West Midlands Combined Authority
Overview & Scrutiny Committee, Monday 3 November 2025 at 10.00am

Quarter 2 Performance Monitoring against the Annual Business Plan

Agreed Scrutiny 2 papers

AI summaryWest Midlands Combined Authority scrutiny committee endorses 2025/26 Annual Business Plan monitoring approach and requests Unit4 procurement system update before year-end.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedMembers endorsed Q2 monitoring approach and assurances
MoneyNot stated
What happens nextUnit4 procurement report dueTo be submitted before end of financial year
Who it affectsWMCA performance monitoringFuture reports to include clearer commentary

What was decided

The committee endorsed the proposed method for monitoring the Annual Business Plan for 2025/26 and the assurances it provided.

A report on the implementation of the new Unit4 procurement system will be submitted to the committee before the end of the financial year.

Officers committed to improving the level of detail and clearer, more informative commentary in future quarterly reports.

Why

Members wanted sufficient detail to support effective scrutiny, particularly around performance indicators and risk assessments, to enable objective assessment of performance.

Several performance indicators showed delays, including risk management (PI 87), financial management training enhancements (PI 94), and EVCATS delivery (PI 86), while procurement efficiencies (PI 93) and the Affordable and Social Housing Plan work were progressing. Report P4, P5, P6

Contributions from Cecilie Booth helped frame the discussion on what level of detail would reassure members and allow tracking of progress.

What happens next

Officers will include clearer, more informative commentary in future reports to support objective scrutiny.

A report on the new Unit4 procurement system implementation will be brought to the committee before the end of the financial year.

An update will be provided in the next quarterly report to help reassure members and track progress.

Options considered

  • Chosen: Endorse the proposed method for monitoring the 2025/26 Annual Business Plan and assurances provided
  • Chosen: Request a report on Unit4 procurement system implementation before end of financial year. To support effective scrutiny of procurement improvements
  • Chosen: Ask officers to provide clearer, more informative commentary in future quarterly reports. Members wanted to assess performance objectively

Implications

  • Risk: Corporate risk management activity (PI 87) has been delayed due to prioritisation of Fraud Risk Assessment work; Strategic Risk Register and quarterly reporting approach remain in development. Report P5
  • Other: The new Unit4 procurement system was signed in August 2025, with eSourcing module live and Contract Management and Supplier Relationship Management modules still being implemented. Report P4
  • Other: EVCATS delivery (PI 86) is slower than planned due to ongoing legal negotiations and the need to secure site ownership before onboarding an investor, though year-end targets remain on track. Report P6

Who and where

  • WMCA Procurement team and external partners Report P4
  • Homes for the West Midlands Limited Liability Partnership (HFWM LLP) Report P4
  • Oldbury EVCATS site and prospective tenants Report P6
  • WMCA Executive Board and Audit Committee Report P5

Timeline

  • August 2025: New Unit4 procurement system was signed; eSourcing module went live. Report P4
  • October 2025: Revised Strategic Risk Register proposal scheduled for Executive Board approval. Report P5
  • November 2025: Audit Committee to review the Strategic Risk Register approach. Report P5
  • 2025/26 year-end: Procurement Strategy rollout (PI 97) and Unit4 system full implementation expected to be completed. Report P4, P5
  • 2026-2036: Shared Affordable Homes Programme (SAHP) period; ASH Plan development to commence once regional SAHP work is further advanced. Report P4

Plain English for the jargon

  • EVCATS: Electric Vehicle Charging Across The Shire, a project to deliver EV charging infrastructure.
  • FBC: Full Business Case.
  • SAHP: Shared Affordable Homes Programme.
  • ASH Plan: Affordable Social Housing Plan.
  • HFWM LLP: Homes for the West Midlands Limited Liability Partnership.
  • RAG rating: Red, Amber, Green status rating used to track performance.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

It was agreed that an update would be provided in the next quarterly report to help reassure members and track progress. With contributions from Cecilie Booth, members discussed the level of sufficient detail to support effective scrutiny, particularly around performance indicators and risk assessments, and asked that consideration be made to clearer, more informative commentary in future reports to enable members to assess performance objectively. Officers acknowledged the feedback and committed to improving the level of detail and assurance in future updates. Resolved (1) The proposed method for monitoring the Annual Business Plan for 2025/26 and the assurances it provided be endorsed. (2) A report on the implementation of the new Unit4 procurement system to be submitted to the committee before the end of the financial year.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Overview & Scrutiny Committee

Appendix 1

RAG rating by each quarter and month (2025/26) Appendix 2

Q2 performance and mitigation commentary (2025/26)

