West Northamptonshire Council
Cabinet, Tuesday 11 October 2022 at 6.00pm

Office Optimisation Stage 1 building adaptations budget and disposals

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 11 October 2022. Below is the council's own wording, with the papers it was decided on.

Item86

Resolved

that Cabinet: a) Agree to the proposed new capital budget of £2 million to carry out Stage 1 of the Office Optimisation project and recommend to Council that the Capital budget is amended to reflect the proposed change. b) Authorise the Assistant Director Assets & Environment to procure and award the contracts to deliver the Stage 1 works. c) Authorise the Assistant Director Assets & Environment in consultation with the Executive Director Finance and Cabinet Member for Finance to dispose of the Lodge Road offices, in whole or part, by leasehold or freehold, for the best consideration reasonably obtainable. d) Agree that the Lodge Road offices be vacated by 31st March 2023 in order that the revenue savings and/or capital gains be achieved as quickly as practicable thereafter. REASONS To provide an effective accommodation solution, and best value for the residents of West Northamptonshire in consideration of service operating models and Council objectives. To provide a fit for purpose facility to replace the Lodge Road offices for Council services which enables the wider objective to provide cost effective accommodation. To reduce the Council’s energy use and carbon emissions. To ensure timely delivery of financial improvements ALTERNATIVE OPTIONS CONSIDERED: The choices on the budget open to the Council are as follows. a. Do nothing. This would not enable the closure of Lodge Road to Council services, retain a high level of under-used office space, not contribute to savings goals or the development of a unified ‘one Council’ culture. b. Approve the proposed budget. This would enable the work to proceed and the new Daventry hub to be created. c. Instead seek to purchase or lease office accommodation elsewhere in central Daventry. This is unlikely to provide suitable accommodation and location, and would not optimise use of the Abbey. It would involve new lease rent or purchase costs. Given the time required to deliver the Stage 1 works, procurement will need to commence as soon as possible. For this reason, formal Cabinet authority for procurement is recommended to be granted now, and in advance of Council approval of the budget. It is undesirable for the Council to hold vacant or partially vacant Lodge Road offices any longer than necessary. This incurs costs, leaves the building vulnerable, and does not make any economic or social contribution to Daventry. It is therefore recommended that authority is granted to enable its disposal for the most economically advantageous outcome. However, it is also possible that the building might deliver greater benefits from other Council uses. These will also be tested prior to any decision to dispose. that Cabinet; a) Agreed to the proposed new capital budget of £2 million to carry out Stage 1 of the Office Optimisation project and recommended to Council that the Capital budget is amended to reflect the proposed change. b) Authorised the Assistant Director Assets & Environment to procure and award the contracts to deliver the Stage 1 works. c) Authorised the Assistant Director Assets & Environment in consultation with the Executive Director Finance and Cabinet Member for Finance to dispose of the Lodge Road offices, in whole or part, by ... view the full minutes text for item 86.
Word for word from the decision West Northamptonshire published for this meeting. Source: westnorthants.moderngov.co.uk

Follow this further

Built from West Northamptonshire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Lodge Road closure budget briefing noteReport 63 KB Copy on its way
PDF
Office Optimisation Stage 1 building adaptations budget and disposalsReport 126 KB Copy on its way

More from West Northamptonshire Cabinet

All decisions
MeetingDecisionOutcome
5 May 2026 WNC Waste Collection and Street Cleansing Services from 2028Cabinet: a) Approved the recommendation to commence the processes necessary to bring the delivery of waste collection... Approved Open
5 May 2026 West Northamptonshire Youth Strategy (2026-2030)Cabinet approved the adoption and implementation of the West Northamptonshire Youth Strategy. REASONS The recommended... Approved Open
5 May 2026 Domestic Abuse and Sexual Violence Strategy 2026-2030Cabinet approved the Domestic Abuse and Sexual Violence Strategy 2026-2030. REASONS The Domestic Abuse Act 2021 is a ... Approved Open
5 May 2026 Approval of the proposed process for the completion and submission of the Local SEND Reform PlanDelegate authority to the Director of Children’s Services in consultation with the Section 151 Officer, the Leader of... Approved Open
5 May 2026 Review of the Housing Allocations PolicyCabinet; 1) Approved the adoption and implementation of the proposed Housing Allocation Policy, as set out in Appendi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies