AI summaryWMCA Board adopts Rosewell Review systems and process recommendations, agrees £457.6m firm and £778.6m provisional Category 1 transport capital allocations, and ring-fences £50m for project development.
Written from the decision and the officer reportPDF Pro
OutcomeNotedPlus Category 1 firm and provisional allocations
Money£50m ring-fenced for Category 1 developmentSubject to Single Assurance Framework and normal decision-making
What happens nextLonger-term implementation plan to be developedIncluding Category 2b-5 programme approach
Who it affectsNot stated
What was decided
The Board agreed five principles to improve systems and processes for transport capital investment and a short-term action plan covering programme governance, the gateway process, prioritisation, and use of development funding for projects in Category 2b to 5. Report P34, P35
Within Category 1 schemes, the Board noted previous commitments of £321.7m, agreed proposed firm capital funding allocations totalling £457.6m, and agreed proposed provisional allocations totalling £778.6m, where further work will refine precise allocations. Report P21
The Board approved ring-fencing £50m of Transport for City Regions capital for critical development activity against specific itemised Category 1 schemes, and endorsed that Local Network Improvement Plans and highways maintenance allocations need not be subject to standard Single Assurance Framework assurance processes.
Why
The Rosewell Review sets out recommendations to improve systems and processes for transport capital investment, including longer-term strategy, streamlined assurance, two-stage funding, programme-level budget management, and a clearer prioritisation approach. Report P23, P34, P35, P36, P37, P38
The recommended approach was developed with local authority partners through regular transport and finance forums and is intended to bring maximum benefits through the emerging Transport for City Regions programme. Report 11.1, P28
Capital investment in transport is a key enabler of inclusive growth, supporting access to jobs and skills, affordable and safe places, health and wellbeing, and climate resilience, and aligns with the West Midlands Local Transport Plan. Report 9.5, 9.6
What happens next
Develop a longer-term implementation plan for the wider Rosewell Review recommendations, including programme management, gateways, budget management, business case content, funding and finance, and resourcing. Report P34, P35, P36, P37, P38
Undertake further work to refine precise allocations for the £778.6m provisional Category 1 schemes.
All projects continue to follow the Single Assurance Framework process with full programme assurance and appraisal review prior to decision, and individual projects will be subject to equality assessments. Report 9.1
The money
£321.7m Previous commitments agreed by WMCA Board for Category 1 schemes
£457.6m Proposed firm capital funding allocations for Category 1 schemes
£778.6m Proposed provisional allocations for Category 1 schemes, subject to refinement
£50m Transport for City Regions capital ring-fenced for development on Category 1 schemes
£862.3m Category 2b projects total capital Report P30
£1.242bn Category 3 projects total capital Report P31
£45.1m Category 4 projects total capital Report P32
£1.668bn Category 5 projects total capital Report P33
Implications
Financial: The Board committed to firm and provisional Category 1 capital allocations, plus a £50m ring-fenced development pot from Transport for City Regions, with any allocations forming part of the final budget rather than additional funding.
Legal: Legal services will provide Funding Agreements and support legal work arising from the report, including implementation of the Rosewell recommendations in Appendix D. Report 8.5, 8.7
Equalities: Individual projects will be subject to equality assessments; temporary infrastructure must meet adequate accessibility requirements during construction. A Health and Equity Impact Assessment was completed on the Rosewell Review recommendations. Report P24
Risk: No significant new risks are introduced; risks are managed in accordance with WMCA and local authority processes. Report 10.1
Other: Capital investment supports inclusive growth fundamentals including access to jobs, affordable and safe places, health and wellbeing, and climate resilience, and Delivery Teams will apply the Inclusive Growth Implementation Toolkit to each programme element. Report 9.5, 9.6
Who and where
Local authorities receiving Local Network Improvement Plans and highways maintenance allocations
WMCA Delivery Teams and Transport for West Midlands Report 9.5, 9.6
Project promoters across the West Midlands, including Birmingham, Coventry, Sandwell, Solihull, Dudley, Walsall and Wolverhampton councils Report P29, P30, P31, P32, P33
Disabled members of the public using temporary infrastructure during construction
Timeline
May 2025: Previous WMCA Board paper on City Region Sustainable Transport Settlement Review Report P26
July 2025: Department for Transport published Transport for City Regions Guidance Report P28
November 2025: Previous WMCA Board paper on Transport Capital Investment Programme Report P27
Plain English for the jargon
SAF: Single Assurance Framework, the WMCA's process for assuring projects before funding decisions
SOC/OBC/FBC: Strategic Outline Case, Outline Business Case, and Final Business Case, the staged business case documents for transport projects
LNIP: Local Network Improvement Plan, funding for local transport improvements