PI PI Description Performance Mitigation Commentary No Rating 93 Continue to look for efficiencies Before the new Unit4 procurement system was signed in August 2025, the previous across the source to pay solution was not fully meeting the needs of the Procurement team. The new system is process to deliver benefits for being rolled out in stages. The eSourcing module is already live and being used for all the organisation and external new procurement activity, while the remaining modules for Contract Management and partners. Supplier Relationship Management are being implemented and integrated. Although the system is not yet fully operational, the project is on track for completion by year- end and will support improved efficiency in procurement and financial processes. 100 Implement the Affordable & Work is currently focused on establishing a regional approach to the Social & Social Housing Plan to meet Affordable Homes Programme (SAHP) 2026–2036, delivering the Collaborative proposed regional targets. Partnering Agreement with Homes for the West Midlands Limited Liability Partnership (HFWM LLP), which supports the delivery of affordable housing across the region, and progressing a new social housing funding opportunity. Development of the Affordable Social Housing (ASH) Plan will commence once the regional SAHP work is further advanced. Risks from this milestone delay are low, as strong progress continues across other workstreams, with record levels of social rent delivery announced by the Mayor.

97 Develop, draft, approve and The milestone remains on track to be delivered by year-end, and the delays are rollout an organisational assessed as having minimal risk impact (resource, political, financial, reputational). Procurement Strategy. PI PI Description Performance Mitigation Commentary No Rating 87 Embed consistent and effective Delivery of Corporate Risk Management activity has been delayed due to risk management. prioritisation of the Fraud Risk Assessment (part of the Integrated Settlement) and development of the new Strategic Risk Register and quarterly reporting approach. A draft register was considered by the Executive Board in August, with a revised proposal scheduled for Board approval in October and Audit Committee review in November. Engagement with Governance Panels will follow once the approach is agreed. We remain confident that this PI will be delivered by year-end, with the exception of the Compliance Risk Assurance activity, which has been deprioritised. 94 Deliver and implement This indicator relates to enhancements in how financial information is shared with enhancements to our training project managers and other stakeholders to improve value, rather than to address offer and financial management gaps in existing provision. Delivery of this indicator has been delayed but remains on information. track for completion within this financial year, with no significant risks identified. Financial information continues to be provided through established channels, ensuring that data remains available to support decision-making. Although the delay is regrettable, it is a timing issue only, and work is expected to accelerate in the coming months.

86 Further the delivery of EVCATS Progress on EVCATS delivery has been slower than planned due to ongoing legal and align this with the Full negotiations for key sites and the need to secure site ownership before onboarding an Business Case (FBC). investor. Work continues on finalising legal agreements for the Oldbury site and first tenants, while retailer and Charge Point Operator selections are underway. Private investor activity will resume once additional sites are secured. Despite these delays, the project remains on track to meet its year-end delivery targets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q2 ABP AppendicesReport 72 KB DownloadRead as text
PDF
Quarter 2 Performance Monitoring against the Annual Business PlanReport 193 KB Download

At this meeting

Whole meeting

Who was there

10 of 14 attended
AB
Councillor Andrew BurrowChair, present
VW
Councillor Vera WatersVice-Chair, present
KA
Councillor Keith ArcherCommittee Member - Voting, present
PB
Councillor Philip BatemanCommittee Member - Voting, present
IK
Councillor Ian KettleCommittee Member - Voting, present
GL
Councillor Gavin LloydCommittee Member - Voting, present, as expected, virtual
EM
Councillor Ewan MackeyCommittee Member - Voting, present
HQ
Councillor Hendrina QuinnenCommittee Member - Voting, present
JS
Councillor Jamie ScottCommittee Member - Voting, present
KS
Councillor Kulwant Singh UppalCommittee Member - Voting, apologies
JB
Councillor Jo BarkerCommittee Member - Non-Voting, present, as expected, virtual
WB
Councillor William BoydCommittee Member - Non-Voting, absent

All 14 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Quarter 2 Performance Monitoring against the Annual Business PlanThis decision
  2. Appendix 2 to Quarterly Report -Performance on Devolved Housing & Land Funds -DashboardsNoted

More from West Midlands Combined Authority Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Feb 2026 WMCA Reserves Policy(1) A briefing note on the use of reserve and associated costs for maintaining and developing 16 Summer Lane, includi... Decided Open
16 Feb 2026 Air Quality Programme Update - Presentation(1) The Head of Environment provide the committee with the research undertaken by the University of Birmingham on the... Decided Open
16 Feb 2026 Q3 Performance monitoring against the Annual Business Plan(1) The Chair of the Overview & Scrutiny Committee write to the Chair of the Transport Delivery Overview & Scrutiny C... Decided Open
16 Feb 2026 Work ProgrammeThe work programme be noted. Noted Open