Resolved
Council: a) Noted that the selection process for the new school involved the Council putting forward a recommendation to the DfE for the preferred trust, following a rigorous selection process. b) Noted the linked paper considered by Cabinet on 13th September 2022, ‘St John Tiffield property arrangements’ on the use of the St John’s Tiffield Site, St. John’s Road, Tiffield , NN12 8AA for the new school. c) Agreed in principle borrowing of approximately £10,000,000 would be required to make up the shortfall for the cost of building the new school, which was expected to be £23m, with delegated authority to the s151 officer to amend the capital programme once full feasibility works are completed. d) Noted that the remaining cost of the build would be met through capital grant funding received by the Council.
Word for word from the decision West Northamptonshire published for this meeting.