Birmingham Eastside Extension Sections 3 & 4 Full Business Case Update

Noted Committee 4 papers

WMCA Board noted this item on Friday 9 May 2025. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

(1) The comments of the Investment Board at its meeting on 7 April 2025 were noted. (2) The business case refresh for Birmingham Eastside extension sections 3 and 4 were approved, noting the very high value for money outcome assessment. (3) The budget and funding strategy for delivery of up to £107m for Birmingham Eastside extension phase 2 was approved, noting that in approving the funding strategy, a City Region Sustainable Transport Settlement 2 pre-commitment of £44.2m would be made to meet the costs of the extension which fell into the City Region Sustainable Transport Settlement 2 period (post-March 2027). (4) The Executive Director of Transport for West Midlands was authorised, in consultation with the Section 73 Officer, to accept target cost project proposals from Midland Metro Alliance for Birmingham Eastside extension phase 2 if they did not exceed the budget and funding strategy for delivery in the revised business case, noting: (i) that the commitment of the full budget was conditional on the proposed funding strategy being outside of the Department for Transport’s change control requirements; (ii) that the commitment of the full budget and entering any contract(s) was conditional on the target cost 2 costs being authorised. (5) The Executive Director of Transport for West Midlands was authorised to negotiate with HS2 Ltd and the Department of Transport the necessary interface arrangements and any third-party interests in land required to deliver Birmingham Eastside extension phase 2, with the final interface agreement to be approved in consultation with the Section 73 Officer and the Monitoring Officer. (6) The Chief Officer (Law, Governance & Audit) was authorised to take all necessary steps to give effect to the above resolutions, including (but not limited to) the negotiation and execution of all necessary legal documents as required to deliver Birmingham Eastside extension phase 2 and to enter into any relevant agreement with HS2 Ltd and the Department for Transport.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Name of meeting: WMCA Board

Meeting date: 09 May 2025 Birmingham Eastside Extension Sections 3 & 4 FBC Report title: Update Anne Shaw, Executive Director for Transport for West Responsible Director: Midlands Report author: Sushama Kumari, Project Sponsor

Key Decision? Yes

Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?

☐Yes ☒No

(If Yes – please contact the Member Relationship Manager to manage this process)

Recommendations WMCA Board is recommended to:

(1) Note Investment Boards comments in section 6.2

(2) Approve the business case refresh for Birmingham Eastside Extension sections 3 & 4 (BEE Phase 2), noting the very high value for money outcome assessment.

(3) Approve the budget and funding strategy for delivery of up to £107m for BEE Phase 2, noting that in approving the funding strategy, a CRSTS Round 2 pre-commitment of £44.2m will be made to meet the costs of the extension which fall into the CRSTS2 period (post March 2027).

(4) Authorise the Executive Director for Transport in consultation with the Section 73 Officer to accept Target Cost Project Proposals from Midland Metro Alliance for BEE Phase 2 if they do not exceed the budget and funding strategy for delivery in the revised business case noting: o that the commitment of the full budget is conditional on the proposed funding strategy being outside of DfT change control requirements. o that the commitment of the full budget and entering any contract(s) is conditional on the Target Cost 2 costs being authorised

(5) Authorise the Executive Director for Transport for West Midlands to negotiate with HS2 and the Department of Transport the necessary interface arrangements and any third-party interests in land required to deliver BEE Phase 2. With the final interface agreement to be approved in consultation with the Section 73 Officer and the Monitoring Officer.

(6) Authorise Director of Law, Governance and Audit to take all necessary steps to give effect to the above recommendations including (but not limited to) the negotiation and execution of all necessary legal documents as required to deliver BEE Phase 2 and enter into any relevant agreement with HS2 and the Department for Transport.

Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference are required to vote in favour of any recommendation/proposition for it to become decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution].

1. Executive Summary 1.1 This report sets out the case for investment in the Birmingham Eastside Extension (BEE) Metro project to complete delivery of the remainder of the BEE scheme, specifically Sections 3 and 4, following the decision by WMCA Board in November 2023 to approve delivery of an interim scheme. The outcome of the Business Case refresh shows that this is a very high value for money investment, which delivers substantial benefits aligned with both WMCA and Birmingham City Council Strategic objectives.

2. Matters for Consideration 2.1 The Birmingham Eastside Extension scheme will provide connectivity to the new HS2 station at Curzon Street and support the wider regeneration of the Eastside and Digbeth areas of the city. The scheme involves the construction of 1.7km of both on street and off-street twin-tracked tramway and includes a major urban realm scheme, designed and delivered focusing upon Digbeth High Street.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Change RequestAppendix 1 683 KB Download
PDF
Benefits and EvaluationAppendix 2 162 KB Download
PDF
Health and Equity AssessmentAppendix 3 125 KB Download
PDF
Birmingham Eastside Extension Sections 3 & 4 Full Business Case UpdateReport 725 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 27 attended
RP
Richard ParkerChair, present
ST
Councillor Sharon ThompsonVice-Chair, present
AA
Councillor Adrian AndrewCommittee Member, present
PB
Councillor Paul BradleyCommittee Member, present
KC
Councillor Kerrie CarmichaelCommittee Member, present
LC
Councillor Lee CarterNon-Constituent Member, apologies
JC
Councillor John CottonCommittee Member, present
IC
Councillor Ian CourtsCommittee Member, present
ID
Councillor Ian DavisonNon-Constituent Member, apologies
CD
Councillor Carol DeanNon-Constituent Member, absent
GD
Councillor George DugginsCommittee Member, present
SE
Councillor Steve EvansCommittee Member, present

All 27 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Birmingham Eastside Extension Sections 3 & 4 Full Business Case UpdateThis decision
  2. Birmingham Eastside ExtensionNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies