West Midlands Combined Authority
WMCA Board, Friday 17 July 2026 at 11.00am

2025/26 Financial Outturn and Capital Budget Update

Noted Committee 6 papers

AI summaryWest Midlands Combined Authority Board approved the 2025/26 financial outturn, including a £7.0m revenue underspend and £463.8m capital delivery, alongside £48.0m of 2027/28 highways funding and £139.80m of local network improvement plan allocations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProvisional figures, subject to external audit
MoneyMultiple amounts approvedIncludes £21.3m General Reserve, £48.0m highways, £139.80m LNIP
What happens nextExternal audit concludes NovemberUnaudited accounts deadline was 30 June 2026
Who it affectsWMCA and seven constituent authoritiesPlus programme recipients across the region

What was decided

The Board approved transferring the 2025/26 revenue underspend to the General Reserve, bringing the anticipated balance to £21.3m, and approved transfers to earmarked reserves totalling £19.4m. Report 3.13, 3.14

The Board approved £48.0m of 2027/28 Baseline Highways Maintenance funding, £139.80m of Local Network Improvement Plan allocations for 2027 to 2032, and £17.2m of 2026/27 highways funding for Birmingham City Council. Report 3.50, 3.59

The Board approved £11.3m of capital budget amendments for the Wednesbury to Brierley Hill Metro Extension and Dudley Interchange projects, and approved the updated capital programme for 2026/27 to 2030/31. Report 3.64, 3.70

Why

The provisional 2025/26 revenue outturn showed a £7.0m underspend, £1.2m lower than forecast at Quarter 3, with the WMCA ending the year in a strong financial position and total reserves rising from £293.1m to £370.3m. Report 2.3, 2.5

Capital delivery of £463.8m against a £653.5m budget represented a 71% delivery rate, an improvement on the previous two years, and the financial position supported strategic investments in transport, housing, and energy. Report 3.17, 3.19

The highways and LNIP allocations were needed to allow local authorities sufficient time to plan their programmes and to give effect to the Transport for City Regions settlement confirmed by Government in June 2025. Report 3.48, 3.51

What happens next

The external audit of the Statement of Accounts is expected to conclude in November, after which the provisional outturn may be revised. Report 2.2

Delegated authorities were granted to officers to award grants for the Warm Homes Social Homes programme, to approve the Changing Futures programme following Single Assurance Framework completion, and to commit up to £6.3m of WMCA funding for the Cradle to Career programme. Report 3.31, 3.38, 3.43

A procurement process for a fund manager for the Collective and Residential Investment Funds is to be undertaken by the Commercial and Investment Activities Director. Report 3.77, 3.78

The money

  • £7.0m Revenue underspend for 2025/26 Report 2.3
  • £21.3m Anticipated General Reserve balance at 31 March 2026 Report 3.14
  • £19.4m Total transfers to earmarked reserves Report P11
  • £4.0m Release from General Transport Budget Risk Reserve for external advice Report 3.11
  • £0.4m Use from General Transport Budget Risk Reserve for Passenger Incentives Programme Report 3.12
  • £23m HS2 Ltd compensation payment for Birmingham Eastside Metro extension Report 3.34, 3.35
  • £6.3m WMCA contribution to the Cradle to Career programme Report 3.43
  • £48.0m First year of 2027/28 Baseline Highways Maintenance funding Report 3.50
  • £17.2m 2026/27 Highways Maintenance funding for Birmingham City Council
  • £139.80m Total LNIP allocations for April 2027 to March 2032 Report 3.59
  • £11.3m Capital budget increase for Wednesbury to Brierley Hill and Dudley Interchange Report 3.63, 3.64
  • £463.8m Capital delivery for 2025/26 Report 3.17
  • £48.2m Treasury Management investment income for 2025/26 Report 3.5, 3.23
  • £684.6m Integrated Settlement grant for 2026/27 Report 3.29
  • £300m Combined CIF and RIF real estate fund value Report 3.78

Options considered

  • Chosen: Transfer full £9.0m underspend on bus network support to the General Transport Risk Reserve. Further support will be required from 2026/27 during transition to franchising, so no surplus funding is created Report 3.8
  • Chosen: Cover the £11.3m capital cost pressures through WMCA resources. Redistributing from TfWM schemes and applying LNIP allocation to avoid impacting Local Authority capital programmes Report 3.69
  • Chosen: Maintain existing formula for CRSTS revenue and LNIP funding allocations. Recommended by Strategic Transport Officers: 25% to WMCA, 75% apportioned among constituent members by population Report 3.53

