Housing Multi-Year Integrated Settlement Programme Business Case and Change Request to the 2025/26 Housing Integrated Settlement Programme Business Case
ApprovedCommittee1 paper
AI summaryWMCA Board approves £208m housing and regeneration funding programme targeting 5,464 new homes across the West Midlands from 1st April 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme Business Case and Change Request both approved
Money£208m total£175m NHDF plus £33m BIL Fund
What happens nextFunding from 1st April 2026Subject to MHCLG funding terms being agreed
Who it affectsWest MidlandsConstituent and non-constituent local authority areas
What was decided
The Board approved the Housing Multi-Year Integrated Programme Business Case, which includes a £175 million allocation of National Housing Delivery Fund between 2026/27 and 2029/30, alongside enhanced intervention rates. Report P9, 1.3
The Board approved the Change Request to the 2025/26 Housing Integrated Settlement Programme Business Case for the final £33 million allocation of Brownfield Infrastructure and Land Fund in 2026/27. Report P9, 1.4
Authority was delegated to the Director of Commercial and Investment, in consultation with the Section 73 Officer, to convert up to 10% of capital funding to revenue, and to finalise funding terms with the Ministry of Housing, Communities and Local Government. Report P9, P84
Why
Housing is recognised as a foundation for improving residents' quality of life and a key driver of regeneration and placemaking investment across the West Midlands. Report 2.1, 2.2
Together the Programme Business Case and Change Request represent £208m of devolved grant funding and target unlocking an estimated 5,464 homes. Report 1.5, 7.7
Using a Standard Delivery approach across the programmes ensures processes are straightforward and can be implemented at pace ahead of the 2026/27 financial year. Report 4.3, 3.5
What happens next
The Director of Commercial and Investment will finalise and formally agree the funding terms with the Ministry of Housing, Communities and Local Government. Report P9, 2.21
Each grant allocation will be subject to individual project cases submitted through WMCA's Single Assurance Framework and formal approval under WMCA governance. Report 2.11
Up to 10% of capital funding (up to £20.8m) may be transferred to revenue to resource programme delivery, assurance, evaluation and pre-development support for local authorities. Report 1.6, 3.7
The money
£175m National Housing Delivery Fund allocation between 2026/27 and 2029/30 Report P9, 1.3
£33m Final Brownfield Infrastructure and Land Fund allocation in 2026/27 Report P12, 2.22
£208m Combined devolved grant funding under the PBC and Change Request Report 1.5
£20.8m Up to 10% of capital funding potentially converted to revenue
£187.2m MYIS capital funding element after revenue adjustment (£157.5m NHD + £29.7m BIL) Report P93
£157,500,000 Total NHD Fund capital allocation across the multi-year period Report P90
£29.7mm Final year of BIL Fund in 2026/27 Report P91
Options considered
Chosen: Split the National Housing Delivery Fund into two elements: Regeneration (£50,000 per home average) and Standard Delivery (£25,000 per home average). Builds on the successful 2025/26 Integrated Settlement approach and allows higher intervention for schemes with viability constraints Report 3.5, 2.14
Chosen: Continue managing the Brownfield Infrastructure and Land Fund using existing review and approval processes from the 2025/26 PBC. Existing processes and resources have been effective throughout 2025/26 Report 3.6, 2.22, 2.23
Chosen: Apply the Inclusive Growth Implementation Toolkit to all grant funding applications. Standard assurance process to identify and maximise inclusive growth outcomes Report P73, 9.13
Implications
Financial: Up to 10% of capital funding (£20.8m) may be converted to revenue to resource programme delivery, with £187.2m remaining as capital across the multi-year period. Report P88
Legal: WMCA has power to accept and deploy the National Housing Delivery Fund under Section 113A(1)(a) of the Local Democracy, Economic Development and Construction Act 2009. Report 8.2
Equalities: Health and Equity Impact Assessments identified that residents with protected characteristics, especially ethnic minorities, women, disabled people and those on low incomes, are overrepresented in housing need across the West Midlands. Report 9.8
Climate: Officers will work with funding applicants to promote efficient and future-proof construction methods and housing design, taking an adaptable approach to environmental considerations. Report P76
Risk: Following independent Appraisal, there are no outstanding red-rated risks for either the Change Request or the Programme Business Case. Report P105, 10.1
Other: The programme targets at least 20% affordable housing and a minimum Benefit Cost Ratio of 1.0 (Standard Delivery) to 1.5 (Regeneration). Report P74, 2.18, P42, P43
Who and where
Constituent and non-constituent local authorities across the WMCA geography Report P124
West Midlands residents, including those on low incomes and with protected characteristics facing housing need Report 9.10
Private sector developers, investors and housing providers building the regional housing pipeline Report P78, 9.12
Timeline
1st April 2026: WMCA enters the multi-year settlement period, with NHDF and the final BIL allocation available Report 2.9, P10
31st March 2027: Target of 481 homes unlocked and 243 new homes started Report P47, P48
31st March 2029: All Brownfield Infrastructure and Land Fund must be transacted and spent by this date Report 2.26
31st March 2030: End of the multi-year settlement period; target of 4,264 homes unlocked, 2,772 starts and 896 completions Report 2.9, P47, P48, 10.1
