Cabinet, Tuesday 11 November 2025 at 6.00pm

New Public Mortuary

Approved Executive 1 paper

AI summaryWest Northamptonshire Cabinet recommended that the Council approve a capital budget increase to complete and fit out the new public mortuary, with the service intended to go live in March 2026.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedCapital budget increase for completion and fit out
MoneyCapital budget increaseSupports completion, fit out and required payments
What happens nextApproval, completion, then go liveMarch 2026 is the intended go live date
Who it affectsResidents and service partnersBody storage, post mortems and transport services

What was decided

Cabinet recommended that the Council approve an increase in the capital budget for the completion and fit out of the new public mortuary.

Why

As the responsible authority for the Northamptonshire Coroner’s Area, the Council needs sufficient, secure and suitable provision for body storage and post mortems for local residents.

The allocation would enable the Council to meet its construction contract obligations, comply with the law, make required payments and maximise the value of its investment.

It would support delivery of the UHN body storage and transport contract from the agreed start date and entry into contracts with other NHS providers and other public bodies, maximising value for money from the investment and service.

What happens next

The Council is asked to approve the additional capital budget so the project can proceed to completion.

Complete the building works and fit out to enable a go live of the service in March 2026.

Make the required payments and progress contracts for mortuary services with other NHS providers and other public bodies.

Options considered

  • Chosen: Allocate the additional budget and complete the new public mortuary. The project has reached a critical stage, completion of the building works is described as imperative, and the Council must comply with the law and make required payments.

Implications

  • Financial: An increase in the capital budget is recommended to enable completion and fit out of the new public mortuary.
  • Legal: The Council must comply with the law, meet its construction contract obligations and make required payments.
  • Risk: The project has reached a critical stage, and completion of the building works is described as imperative.
  • Financial: The Council wants to maximise the value of its investment and value for money from the service.
  • Other: A new public mortuary is intended for the county, with body storage and transport for KGH and NGH under the UHN contract.
  • Other: The new facility is intended to provide sufficient, secure and suitable body storage and post mortem provision.
  • Other: The additional allocation would support entry into mortuary service contracts with other NHS providers and other public bodies.

Who and where

  • Local residents needing mortuary provision
  • University Hospitals of Northamptonshire, the UHN service partner
  • KGH and NGH, covered by the UHN service
  • Other NHS providers that may enter mortuary service contracts
  • Other public bodies that may enter mortuary service contracts
  • West Northamptonshire Council, as the responsible authority

Timeline

  • 2025-11-11: Cabinet recommended that the Council approve the capital budget increase.
  • the agreed start date: Delivery of the UHN body storage and transport contract is to be supported.
  • March 2026: Go live of the new mortuary service is intended.

Plain English for the jargon

  • UHN: University Hospitals of Northamptonshire
  • Go live: Start of the new mortuary service
  • Northamptonshire Coroner’s Area: The area for which the Council is the responsible authority
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item405

Resolved

Cabinet recommended to Council approval of an increase in the capital budget for the completion of the build and fit out of the new public mortuary. REASONS 1. To enable the Council to make best use of the facilities at the proposed new mortuary to meet the needs of local residents. The Council, as the responsible authority for the Northamptonshire Coroner’s Area, needs to ensure there is sufficient, secure and suitable provision for the storage of bodies and the conduct of post-mortems. 2. To ensure the Council can meet its obligations under the construction contract. 3. To enable the new public mortuary to be completed and so maximise the value of the Council’s investment. 4. To support delivery of the contract with University Hospitals of Northamptonshire (UHN) for body storage and transport service from the agreed start date. 5. To support entry into contracts for the provision of mortuary services with other NHS providers and other public bodies, thereby maximising value for money from the investment and service. ALTERNATIVE OPTIONS: The project has reached a critical stage where, in order to maximise the benefit of the Council’s investment thus far, deliver a new public mortuary for the county and to fulfil the contract with UHN for the provision of a body storage and transport service for KGH and NGH it is imperative that the building works complete. The intention is to enable a ‘go live’ of the service in March 2026. It is therefore concluded that the additional budget should be allocated, so the Council can comply with the law and make required payments, and the project can proceed to completion.
Word for word from the decision West Northamptonshire published for this meeting. Source: westnorthants.moderngov.co.uk

Follow this further

Built from West Northamptonshire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
New Public MortuaryReport 100 KB Copy on its way

More from West Northamptonshire Cabinet

All decisions
MeetingDecisionOutcome
5 May 2026 WNC Waste Collection and Street Cleansing Services from 2028Cabinet: a) Approved the recommendation to commence the processes necessary to bring the delivery of waste collection... Approved Open
5 May 2026 West Northamptonshire Youth Strategy (2026-2030)Cabinet approved the adoption and implementation of the West Northamptonshire Youth Strategy. REASONS The recommended... Approved Open
5 May 2026 Domestic Abuse and Sexual Violence Strategy 2026-2030Cabinet approved the Domestic Abuse and Sexual Violence Strategy 2026-2030. REASONS The Domestic Abuse Act 2021 is a ... Approved Open
5 May 2026 Approval of the proposed process for the completion and submission of the Local SEND Reform PlanDelegate authority to the Director of Children’s Services in consultation with the Section 151 Officer, the Leader of... Approved Open
5 May 2026 Review of the Housing Allocations PolicyCabinet; 1) Approved the adoption and implementation of the proposed Housing Allocation Policy, as set out in Appendi... Approved Open