
WM INVESTMENT ZONE – REGIONAL REVENUE Overall Project Status PROJECTS SRO Steve Bowyer, Head of WM Investment Zone • Supply Chain Transition Fund – Specification in development; Tender publication December. • Equity Fund – discussions ongoing with MindForge, along with potential complementary Progress To investment routes. Date • Investment & Promotion – strong profile for WMIZ through DBT engagement. Proposal for 2025/26 to be incorporated into wider Economic Delivery Vehicle discussions. • Capacity Budgets – 2024/25 agreed and largely issued; 5-year allocations approved. RED: Route for deploying Equity Fund unresolved which could result in underspend for year Top Risk and/or risks to investment. Mitigation: Further discussions with MindForge and partners; aim for conclusive officer recommendation at December Programme Overview Group. Anticipating an underspend against profiled budget this year which may also impact on outputs. Finance Further discussions to be held with MHCLG but no ramifications anticipated. • Publish Supply Chain Transition Fund tender. Upcoming • Progress Equity Fund proposition. Priorities • Develop commission for Investment & Promotion 2025/26. • Finalise any outstanding 2024/25 capacity awards and resolve agreements for full term.
Overall Project BIRMINGHAM KNOWLEDGE QUARTER Status SRO Philip Nell, Strategic Director, Place Prosperity & Sustainability, Birmingham City Council Key challenges now beginning to be addressed: • Resource Plan for BCC capacity prepared and to be considered at December Cabinet meeting and subsequent governance processes (including Commissioners). Progress • Although Strategic Board not yet in place, initial shadow meeting planned for January 2025. to Date • Coherence around a single BKQ vision and proposition (to be presented ahead of Dec WMIZ Board). • Masterplanning in progress – integrated draft spatial plan expected end January 2025. • Strategic Outline Cases for capital investment submitted to SAF. AMBER: Ongoing lack of formal Partnership Board inhibits cohesion and decision-making. Top Risk Mitigation: Legal adviser commissioned to prepare collaboration agreement to be prepared. Commercial basis for partnership to be explored urgently through dedicated partner session. Finance Potential slight underspend on capital spend forecast for 2024/25 (within tolerances overall). • Develop draft collaboration agreement and draft ToR for Strategic Programme Board. • Agreement of new BKQ proposition. Upcomin • Approval of BCC Cabinet Report containing key IZ capacity arrangements. g • Develop draft spatial plan and narrative for workshop to be held during Jan. Priorities • Commence options appraisal for development of FBCs for capital projects. • Announcement of key investor commitment by BKQ partner. WM INVESTMENT ZONE – PROJECT STATUS OVERVIEW Appendix A
PERIOD October-December 2024 DATE OF 5th December 2024 COVERED REPORT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for WM Investment Zone: Programme ReportReport | 112 KB | DownloadRead as text |
PDF |
West Midlands Investment Zone: Update ReportReport | 157 KB | Download |
Follow Investment Zone Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Mar 2025 | Programme Update and Year 1 Review(1) The progress of programme delivery since the last meeting of the board be noted. (2) The Year 1 Review be endorse... | Noted | Open |
| 6 Mar 2025 | West Midlands Investment Zone - Strategic Delivery Plan 2025/26The Strategic Delivery Plan be endorsed for the implementation of the West Midlands Investment Zone for 2025/06. | Decided | Open |
| 5 Dec 2024 | Coventry and Warwick Gigapark Full Business Case(1) The full business case for the Coventry and Warwick Gigapark, including the comments from the Investment Panel, b... | Noted | Open |
| 5 Dec 2024 | Warwick District Council Local Growth Initiatives(1) The list of growth initiatives proposed by Warwick District Council, including the proposals for the Abbey Fields... | Approved | Open |
| 3 Oct 2024 | West Midlands Investment Zone – Programme Status ReportThe progress of programme delivery be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.