Implications

  • Financial: Total revenue reserves increased from £293.1m to £370.3m at 31 March 2026, with the General Reserve rising to £21.3m, approximately 3.6% of the 2026/27 net budget. Report 2.5, 3.14, 3.15
  • Financial: Net investments increased by £143.7m to £375.5m; no new borrowing was undertaken in 2025/26 and borrowing fell to £544.1m following scheduled repayments and early redemption of PWLB loans. Report 3.21, 3.22
  • Risk: The outturn remains provisional pending the external audit expected to conclude in November, and the figures are management accounts used during the year. Report 2.2
  • Legal: WMCA is under a statutory duty to maintain a balanced budget; failure to comply could result in government intervention, clawback of funds, or adverse audit findings. Report 6.5
  • Equalities: The report states there are no equalities implications arising from it.
  • Staffing: Proposals include £0.2m to support short-term staffing capacity within Communications and Programme Assurance teams. Report P44

Who and where

  • West Midlands Combined Authority and its seven constituent local authorities Report 3.50, 3.53
  • Birmingham City Council as recipient of £17.2m highways maintenance funding for 2026/27
  • Bidders for the Warm Homes Plan Social Homes programme Report 3.32
  • Birmingham, Sandwell and Wolverhampton residents supported by the Changing Futures programme Report 3.37
  • Children, young people and families in six communities served by the Cradle to Career programme Report 3.39, 3.40

Timeline

  • 1 April 2026: Start of 2026/27 financial year; Integrated Settlement grant period begins Report 3.29
  • 30 June 2026: Statutory deadline for publication of unaudited accounts Report 2.2
  • November 2026: External audit of Statement of Accounts expected to conclude Report 2.2
  • 31 March 2028: Deadline for full spend of the new £23.0m Social Homes retrofit grant Report 3.30
  • 31 March 2032: End of the five-year LNIP and Transport for City Regions period Report 3.48, 3.59

Plain English for the jargon

  • WMCA: West Midlands Combined Authority
  • CRSTS: City Region Sustainable Transport Settlement
  • TCR: Transport for City Regions
  • LNIP: Local Network Improvement Plan
  • Integrated Settlement: A multi-year government grant combining several funding streams into a single allocation for the region
  • BSIP: Bus Service Improvement Plan
  • SAF: Single Assurance Framework, the WMCA's process for approving projects and expenditure
  • ENCTS: English National Concessionary Travel Scheme
  • CIF and RIF: Collective Investment Fund and Residential Investment Fund
  • PWLB: Public Works Loan Board
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

(1) The outturn position for both revenue and capital, including how this compared with the quarter 3 position previously reported to the WMCA Board on 13 March 2026 was noted. (2) It was noted that the outturn position was provisional and would remain subject to change, pending completion of the external audit review. (3) The intended transfer of the 2025/26 residual underspend on the revenue programme to the General Reserve was approved, and the anticipated balance at 31 March 2026 of £21.3m was noted. (4) The transfers to earmarked reserves, totalling £19.4m, was approved. (5) The release of £4.0m from the General Transport Budget Risk Reserve to continue funding external advice for priority activity was approved, noting that this represented the continuation of work initiated in 2025/26 and extending into 2026/27. (6) The use of £0.4m from the General Transport Budget Risk Reserve to fund the final year of the Passenger Incentives Programme was approved. (7) The balances held within Earmarked Reserves, and the alignment of reserves with the Reserves Strategy approved on 13 February 2026 was noted. (8) The Treasury Management Outturn 2025/26 was noted. (9) The new grant awards (both revenue and capital) for the WMCA were noted, and the changes in the Integrated Settlement grant for the multi- year period to March 2029 were noted. (10) Authority was delegated to the Interim Executive Director of Strategy & Policy, in consultation with Section 73 Officer and Monitoring Officer, to award grants required to enable delivery of the Warm Homes Plan funding for Social Homes programme in compliance with the grant conditions. (11) The receipt, terms and treatment of the £23m received by the WMCA from HS2 Ltd, intended to compensate for additional costs incurred by the WMCA in delivering the Birmingham Eastside metro extension, were noted. (12) Authority was delegated to the Interim Executive Director of Policy & Strategy to approve the Changing Futures programme expenditure and associated decisions, following completion of the Single Assurance Framework process. (13) Authority was delegated to the Interim Executive Director of Policy & Strategy, in conjunction with the Monitoring Officer and the Section 73 Officer, to secure and commit up to £6.3m of WMCA funding, subject to completion and approval of the Business Justification Case and compliance with the Single Assurance Framework for the Cradle to Career programme. (14) The proposals to fund the Flowtrack Trial - ITS Showcase from previously unapplied legacy grant funding to allow for progression of the project were noted. (15) The first year of Baseline Highways Maintenance funding for 2027/28 within the Transport for City Regions programme of £48.0m was approved. (16) Authority was delegated to the Interim Executive Director of Transport for West Midlands, in consultation with the Section 73 Officer, to agree suitable terms and conditions to apply to 2027/28 Baseline Highways Maintenance funding. (17) The 2026/27 Highways Maintenance funding of £17.2m for Birmingham City Council was approved, subject to the conditions and delegations noted within the report. (18) The detailed Local Network Improvement Plan allocations by authority ...
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Name of Meeting: WMCA Board

Meeting Date: Friday 17 July 2026

Report Title: 2025/26 Financial Outturn and Capital Budget update

Accountable Director: Claire Nye, Chief Finance Officer

Report Author: Beverly Sullivan, Financial Planning & Co- ordination Manager

Key Decision: Yes

Voting Requirements A majority of voting members, including the Mayor, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendation / proposition for it to become a decision of the board.