TCR: Transport for City Regions, the government's devolved transport funding programme
WMLTP: West Midlands Local Transport Plan, the regional transport strategy
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
(1) The work of the Rosewell Review, including its proposals regarding future transport funding (Objective 3 of the review) and its proposals to improve systems and processes regarding the development and delivery of major capital programmes (Objective 4 of the review), was noted. (2) The five principles to improve systems and processes for transport capital investment, and development of a longer-term implementation plan for the wider Rosewell Review recommendations, were agreed. (3) The short-term action plan to develop further detail on the programme approach for projects in Category 2b - 5: programme governance, gateway process, prioritisation of projects and use of development funding was agreed. (4) Within the Category 1 schemes: (a) the previous commitments agreed by the WMCA Board totalling £321.7m were noted. (b) the proposed firm capital funding allocations totalling £457.6m were agreed. (c) the proposed provisional allocations totalling £778.6m, where further work would be undertaken to refine precise allocations, were agreed. (5) That a sum of £50m Transport for City Regions capital was ring-fenced to allow critical development activity to take place against specific itemised Category 1 schemes (totalling £778.6m), was approved subject to: (a) the availability of allocations being subject to the WMCA’s normal decision-making process and scheme of delegation, including adherence to the Single Assurance Framework where necessary. (b) any allocations to projects constituting a part of the final budget (not in addition to). (6) That the following programmes need not be subject to the standard Single Assurance Framework assurance processes as these were over-arching programme allocations be endorsed: (a) Local Network Improvement Plans to local authorities and the WMCA. (b) highways maintenance allocations to relevant local authorities.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title: Rosewell Review / Transport for City Regions
Responsible Director: Sandeep Shingadia, Executive Director of Transport
Report author: Carl Beet, Head of Transport Strategy and Planning
Key Decision? Yes
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
(If Yes – please contact the Member Relationship Manager to manage this process)
Recommendations (1) To note the work of the Rosewell Review including its proposals regarding future transport funding (Objective 3 of the review) and its proposals to improve systems and processes regarding the development and delivery of major capital programmes (Objective 4 of the review).
(2) To agree the 5 principles to improve systems and processes for transport capital investment (para 2.26); and development of a longer-term implementation plan for the wider Rosewell Review recommendations.
(3) To agree to the short-term action plan to develop further detail on the programme approach for projects in Cat 2b - 5; programme governance; gateway process; prioritisation of projects and use of development funding (as set out in para 2.30).
(4) Within the Category 1 schemes detailed in Paragraph 2.19:
a) Note the previous commitments agreed by Board totalling £321.7m.
b) Agree to the proposed firm capital funding allocations totalling £457.6m.
c) Agree to the proposed provisional allocations totalling £778.6m, where further work will be undertaken to refine precise allocations. (5) Approve that a sum of £50m TCR capital is ring-fenced to allow critical development activity to take place against specific itemised Category 1 schemes (totalling £778.6m), as detailed in Section 2.19, subject to:
a) Availability of allocations being subject to WMCA’s normal decision-making process and scheme of delegation, including adherence to SAF where necessary..
b) Any allocations to projects constituting a part of the final budget (not in addition to).
(6) Endorse that the following programmes need not be subject to the standard Single Assurance Framework assurance processes as these are overarching programme allocations:
(a) Local Network Improvement Plans to Local Authorities and WMCA.
(b) Highways Maintenance allocations to relevant Local Authorities.
Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference are required to vote in favour of any recommendation/proposition for it to become decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution].
1. Executive Summary 1.1 The Rosewell Review was commissioned by the Mayor of the West Midlands to drive a step-change in the delivery of major infrastructure investment, with a particular focus on transport, to spur economic growth. The review has been led by the experienced economist Bridget Rosewell and is supported by political oversight and steering groups that include significant representation from local authorities.
1.2The review has been framed by four objectives: first, to develop a clear investment prospectus for the region (completed); second, to assess the range of existing and planned capital programmes; third, to create robust funding and financing recommendations for future transport investment under the Transport for City Regions programme; and fourth, to examine and improve current systems and processes associated with project delivery. These objectives ensure that all stages of investment, from conception to delivery, are thoroughly evaluated and strategically aligned with regional goals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.