Plain English for the jargon
NHDF: National Housing Delivery Fund: devolved capital funding for housing and regeneration
BIL Fund: Brownfield Infrastructure and Land Fund: devolved funding to unlock brownfield land for housing
PBC: Programme Business Case: the document setting out how a funding programme will be delivered
BCR: Benefit Cost Ratio: a threshold used to assess value for money of interventions
MYIS: Multi-Year Integrated Settlement: a four-year funding settlement from government running 2026/27 to 2029/30
MHCLG: Ministry of Housing, Communities and Local Government
WMCA: West Midlands Combined Authority
Single Assurance Framework: WMCA's process for reviewing and approving project-level funding applications
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
(1) The Housing Multi-Year integrated programme business case, which included a £175m allocation of National Housing Delivery Fund between 2026/27 and 2029/30, alongside enhanced intervention rates was approved. (2) The Director of Commercial & Investment was authorised to finalise and formally agree the funding terms with the Ministry of Housing, Communities & Local Government. (3) The change request for the 2025/26 Housing Integrated Settlement programme business case, as previously agreed by WMCA Board, for the final £33m allocation of Brownfield Infrastructure & Land Fund from the Government in 2026/27 was approved. (4) Authority was delegated to the Director of Commercial & Investment, in consultation with the Section 73 Officer, to determine the transition of capital grant to revenue funding up to a maximum of 10% of the overall programme value.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Meeting date: 13 March 2026 Housing Multi-Year Integrated Settlement Programme Business Case and Change Request to the 2025/26 Report title: Housing Integrated Settlement Programme Business Case
Responsible Director: Ian Martin – Director of Commercial & Investment
Lauren Rigby-Hopkins – Business Development & Partnerships Lead [email removed] Report author: Rob Lamond – Head of Strategy & Analysis, Housing, Property & Regeneration [email removed]
Key Decision? Yes
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
(If Yes – please contact the Member Relationship Manager to manage this process)
Recommendations (1) Approve the Housing Multi Year Integrated Programme Business Case, which includes a £175 million allocation of National Housing Delivery Fund between 2026/27 and 2029/30, alongside enhanced intervention rates set out in Section 2.14 of this report. (2) Authorise the Director of Commercial & Investment to finalise and formally agree the funding terms with the Ministry of Housing, Communities & Local Government. (3) Approve the Change Request for the 2025/26 Housing Integrated Settlement Programme Business Case, as previously agreed by WMCA Board, for the final £33 million allocation of Brownfield Infrastructure & Land Fund from Central Government in 2026/27. (4) Delegate authority to the Director of Commercial & Investment in consultation with the Section 73 Officer, to determine the transition of capital grant to revenue funding up to a maximum of 10% of the overall programme value in line with Section 7.0 of the report. Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference are required to vote in favour of any recommendation/proposition for it to become decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution].
1. Executive Summary 1.1 From 1st April 2026, WMCA will be required to deliver additional devolved funding allocations for housing and regeneration in the West Midlands, including:
A) £175m of National Housing Delivery Fund (NHDF) over 4 years
B) £33m of Brownfield Infrastructure & Land (BIL) Fund in 2026/27.
1.2To effectively manage these funding programmes, WMCA have developed a Programme Business Case and Change Request which sets out the rationale and methodology for delivering these funds within the terms and conditions set by the Ministry of Housing, Communities & Local Government (MHCLG).
1.3This report seeks formal approval from WMCA Board for the Housing Multi-Year Integrated Settlement Programme Business Case (PBC), which outlines the process for managing a £175m allocation from the National Housing Delivery Fund between 2026/27 and 2029/30.
1.4Additionally, WMCA Board are asked to formally approve a Change Request to the existing Housing Integrated Settlement Programme Business Case for 2025/26, which will enable WMCA to utilise previously agreed management and delivery processes for the final £33m allocation of the £100m Brownfield Infrastructure & Land Fund. This approach will effectively extend existing approved arrangements to cover the 26/27 Financial Year.
1.5Both the Programme Business Case and Change Request combined represent £208m of devolved grant funding and will target unlocking an estimated 5,464 homes.
1.6The programmes set out within this report will also enable the transfer of up to 10% of capital funding to revenue which will resource programme delivery and the processes for administering grant funding, whilst also supporting Local Authorities with the pre- development costs and feasibility work associated with priority housing sites in the regional pipeline.
2. Matters for Consideration
Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Multi-Year Integrated Settlement Programme Business Case and Change Request to the 2025/26 Housing Integrated Settlement Programme Business CaseReport
7Housing Multi-Year Integrated Settlement Programme Business Case and Change Request to the 2025/26 Housing Integrated Settlement Programme Business CaseThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.