Report has been considered by: N/A

Recommendations for Approval:

2025/26 Revenue, Capital and Reserves Outturn position

(1) Note the outturn position for both revenue and capital, including how this compares with the Quarter 3 position previously reported to the WMCA Board in March 2026. (2) Note that the outturn position is provisional and will remain subject to change pending completion of the external audit review. (3) Approve the intended transfer of the 2025/26 residual underspend on the revenue programme to the General Reserve and note the anticipated balance at 31 March 2026 of £21.3m. (4) Approve the transfers to earmarked reserves as outlined in paragraphs 2.8 to 2.10 of this report, a total of £19.4m. (5) Approve the release of £4.0m from the General Transport Budget Risk Reserve to continue funding external advice for priority activity, noting that this represents the continuation of work initiated in 2025/26 and extending into 2026/27. (6) Approve the use of £0.4m from the General Transport Budget Risk Reserve to fund the final year of the Passenger Incentives Programme. (7) Note the balances held within Earmarked Reserves (see Appendix 6), and the alignment of reserves with the Reserves Strategy approved in February 2026.

Treasury Management Outturn

(8) Note the Treasury Management Outturn 2025/26 as detailed in paragraphs 2.21 to 2.24 and Appendix 7 of this report. Grants Update

(9) Note the new grant awards (both revenue and capital) for the WMCA and note the changes in the Integrated Settlement grant for the multi- year period to March 2029. (10) Delegate authority to the Interim Executive Director of Strategy & Policy in consultation with Section 73 Officer and Monitoring Officer to award grants required to enable delivery of the Warm Homes Plan funding for Social Homes programme in compliance with the grant conditions, as per paragraphs 4.2 to 4.3. (11) Note the receipt, terms and treatment of the £23m received by WMCA from HS2 intended to compensate for additional costs incurred by WMCA in delivering the BEE Metro Extension, as detailed in paragraphs 4.6 to 4.8. (12) Delegate authority to the Executive Director of Policy & Strategy, to approve the Changing Futures programme expenditure and associated decisions following completion of the SAF process (see paragraphs 4.9 to 4.10). (13) Delegate authority to the Executive Director of Policy & Strategy in conjunction with the Monitoring officer and the Section 73 Officer, to secure and commit up to £6.3m of WMCA funding, subject to completion and approval of the Business Justification Case and compliance with the Single Assurance Framework for the Cradle to Career programme. (see paragraphs 4.11 to 4.15). (14) Note the proposals to fund the Flowtrack Trial - ITS Showcase from previously unapplied legacy grant funding to allow for progression of the project. (paragraph 4.16).

Highways Maintenance

(15) Approve the first year of Baseline Highways Maintenance funding for 2027/28 within the Transport for City Regions programme of £48.0m, as set out at paragraphs 5.1 to 5.8. (16) Delegate authority to the Executive Director for Transport and the WMCA Section 73 Officer to agree suitable terms and conditions to apply to 2027/28 Baseline Highways Maintenance funding. (17) Approve the 2026/27 Highways Maintenance funding of £17.2m for Birmingham City Council, subject to the conditions and delegations noted at paragraphs 5.9 to 5.12.

Local Network Improvement Plan (LNIP)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Financial Outturn and Capital Budget UpdateReport 346 KB DownloadRead as text
PDF
WMCA Consolidated Revenue Full Year SummaryAppendix 1 163 KB Download
PDF
Summary of Movements from Q3 Revenue ForecastAppendix 2 136 KB Download
PDF
Transport for West Midlands Revenue Full Year SummaryAppendix 3 61 KB Download
PDF
WMCA Programme BudgetAppendix 4 258 KB Download
PDF
Mayoral Office Budget PositionAppendix 5 208 KB Download

At this meeting

Whole meeting

Who was there

0 of 29 attended
RP
Richard ParkerChair, expected
SS
Councillor Stephen SimkinsDeputy Chair, expected
NB
Councillor Nicky BarkerCommittee Member, expected
PB
Councillor Paul BradleyCommittee Member, expected
LC
Councillor Lee CarterNon-Constituent Member, expected
GD
Councillor Gary DaleCommittee Member, expected
ID
Councillor Ian DavisonNon-Constituent Member, expected
CD
Councillor Carol DeanNon-Constituent Member, expected
HD
Councillor Heather DelaneyCommittee Member, expected
MD
Councillor Matthew DormerNon-Constituent Member, expected
GD
Councillor George DugginsCommittee Member, expected
SE
Councillor Steve EvansCommittee Member, expected

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. 2025/26 Financial Outturn and Capital Budget UpdateThis decision
  2. West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Noted
  3. Financial Outturn 2017/18Noted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open